POTTER N HUGHES (0904-02-050)

Items: 95

County: POTTER
Length: 0.6130 MILES
Highway: N HUGHES
District: AMARILLO
Control Number: 0904-02-050
DBE Goal: 0.0%
Project: BR 2024(903)
Guaranty: $100,000.00
Time: 157 WORKING DAYS
Engineer's Estimate: $5,801,924.40
Date: 03/04/2026 (3 months ago) Changed
Contract Number: 11253009
Type: BRIDGE REPLACEMENT
Project ID: A00188550
Contract Type: Federal
Project Description: REHABILITATE EXISTING OFF-SYSTEM BRIDGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$5,801,924.40
$4,519,471.08
Over/Under Est: -22.1% -$1,282,453.32
$6,120,788.00
Over/Under Est: 5.5% $318,863.60
Amt Left: 35.43% $1,601,316.92
Over/Under Est: 7.06% $409,493.35
Amt Left: 37.44% $1,691,946.67
Delta: -1.48% -$90,629.75
Over/Under Est: 8.44% $489,400.35
Amt Left: 39.2% $1,771,853.67
Delta: -1.29% -$79,907.00
Over/Under Est: 27.35% $1,587,092.10
Amt Left: 63.49% $2,869,545.42
Delta: -17.45% -$1,097,691.75
$7,622,831.70
Over/Under Est: 31.38% $1,820,907.30
Amt Left: 68.67% $3,103,360.62
Delta: -3.16% -$233,815.20

Bid Items & Bid Tabulations

95 Total 0 of 95
POTTER  |  N HUGHES  |  AMARILLO  |  0904-02-050  |  03/04/2026  |  $5,801,924.40  |  BR 2024(903)  |  BRIDGE REPL  |  157 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALTUS CONSTRUCTION LLC
IBCTX, LLC
L A FULLER & SONS CONSTRUCTION, LTD.
RAGLE CONSTRUCTION, INC.
COPPELL CONSTRUCTION CO., INC.
GILVIN-TERRILL, LTD.
REMOV CONC (RIPRAP)
SY 20.000 $30.000 $16.427 $80.000 $64.450 $100.000 $90.000 $350.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 297.000 $15.000 $9.035 $50.000 $7.250 $6.000 $20.000 $55.000
REMOV CONC (RAIL)
LF 2,388.000 $40.000 $19.713 $90.000 $21.400 $40.000 $160.000 $65.000
REMOV CONC (MISC)
SY 5,216.000 $30.000 $66.838 $55.000 $65.300 $100.000 $163.000 $200.000
EMBANK (FNL)(DC)(TY B)
CY 110.000 $40.000 $16.186 $140.000 $72.100 $500.000 $105.000 $255.000
SP MIXES SP-D SAC-A PG70-28
TON 130.000 $190.000 $138.113 $500.000 $356.350 $300.000 $350.000 $650.000
PLANE ASPH CONC PAV(2")
SY 2,545.000 $4.000 $4.380 $10.000 $6.350 $6.100 $10.000 $10.000
REINF CONC SLAB
SF 46,778.000 $40.500 $25.353 $32.000 $45.000 $31.000 $38.000 $40.650
BRIDGE SIDEWALK
SF 13,860.000 $30.000 $10.699 $14.000 $13.500 $14.500 $12.000 $25.000
APPROACH SLAB
CY 22.000 $850.000 $616.039 $1,000.000 $1,061.100 $1,300.000 $1,500.000 $2,000.000
EPOXY WATERPROOF FINISH (TY X)
SF 1,835.000 $10.000 $18.727 $20.000 $19.650 $17.100 $15.000 $17.500
PENETRATING CONCRETE SURFACE TREATMENT
SY 6,130.000 $10.000 $9.801 $10.000 $1.000 $7.700 $17.000 $8.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 1,924.000 $165.000 $61.428 $1.000 $20.550 $30.000 $50.000 $125.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 512.000 $180.000 $176.544 $245.000 $47.600 $100.000 $210.000 $175.000
RIPRAP (MOW STRIP)(4 IN)
CY 12.000 $750.000 $684.487 $1,500.000 $1,008.900 $650.000 $1,000.000 $1,000.000
STR STEEL (MISC NON-BRIDGE)
LB 980.000 $30.000 $16.427 $28.000 $23.150 $19.000 $30.000 $75.000
RAIL (TY T402)
LF 918.000 $180.000 $205.937 $200.000 $227.800 $133.000 $212.000 $275.000
RAIL (TY SSTR)
LF 891.000 $115.000 $77.538 $110.000 $159.300 $71.000 $190.000 $100.000
RAIL (TY C402)
LF 902.000 $150.000 $221.138 $210.000 $253.550 $150.000 $207.000 $275.000
RAIL (TY PR11)
LF 743.000 $135.000 $131.268 $200.000 $148.550 $100.000 $202.000 $185.000
RAIL (CLF-RO)
LF 596.000 $170.000 $132.374 $215.000 $200.150 $250.000 $300.000 $215.000
RETROFIT RAIL (TY T402)
LF 801.000 $220.000 $202.707 $300.000 $247.900 $200.000 $180.000 $130.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 272.000 $250.000 $203.353 $240.000 $324.650 $196.000 $255.000 $362.000
HYDRO-DEMOLITION (3 IN)
SY 18.000 $200.000 $912.646 $1.000 $814.100 $185.000 $250.000 $1,300.000
HYDRO-DEMOLITION (4 IN)
