POTTER IH 40 (0090-05-098)

Items: 51

County: POTTER
Length: N/A
Highway: IH 40
District: AMARILLO
Control Number: 0090-05-098
DBE Goal: N/A
Project: NH 2019(408)
Guaranty: N/A
Time: 85 WORKING DAYS
Engineer's Estimate: $7,871,583.90
Date: 01/08/2019 (7 years ago)
Contract Number: N/A
Type: SMA OVERLAY, MBGF, STRIPING, RUMBLE STRIPS.
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$7,871,583.90
1
$7,778,312.13
Over/Under Est: -1.18% -$93,271.77
$7,967,170.83
Over/Under Est: 1.21% $95,586.93
Amt Left: 2.43% $188,858.70
Over/Under Est: 3.23% $254,132.60
Amt Left: 4.47% $347,404.37
Delta: -1.99% -$158,545.67
$8,416,560.46
Over/Under Est: 6.92% $544,976.56
Amt Left: 8.21% $638,248.33
Delta: -3.58% -$290,843.96

Bid Items & Bid Tabulations

51 Total 0 of 51
POTTER  |  IH 40  |  AMARILLO  |  0090-05-098  |  01/08/2019  |  $7,871,583.90  |  NH 2019(408)  |  SMA OVERLAY, MBGF, STRIPING, RUMBLE...  |  85 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
DUININCK, INC.
ALLEN BUTLER CONSTRUCTION, INC.
J. LEE MILLIGAN, INC.
PREPARING ROW
AC 19.530 $200.000 $200.000 $190.000 $318.110 $250.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 610.000 $35.000 $28.740 $50.000 $27.990 $46.000
BACKFILL (TY A)
STA 849.800 $200.000 $156.660 $255.000 $146.020 $210.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 19.530 $500.000 $287.260 $285.000 $970.830 $300.000
EMULS ASPH (EROSN CONT)(MS-2)
GAL 5,908.000 $3.750 $3.280 $4.650 $14.700 $3.700
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 44,970.000 $120.000 $122.900 $120.000 $116.170 $125.300
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,042.000 $55.000 $49.730 $73.000 $65.460 $61.300
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 11,825.000 $25.000 $27.370 $23.500 $25.690 $26.000
PLANE CONC PAV(0" TO 2")
SY 13,070.000 $3.000 $5.130 $3.400 $2.100 $4.800
PLANE ASPH CONC PAV (2")
SY 633.000 $3.000 $5.130 $9.250 $6.850 $6.300
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 849.800 $3.000 $5.130 $14.000 $5.360 $5.800
DRILL SHAFT (SIGN MTS) (12 IN)
LF 60.000 $175.000 $116.420 $130.000 $138.750 $132.000
RIPRAP (CONC)(4 IN)
CY 15.000 $400.000 $421.560 $620.000 $533.040 $910.000
RIPRAP (MOW STRIP)(4 IN)
CY 504.000 $400.000 $430.290 $620.000 $517.200 $632.000
CLEANING AND SEALING JOINTS
LF 983.000 $70.000 $64.750 $64.500 $41.070 $60.400
SHOT BLASTING
SY 18.200 $7.000 $195.940 $180.000 $277.500 $185.000
MOBILIZATION
LS 1.000 $650,000.000 $350,712.460 $400,000.000 $805,006.250 $658,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $13,000.000 $9,323.040 $30,000.000 $10,539.790 $24,350.000
RUMBLE STRIPS (SHOULDER)
LF 161,538.000 $0.200 $0.170 $0.110 $0.110 $0.100
MTL W-BEAM GD FEN (STEEL POST)
LF 9,000.000 $25.000 $25.990 $27.000 $28.300 $26.850
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 13.000 $1,800.000 $1,977.960 $2,400.000 $2,553.000 $2,425.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,000.000 $1,245.500 $1,200.000 $1,304.250 $1,240.000
REMOVE METAL BEAM GUARD FENCE
LF 8,617.500 $2.500 $3.180 $3.400 $3.610 $3.450
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $220.000 $424.000 $340.000 $360.750 $345.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 13.000 $300.000 $318.000 $340.000 $360.750 $345.000
GUARDRAIL END TREATMENT (INSTALL)
EA 17.000 $2,500.000 $3,134.420 $3,500.000 $3,718.490 $3,530.000
GUARDRAIL END TREATMENT (REMOVE)
EA 17.000 $250.000 $318.000 $340.000 $360.750 $345.000
ALUMINUM SIGNS (TY G)
SF 225.000 $30.000 $29.110 $36.500 $38.630 $35.800
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $900.000 $1,106.030 $1,100.000 $1,110.000 $1,055.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $2,000.000 $2,910.600 $3,700.000 $3,885.000 $3,700.000
INSTALL LRSS (STRUCT STEEL)
LB 1,515.000 $5.000 $8.150 $5.250 $5.550 $5.250
REMOVE LRSA
EA 5.000 $600.000 $931.390 $840.000 $888.000 $845.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 214.000 $100.000 $139.710 $140.000 $149.850 $145.000
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 79.000 $100.000 $139.710 $140.000 $149.850 $145.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 293.000 $15.000 $20.370 $10.500 $11.100 $10.550
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 83.000 $25.000 $37.100 $37.000 $38.850 $37.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 31.000 $25.000 $37.100 $37.000 $38.850 $37.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 13.000 $15.000 $21.200 $21.000 $22.200 $21.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BR)
EA 13.000 $15.000 $21.200 $21.000 $22.200 $21.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 16,020.000 $1.000 $0.840 $1.050 $1.060 $1.100
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 165.000 $0.750 $0.370 $0.370 $0.390 $0.370
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 12,014.000 $0.750 $0.830 $0.820 $0.870 $0.820
REFL PAV MRK TY I (W)(NUMBER)(090MIL)
EA 7.000 $300.000 $477.000 $475.000 $499.500 $474.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 42,710.000 $0.350 $0.530 $0.370 $0.390 $0.370
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 188,095.000 $0.350 $0.370 $0.370 $0.390 $0.370
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 186,196.000 $0.350 $0.370 $0.370 $0.390 $0.370
REFL PAV MRKR TY II-C-R
EA 2,304.000 $3.100 $3.180 $3.150 $3.330 $3.150
UNDERSEAL COURSE
GAL 61,375.000 $3.250 $3.580 $3.500 $4.020 $2.750
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $17,000.000 $4,500.700 $10,500.000 $11,099.990 $23,640.000
TMA (STATIONARY)
DAY 43.000 $200.000 $355.140 $275.000 $1,355.640 $635.000
TMA (MOBILE OPERATION)
HR 260.000 $45.000 $60.400 $100.000 $102.860 $63.500
Totals: $7,871,583.900 $7,778,312.158 $7,967,170.830 $8,125,716.537 $8,416,560.465