POTTER VA (0904-00-208)
Items: 27
County: POTTER
Length: N/A
Highway: VA
District: AMARILLO
Control Number: 0904-00-208
DBE Goal: 0.0%
Project: C 904-00-208
Guaranty: N/A
Time: 223 WORKING DAYS
Engineer's Estimate: $1,584,515.00
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
CLINT HARMS
BRANDON BILBREY
KIT BLACK
DARRELL CALDWELL
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,584,515.00 | |||
| $1,283,633.00 |
-18.99%
-$300,882.00
|
|||
| $1,496,438.00 |
-5.56%
-$88,077.00
|
16.58%
$212,805.00
|
||
| $1,572,010.00 |
-0.79%
-$12,505.00
|
22.47%
$288,377.00
|
-5.05%
-$75,572.00
|
|
| $1,790,086.00 |
12.97%
$205,571.00
|
39.45%
$506,453.00
|
-13.87%
-$218,076.00
|
|
| $2,250,479.00 |
42.03%
$665,964.00
|
75.32%
$966,846.00
|
-25.72%
-$460,393.00
|
E
Engineer's Estimate
$1,584,515.00
1
$1,283,633.00
Over/Under Est:
-18.99%
-$300,882.00
$1,496,438.00
Over/Under Est:
-5.56%
-$88,077.00
Amt Left:
16.58%
$212,805.00
$1,572,010.00
Over/Under Est:
-0.79%
-$12,505.00
Amt Left:
22.47%
$288,377.00
Delta:
-5.05%
-$75,572.00
$1,790,086.00
Over/Under Est:
12.97%
$205,571.00
Amt Left:
39.45%
$506,453.00
Delta:
-13.87%
-$218,076.00
$2,250,479.00
Over/Under Est:
42.03%
$665,964.00
Amt Left:
75.32%
$966,846.00
Delta:
-25.72%
-$460,393.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| S&S BRIDGE PAINTING | 34.55% | $443,495.20 |
| TAYLOR CONTRACTING LLC | 28.94% | $371,483.39 |
| FC TRAFFIC CONTROL, INC. | 2.87% | $36,840.27 |
| Total: | 66.36% | $851,818.86 |
Bid Items & Bid Tabulations
27
Total
0 of 27