POTTER BI 40-D (0090-06-044)

Items: 107

County: POTTER
Length: N/A
Highway: BI 40-D
District: AMARILLO
Control Number: 0090-06-044
DBE Goal: N/A
Project: BR 2021(281)
Guaranty: N/A
Time: 364 WORKING DAYS
Engineer's Estimate: $4,894,339.30
Date: 01/07/2021 (5 years ago)
Contract Number: N/A
Type: REPLACE EXISTING BRIDGES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (7)
E
Engineer's Estimate
$4,894,339.30
$5,207,276.12
Over/Under Est: 6.39% $312,936.82
Over/Under Est: 19.16% $937,587.40
Amt Left: 12% $624,650.58
Over/Under Est: 26.23% $1,283,917.10
Amt Left: 18.65% $970,980.28
Delta: -5.94% -$346,329.70
$6,212,186.35
Over/Under Est: 26.93% $1,317,847.05
Amt Left: 19.3% $1,004,910.23
Delta: -0.55% -$33,929.95
Over/Under Est: 27.7% $1,355,488.80
Amt Left: 20.02% $1,042,551.98
Delta: -0.61% -$37,641.75
$6,588,543.00
Over/Under Est: 34.62% $1,694,203.70
Amt Left: 26.53% $1,381,266.88
Delta: -5.42% -$338,714.90
$7,037,270.35
Over/Under Est: 43.78% $2,142,931.05
Amt Left: 35.14% $1,829,994.23
Delta: -6.81% -$448,727.35
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 6.24% $331,068.33
RK HALL, LLC 6.12% $324,701.63
MICA CORPORATION 4.31% $228,670.59
HUNTER DEMOLITION & WRECKING CORPORATION 3.43% $181,981.47
BARRICADES UNLIMITED 1.87% $99,214.39
HJC FARMS, INC. 1.82% $96,561.60
MARCOMS CONSTRUCTION LLC 1.76% $93,378.25
L&H ELECTRICAL, LLC 1.52% $80,644.85
TORO BRAVO CONSTRUCTION, LLC 0.90% $47,750.24
TRP CONSTRUCTION GROUP, LLC 0.86% $45,628.01
TRP CONSTRUCTION GROUP, LLC 0.74% $39,261.31
FC TRAFFIC CONTROL, INC. 0.47% $24,936.24
TEXAS ALTERNATIVE GRASSER INCORPORATED 0.41% $21,752.89
A BROTHERS MILLING, LLC 0.35% $18,569.54
TORO BRAVO CONSTRUCTION, LLC 0.32% $16,977.86
PINNACLE GRINDING AND GROOVING LLC 0.20% $10,611.16
PENHALL COMPANY 0.16% $8,488.93
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.11% $5,836.14
COPPELL CONSTRUCTION CO., INC. 0.00% $0.00
Total: 31.59% $1,676,033.43

Bid Items & Bid Tabulations

107 Total 0 of 107
POTTER  |  BI 40-D  |  AMARILLO  |  0090-06-044  |  01/07/2021  |  $4,894,339.30  |  BR 2021(281)  |  REPLACE EXIST BRIDGES  |  364 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
INTEGRITY SERVICES, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
COPPELL CONSTRUCTION CO., INC.
GILVIN-TERRILL, LTD.
STATELINE CONSTRUCTION, LLC
EARTH BUILDERS, L.P.