SY 18.000 $200.000 $912.646 $1.000 $814.100 $257.000 $350.000 $1,300.000
MOBILIZATION
LS 1.000 $470,000.000 $449,694.497 $612,000.000 $620,000.000 $620,000.000 $700,000.000 $762,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $13,000.000 $25,108.570 $14,250.000 $18,434.000 $75,000.000 $40,000.000 $31,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $6,098.787 $30,000.000 $19,526.500 $25,000.000 $15,000.000 $18,500.000
TMA (STATIONARY)
DAY 30.000 $150.000 $213.560 $50.000 $535.950 $346.000 $480.000 $500.000
TMA (MOBILE OPERATION)
HR 24.000 $100.000 $60.705 $75.000 $110.600 $68.000 $350.000 $950.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 600.000 $6.000 $4.380 $8.000 $5.750 $5.000 $7.500 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 600.000 $1.000 $1.095 $4.000 $1.730 $1.500 $2.500 $3.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 90.000 $6.000 $8.213 $20.000 $7.470 $6.500 $11.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 90.000 $1.000 $1.095 $10.000 $2.300 $2.000 $5.000 $3.000
CONC CURB (TY II)
LF 101.000 $35.000 $40.455 $56.000 $58.050 $28.000 $125.000 $41.750
CONC CURB & GUTTER (TY II)
LF 49.000 $50.000 $51.342 $71.000 $48.550 $54.000 $150.000 $45.000
CONC SIDEWALKS (4")
SY 1,673.000 $95.000 $89.465 $97.000 $57.750 $89.000 $20.000 $101.000
CURB RAMPS (TY 2)
SY 50.000 $180.000 $205.346 $330.000 $337.500 $144.000 $600.000 $185.000
CURB RAMPS (TY 3)
SY 25.000 $195.000 $164.277 $330.000 $213.150 $150.000 $350.000 $185.000
CURB RAMPS (TY 7)
SY 32.000 $195.000 $246.415 $330.000 $267.950 $155.000 $350.000 $175.000
MTL W-BEAM GD FEN (STEEL POST)
LF 150.000 $40.000 $27.379 $37.000 $74.750 $33.000 $40.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $3,400.000 $1,998.704 $2,500.000 $4,255.000 $2,300.000 $3,300.000 $3,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $2,000.000 $1,303.265 $1,700.000 $2,185.000 $1,500.000 $2,150.000 $2,150.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $4.000 $2.190 $6.000 $9.200 $3.000 $3.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $475.000 $188.316 $250.000 $575.000 $200.000 $300.000 $300.000
RM MTL BM GD FENCE TRANS (TL-2)
EA 2.000 $700.000 $180.704 $350.000 $460.000 $500.000 $300.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,800.000 $2,924.680 $3,900.000 $5,750.000 $3,600.000 $4,500.000 $4,500.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,650.000 $1,642.771 $1,100.000 $2,300.000 $1,500.000 $1,350.000 $1,350.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 1.000 $18,000.000 $22,509.249 $28,000.000 $33,350.000 $27,000.000 $33,000.000 $33,000.000
REMOVE RD IL ASM (BRIDGE MOUNT)
EA 8.000 $534.000 $1,314.216 $1,400.000 $1,150.000 $1,000.000 $1,200.000 $1,000.000
REPLACE LUMINAIRE W/(250W EQ) LED
EA 3.000 $783.000 $1,040.421 $1,000.000 $862.500 $750.000 $950.000 $750.000
IN RD IL (TY SA) 40B-8 (250W EQ) LED
EA 8.000 $12,000.000 $7,529.367 $7,500.000 $9,775.000 $6,500.000 $6,875.000 $6,500.000
CONDT (PVC) (SCH 40) (2")
LF 2,305.000 $18.000 $21.629 $22.000 $20.700 $15.000 $19.750 $15.000
ELEC CONDR (NO.6) INSULATED
LF 5,675.000 $2.600 $4.654 $5.000 $3.750 $3.250 $4.250 $3.250
GROUND BOX TY A (122311)W/APRON
EA 2.000 $1,865.000 $2,299.879 $2,300.000 $1,725.000 $1,500.000 $2,100.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $1,100.000 $739.247 $2,200.000 $983.250 $800.000 $800.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $1,200.000 $870.668 $2,300.000 $1,146.550 $900.000 $900.000 $900.000
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 1.000 $1,200.000 $1,979.539 $2,800.000 $3,407.450 $2,000.000 $2,000.000 $2,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $150.000 $492.831 $660.000 $930.350 $700.000 $700.000 $700.000
REMOVE SM RD SN SUP&AM
