Show Job Controls
Bid Cobra

POTTER VA (0904-00-180)

Items: 16

County: POTTER
Length: N/A
Highway: VA
District: AMARILLO
Control Number: 0904-00-180
DBE Goal: N/A
Project: STP 2018(521)
Guaranty: N/A
Time: 36 WORKING DAYS
Engineer's Estimate: $635,882.38
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: THERMOPLASTIC STRIPING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$635,882.38
1
$482,197.48
Over/Under Est: -24.17% -$153,684.90
$499,120.11
Over/Under Est: -21.51% -$136,762.27
Amt Left: 3.51% $16,922.63
$507,313.64
Over/Under Est: -20.22% -$128,568.74
Amt Left: 5.21% $25,116.16
Delta: -1.64% -$8,193.53
Over/Under Est: -14.96% -$95,159.03
Amt Left: 12.14% $58,525.87
Delta: -6.59% -$33,409.71
$561,199.36
Over/Under Est: -11.74% -$74,683.02
Amt Left: 16.38% $79,001.88
Delta: -3.79% -$20,476.01
Over/Under Est: 8.07% $51,290.26
Amt Left: 42.51% $204,975.16
Delta: -22.45% -$125,973.28
Over/Under Est: 10.97% $69,768.42
Amt Left: 46.34% $223,453.32
Delta: -2.69% -$18,478.16

Bid Items & Bid Tabulations

16 Total 0 of 16
POTTER  |  VA  |  AMARILLO  |  0904-00-180  |  02/02/2018  |  $635,882.38  |  STP 2018(521)  |  THERMOPLASTIC STRIPING  |  36 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L&L COMPANY
MIJELUM, L.L.C.
FLAT LINE, INC.
BARRICADES UNLIMITED
STRIPE-A-ZONE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $46,954.250 $1.000 $10,000.000 $5,000.000 $1.000 $0.010 $50,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $1,000.000 $1.000 $1.000 $1.000 $1.000 $0.010 $25,000.000 $2,000.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 24,684.000 $0.330 $0.400 $0.450 $0.330 $0.440 $0.675 $0.740 $0.650
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 396.000 $1.930 $3.000 $1.800 $4.000 $3.000 $4.000 $2.900 $2.900
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 5,057.000 $3.360 $3.500 $3.400 $3.000 $5.500 $4.250 $5.800 $5.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 45.000 $68.750 $70.000 $85.000 $150.000 $63.000 $80.000 $105.000 $100.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 6.000 $100.250 $150.000 $185.000 $175.000 $71.000 $100.000 $148.000 $150.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 4.000 $450.000 $200.000 $250.000 $200.000 $79.000 $120.000 $180.000 $200.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 38.000 $106.150 $100.000 $150.000 $200.000 $79.000 $100.000 $126.000 $110.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 10.000 $198.000 $200.000 $334.000 $250.000 $237.000 $425.000 $459.000 $450.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 142.000 $10.000 $20.000 $15.000 $15.000 $12.000 $26.000 $68.000 $40.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 6,293.000 $1.500 $3.000 $2.000 $3.000 $3.000 $3.000 $2.300 $2.250
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 43,660.000 $0.240 $0.200 $0.210 $0.200 $0.210 $0.230 $0.240 $0.330
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,161,985.000 $0.240 $0.185 $0.190 $0.194 $0.210 $0.215 $0.220 $0.250
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 197,170.000 $0.240 $0.190 $0.210 $0.200 $0.210 $0.230 $0.240 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 841,594.000 $0.240 $0.190 $0.189 $0.195 $0.210 $0.215 $0.220 $0.250
Totals: $635,882.380 $482,197.485 $499,120.116 $507,313.640 $540,723.350 $561,199.365 $687,172.640 $705,650.800