J. LEE MILLIGAN, INC.
PREPARING ROW
AC 3.800 $750.000 $750.000 $13,000.000 $7,650.000 $4,000.000 $8,500.000 $30,000.000 $27,000.000
REMOVING CONC (PAV)
SY 33.000 $10.000 $8.000 $500.000 $103.000 $60.000 $20.000 $10.000 $46.000
REMOVING CONC (RIPRAP)
SY 489.000 $25.000 $18.500 $50.000 $33.000 $70.000 $14.000 $10.000 $27.500
REMOVING CONC (CURB AND GUTTER)
LF 4,569.000 $6.000 $6.250 $25.000 $5.500 $2.000 $4.000 $5.000 $3.750
REMOVING CONC (SIDEWALK OR RAMP)
SY 1,085.000 $10.000 $14.000 $45.000 $23.000 $30.000 $12.000 $10.000 $14.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 3,853.000 $6.000 $5.540 $10.000 $5.000 $10.000 $9.000 $5.000 $14.000
EXCAVATION (ROADWAY)
CY 13,454.000 $12.000 $10.000 $8.000 $14.000 $17.000 $14.000 $15.000 $17.650
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 2,090.000 $25.000 $17.000 $25.000 $22.000 $20.000 $19.000 $15.000 $15.500
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 5,948.000 $1.000 $0.750 $1.500 $0.500 $0.450 $0.850 $1.000 $0.500
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 667.000 $6.000 $3.190 $3.000 $4.500 $4.000 $2.000 $6.000 $4.450
FL BS (CMP IN PLC)(TY A GR 4)(10")
SY 4,042.000 $25.000 $40.500 $20.000 $30.000 $25.000 $31.000 $50.000 $22.800
PRIME COAT (MC-30)
GAL 1,012.000 $5.000 $11.000 $10.000 $11.000 $8.000 $12.000 $10.000 $6.350
EMULS ASPH (EROSN CONT)(MULTI)
GAL 416.000 $10.000 $5.000 $10.000 $11.000 $8.000 $22.000 $5.000 $7.450
PLANE ASPH CONC PAV (2")
SY 3,159.000 $6.000 $3.080 $10.000 $1.000 $8.000 $11.000 $10.000 $5.400
CONC PVMT (CONT REINF - CRCP) (8")
SY 35.000 $150.000 $95.000 $200.000 $304.000 $99.000 $265.000 $300.000 $110.000
CEM STABIL BKFL
CY 340.000 $145.000 $220.000 $250.000 $206.000 $230.000 $290.000 $200.000 $195.000
SAND BACKFILL
CY 142.000 $50.000 $35.000 $200.000 $50.000 $25.000 $250.000 $80.000 $160.000
TEMPORARY SPL SHORING
SF 2,440.000 $25.000 $30.000 $40.000 $16.000 $30.000 $36.000 $25.000 $73.500
DRILL SHAFT (18 IN)
LF 240.000 $125.000 $88.000 $120.000 $106.000 $200.000 $135.000 $130.000 $150.000
DRILL SHAFT (36 IN)
LF 1,730.000 $190.000 $293.700 $350.000 $340.000 $395.000 $345.000 $350.000 $360.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 40.000 $190.000 $190.000 $300.000 $270.000 $362.000 $345.000 $400.000 $360.000
CL C CONC (ABUT)(HPC)
CY 135.200 $1,100.000 $1,150.000 $1,200.000 $1,020.000 $1,300.000 $1,200.000 $1,200.000 $1,535.000
CL C CONC (CAP)(HPC)
CY 85.600 $1,200.000 $1,150.000 $1,200.000 $1,170.000 $1,900.000 $1,450.000 $1,200.000 $1,975.000
CL C CONC (COLUMN)(HPC)
CY 93.200 $1,300.000 $1,250.000 $1,200.000 $1,139.000 $1,000.000 $1,650.000 $1,200.000 $1,400.000
CL C CONC (CRASHWALL)(HPC)
CY 140.400 $750.000 $700.000 $1,200.000 $575.000 $1,200.000 $1,100.000 $1,200.000 $855.000
REINF CONC SLAB (HPC)
SF 20,580.000 $25.000 $23.540 $24.000 $27.000 $32.000 $26.500 $35.000 $36.650
APPROACH SLAB (HPC)
CY 189.800 $575.000 $650.000 $600.000 $600.000 $1,100.000 $725.000 $800.000 $670.000
PRESTR CONC GIRDER (TX34)
LF 2,603.320 $165.000 $214.530 $185.000 $220.000 $195.000 $215.000 $200.000 $235.000