EA 12.000 $130.000 $109.518 $110.000 $166.800 $100.000 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 38.000 $35.000 $16.427 $25.000 $48.300 $35.000 $35.000 $35.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 4.000 $35.000 $27.379 $30.000 $58.650 $50.000 $50.000 $50.000
INSTL OM SM RD SIGN (1-OM-PW)Y
EA 10.000 $1.000 $24.093 $22.000 $18.400 $10.000 $10.000 $10.000
INSTL OM SM RD SIGN (1-OM-PW)R
EA 3.000 $1.000 $26.284 $22.000 $18.400 $10.000 $10.000 $10.000
INSTL OM SM RD SIGN (2-OM-PW)Y
EA 1.000 $1.000 $28.748 $110.000 $94.300 $150.000 $150.000 $150.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 192.000 $1.000 $1.642 $2.000 $1.750 $1.500 $1.500 $1.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,000.000 $1.000 $1.642 $2.000 $1.750 $1.500 $1.500 $1.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 451.000 $10.000 $12.046 $12.000 $12.650 $11.000 $11.000 $11.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 18.000 $250.000 $355.933 $350.000 $373.750 $325.000 $325.000 $325.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $250.000 $355.933 $350.000 $373.750 $325.000 $325.000 $325.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 17.000 $50.000 $54.759 $55.000 $57.500 $50.000 $50.000 $50.000
RE PM TY II (W) 6" (BRK)
LF 290.000 $0.500 $0.657 $1.000 $0.700 $0.600 $0.600 $0.600
RE PM TY II (W) 6" (SLD)
LF 1,253.000 $0.500 $0.657 $1.000 $0.700 $0.600 $0.600 $0.600
RE PM TY II (W) 8" (DOT)
LF 180.000 $0.500 $0.821 $1.000 $0.850 $0.750 $0.750 $0.750
RE PM TY II (W) 8" (SLD)
LF 1,000.000 $1.500 $0.821 $1.000 $0.850 $0.750 $0.750 $0.750
RE PM TY II (W) 24" (SLD)
LF 451.000 $6.500 $6.571 $7.000 $6.900 $6.000 $6.000 $6.000
RE PM TY II (W) (ARROW)
EA 18.000 $130.000 $109.518 $110.000 $115.000 $100.000 $100.000 $100.000
RE PM TY II (W) (WORD)
EA 4.000 $100.000 $164.277 $165.000 $172.500 $150.000 $150.000 $150.000
RE PM TY II (W) 18" (YLD TRI)
EA 17.000 $35.000 $32.855 $33.000 $34.500 $30.000 $30.000 $30.000
RE PM TY II (Y) 6" (BRK)
LF 160.000 $0.500 $0.657 $1.000 $0.700 $0.600 $0.600 $0.600
RE PM TY II (Y) 6" (SLD)
LF 9,060.000 $0.500 $0.657 $1.000 $0.700 $0.600 $0.600 $0.600
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 290.000 $0.600 $1.314 $2.000 $1.400 $1.200 $1.200 $1.200
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,253.000 $0.600 $1.314 $2.000 $1.400 $1.200 $1.200 $1.200
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 160.000 $0.600 $1.314 $2.000 $1.400 $1.200 $1.200 $1.200
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 11,400.000 $0.600 $1.314 $2.000 $1.400 $1.200 $1.200 $1.200
ELIM EXT PM & MRKS (4")
LF 3,640.000 $1.300 $2.190 $2.500 $2.300 $2.000 $2.000 $2.000
ELIM EXT PM & MRKS (8")
LF 400.000 $2.200 $2.190 $3.000 $2.300 $2.000 $2.000 $2.000
ELIM EXT PM & MRKS (12")
LF 80.000 $3.200 $2.737 $4.000 $2.900 $2.000 $2.500 $2.500
ELIM EXT PM & MRKS (ARROW)
EA 10.000 $40.000 $98.566 $100.000 $103.500 $90.000 $90.000 $90.000
PAV SURF PREP FOR MRK (6")
LF 13,133.000 $0.200 $0.602 $1.000 $0.650 $0.550 $0.550 $0.550
PAV SURF PREP FOR MRK (8")
LF 1,159.000 $0.300 $0.602 $1.000 $0.650 $0.550 $0.550 $0.550
PAV SURF PREP FOR MRK (24")
LF 451.000 $1.300 $4.380 $5.000 $4.600 $4.000 $4.000 $4.000
CARBON FIBER REINF POLYMER PROTECTION
SF 1,665.000 $45.000 $52.886 $80.000 $37.950 $33.000 $80.000 $35.000
REPLACING ELASTOMERIC BEARING PADS
EA 154.000 $1,800.000 $960.232 $4,000.000 $3,924.200 $6,000.000 $4,000.000 $3,750.000
CONCRETE BEAM REPAIR (CFRP)
EA 56.000 $6,600.000 $2,540.184 $6,500.000 $3,415.500 $2,700.000 $6,500.000 $3,000.000
Totals: $5,801,924.400 $4,519,471.034 $6,120,788.000 $6,211,417.750 $6,291,324.750 $7,389,016.500 $7,622,831.700
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $200,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $205,000.00