SILICONE RESIN PAINT FINISH
SF 1,532.000 $7.000 $6.690 $10.000 $11.000 $11.000 $17.000 $12.000 $5.550
RIPRAP (CONC)(4 IN)
CY 314.000 $500.000 $475.000 $550.000 $528.000 $523.000 $445.000 $800.000 $565.000
STR STEEL (MISC NON - BRIDGE)
LB 440.000 $8.000 $18.250 $20.000 $17.000 $12.000 $45.000 $20.000 $20.600
RAIL (TY SSTR)(HPC)
LF 607.000 $77.000 $89.100 $120.000 $96.000 $73.000 $145.000 $125.000 $80.750
RAIL (TY C221)(HPC)
LF 1,161.000 $150.000 $83.600 $120.000 $90.000 $112.000 $145.000 $175.000 $115.500
HEADER TYPE EXPANSION JOINT
LF 176.000 $100.000 $105.600 $175.000 $250.000 $50.000 $145.000 $200.000 $179.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $100,000.000 $100,100.000 $80,000.000 $350,000.000 $210,000.000 $225,000.000 $175,000.000 $300,000.000
MOBILIZATION
LS 1.000 $250,000.000 $509,593.440 $500,000.000 $609,000.000 $600,000.000 $625,000.000 $650,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $12,000.000 $1,350.000 $7,700.000 $2,100.000 $10,000.000 $3,200.000 $2,500.000 $15,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,575.000 $4.000 $4.200 $4.000 $4.000 $5.000 $2.500 $5.000 $6.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,575.000 $1.000 $1.480 $2.000 $1.000 $1.000 $1.000 $1.000 $3.250
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 360.000 $4.000 $7.080 $8.000 $3.500 $5.000 $4.000 $5.000 $8.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 360.000 $1.000 $1.100 $2.000 $1.000 $1.000 $1.000 $1.000 $3.900
CONSTRUCTING DETOURS (TY 1)
SY 2,062.000 $80.000 $67.680 $80.000 $57.000 $150.000 $85.000 $150.000 $107.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 2,070.000 $10.000 $16.500 $20.000 $7.000 $12.000 $20.000 $50.000 $15.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 1,920.000 $10.000 $10.000 $15.000 $4.500 $3.000 $20.000 $20.000 $13.250
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 2,070.000 $15.000 $12.000 $20.000 $7.000 $5.000 $20.000 $30.000 $14.500
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 412.000 $69.000 $106.700 $100.000 $115.000 $150.000 $145.000 $100.000 $165.000
PERM CTB (SGL SLOPE) (TY 3) SPECIAL
LF 24.000 $100.000 $819.500 $100.000 $884.000 $219.000 $145.000 $100.000 $243.250
CONC CURB & GUTTER (TY II)
LF 3,943.000 $20.000 $18.000 $40.000 $22.000 $20.000 $24.000 $20.000 $22.000
CONC SIDEWALKS (4")
SY 1,599.000 $60.000 $50.000 $100.000 $76.000 $44.000 $42.000 $60.000 $48.500
CURB RAMPS (TY 1)
EA 4.000 $2,000.000 $1,800.000 $2,000.000 $2,970.000 $1,250.000 $2,350.000 $2,500.000 $1,400.000
CONC MEDIAN
SY 2,034.000 $60.000 $97.000 $100.000 $117.000 $45.000 $45.000 $80.000 $49.800
MTL W-BEAM GD FEN (STEEL POST)
LF 230.000 $25.000 $26.950 $26.000 $30.000 $29.000 $35.000 $40.000 $32.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,800.000 $1,633.500 $1,500.000 $1,960.000 $2,200.000 $1,800.000 $2,500.000 $2,445.000
REMOVE METAL BEAM GUARD FENCE
LF 895.000 $3.000 $3.130 $4.000 $3.000 $2.000 $3.000 $5.000 $2.250
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $250.000 $350.000 $500.000 $235.000 $200.000 $500.000 $100.000 $225.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,700.000 $2,200.000 $2,800.000 $3,330.000 $2,750.000 $3,000.000 $3,000.000 $3,055.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $270.000 $269.500 $500.000 $380.000 $205.000 $500.000 $100.000 $230.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $3,000.000 $1,644.500 $4,000.000 $3,560.000 $280.000 $1,500.000 $1,500.000 $310.000
CRASH CUSH ATTEN (REMOVE)
EA 3.000 $1,000.000 $1,457.500 $2,000.000 $1,180.000 $190.000 $1,500.000 $1,500.000 $210.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 5.000 $20,000.000 $9,791.250 $20,000.000 $28,500.000 $6,850.000 $9,850.000 $7,500.000 $4,450.000
CHAIN LINK FENCE (INSTALL) (6')
LF 490.000 $30.000 $20.000 $80.000 $35.000 $30.000 $65.000 $40.000 $55.500
CHAIN LINK FENCE (INSTALL) (8')
LF 490.000 $50.000 $80.000 $90.000 $71.000 $35.000 $85.000 $50.000 $72.200
REMOVE RD IL ASM (TRANS-BASE)
EA 5.000 $1,000.000 $517.000 $500.000 $470.000 $470.000 $500.000 $200.000 $335.000
IN RD IL (TY ST) 40T-10-10(250W EQ)LED
EA 5.000 $4,000.000 $7,150.000 $4,000.000 $6,500.000 $6,500.000 $5,000.000 $8,000.000 $8,225.000
CONDT (PVC) (SCH 80) (2")
LF 855.000 $10.000 $17.600 $10.000 $16.000 $16.000 $12.000 $10.000 $8.900
ELEC CONDR (NO.6) BARE
LF 1,375.000 $3.000 $2.200 $2.000 $2.000 $2.000 $6.000 $2.000 $1.650
ELEC CONDR (NO.6) INSULATED
LF 2,750.000 $3.000 $2.640 $2.000 $2.400 $3.000 $6.000 $2.000 $1.650
GROUND BOX TY A (122311)W/APRON
EA 2.000 $510.000 $1,069.200 $1,000.000 $972.000 $972.000 $6,500.000 $2,000.000 $1,555.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $1,000.000 $979.000 $600.000 $890.000 $890.000 $2,500.000 $750.000 $790.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $1,276.000 $800.000 $1,160.000 $1,160.000 $2,500.000 $750.000 $1,425.000
REMOVE SM RD SN SUP&AM
EA 4.000 $150.000 $126.500 $100.000 $115.000 $115.000 $500.000 $100.000 $165.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 26.000 $20.000 $30.000 $30.000 $25.000 $14.000 $45.000 $20.000 $70.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 6.000 $175.000 $142.000 $50.000 $175.000 $115.000 $65.000 $100.000 $230.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 21.000 $38.000 $35.000 $30.000 $40.000 $19.000 $45.000 $25.000 $88.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
LF 2,522.000 $1.000 $1.760 $1.000 $1.500 $1.600 $1.000 $2.000 $1.800
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 1,744.000 $1.000 $1.760 $1.000 $1.600 $1.600 $1.000 $2.000 $1.800
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 5,592.000 $2.000 $1.760 $1.000 $1.400 $1.600 $1.000 $2.000 $1.800
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,563.000 $2.000 $1.760 $1.000 $1.400 $1.600 $2.000 $2.000 $1.800
REFL PAV MRK TY I (W)4"(BRK)(100MIL)
LF 955.000 $1.300 $1.090 $1.000 $1.200 $0.990 $2.000 $1.000 $1.100
REFL PAV MRK TY I (W)4"(SLD)(100MIL)
LF 3,375.000 $1.300 $1.090 $1.000 $1.000 $0.990 $2.000 $1.000 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 290.000 $2.600 $2.200 $1.000 $2.000 $2.000 $5.000 $2.000 $2.220
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 48.000 $4.000 $22.000 $1.000 $4.500 $20.000 $5.000 $25.000 $22.200
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $150.000 $550.000 $1.000 $175.000 $500.000 $85.000 $500.000 $555.300
REFL PAV MRK TY I (Y)4"(SLD)(100MIL)
LF 3,620.000 $1.300 $1.090 $1.000 $1.000 $0.990 $2.000 $1.000 $1.100
REFL PAV MRK TY II (W) 4" (BRK)
LF 955.000 $0.800 $0.390 $1.000 $0.500 $0.350 $2.000 $0.500 $0.390
REFL PAV MRK TY II (W) 4" (SLD)
LF 3,375.000 $0.800 $0.390 $1.000 $0.500 $0.350 $2.000 $0.500 $0.390
REFL PAV MRK TY II (W) 8" (SLD)
LF 290.000 $1.250 $0.770 $1.000 $1.000 $0.700 $4.000 $1.000 $0.780
REFL PAV MRK TY II (W) 12" (SLD)
LF 48.000 $1.750 $5.500 $1.000 $1.000 $5.000 $65.000 $5.000 $5.550
REFL PAV MRK TY II (Y) 4" (SLD)
LF 3,620.000 $0.800 $0.390 $1.000 $0.500 $0.350 $2.000 $0.500 $0.390
REFL PAV MRKR TY II-C-R
EA 95.000 $5.000 $16.500 $5.000 $6.000 $2.000 $25.000 $18.000 $16.650
ELIM EXT PAV MRK & MRKS (4")
LF 7,201.000 $5.000 $0.830 $0.500 $1.000 $0.750 $2.000 $1.000 $0.850
ELIM EXT PAV MRK & MRKS (8")
LF 95.000 $6.000 $2.200 $1.000 $1.200 $2.000 $2.000 $2.000 $2.250
ELIM EXT PAV MRK & MRKS (ARROW)
EA 1.000 $20.000 $100.000 $50.000 $75.000 $100.000 $500.000 $100.000 $111.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 1.000 $20.000 $100.000 $50.000 $75.000 $100.000 $500.000 $100.000 $111.000
PAV SURF PREP FOR MRK (4")
LF 1,806.000 $2.000 $1.100 $1.000 $0.300 $1.000 $2.000 $1.000 $1.100
FULL - WIDTH MOWING
CYC 6.000 $3,500.000 $5,000.000 $1,000.000 $5,000.000 $1,500.000 $2,000.000 $250.000 $1,840.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
CYC 14.000 $1,800.000 $2,000.000 $150.000 $1,700.000 $1,500.000 $1,500.000 $300.000 $1,215.000
D-GR HMA TY-B SAC-B PG64-22
TON 790.000 $150.000 $104.500 $140.000 $132.000 $110.000 $175.000 $175.000 $147.000
TACK COAT
GAL 467.000 $5.000 $5.500 $8.000 $8.000 $4.000 $12.000 $5.000 $3.500
SP MIXES SP-C SAC-A PG70-28
TON 743.000 $220.000 $187.000 $140.000 $200.000 $115.000 $185.000 $175.000 $155.000
TACK COAT
GAL 877.000 $5.000 $7.700 $8.000 $8.000 $4.000 $12.000 $5.000 $3.500
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $206.000 $250.000 $1,000.000 $590.000 $500.000 $2,500.000 $250.000 $190.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,750.000 $10,000.000 $14,000.000 $15,000.000 $15,000.000 $15,000.000 $22,300.000
MODULAR GLARE SCREENS (FURN & INSTALL)
LF 2,036.000 $15.000 $20.000 $8.000 $22.000 $13.000 $20.000 $20.000 $22.000
MODULAR GLARE SCREENS (REMOVE)
LF 2,036.000 $1.000 $1.500 $2.000 $2.000 $1.000 $5.000 $1.000 $1.900
TMA (STATIONARY)
DAY 100.000 $325.000 $192.050 $200.000 $600.000 $200.000 $165.000 $50.000 $495.000
TMA (MOBILE OPERATION)
HR 200.000 $80.000 $366.000 $50.000 $83.000 $95.000 $85.000 $100.000 $88.000
Totals: $4,894,339.300 $5,207,276.130 $5,831,926.700 $6,178,256.400 $6,212,186.350 $6,249,828.100 $6,588,543.000 $7,037,270.350