Show Job Controls
Bid Cobra

POTTER IH 40 (0090-05-097)

Items: 90

County: POTTER
Length: N/A
Highway: IH 40
District: AMARILLO
Control Number: 0090-05-097
DBE Goal: N/A
Project: NH 2018(284)
Guaranty: N/A
Time: 57 WORKING DAYS
Engineer's Estimate: $1,939,896.84
Date: 11/02/2017 (8 years ago)
Contract Number: N/A
Type: INTERSECTION & SAFETY IMPROVEMENTS ADDING TRUN LNS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,939,896.84
$1,771,160.83
Over/Under Est: -8.7% -$168,736.01
Over/Under Est: -0.59% -$11,510.84
Amt Left: 8.88% $157,225.17
$1,993,861.80
Over/Under Est: 2.78% $53,964.96
Amt Left: 12.57% $222,700.97
Delta: -3.40% -$65,475.80
Over/Under Est: 10.81% $209,640.61
Amt Left: 21.36% $378,376.62
Delta: -7.81% -$155,675.65
$2,159,191.26
Over/Under Est: 11.3% $219,294.42
Amt Left: 21.91% $388,030.43
Delta: -0.45% -$9,653.81

Bid Items & Bid Tabulations

90 Total 0 of 90
POTTER  |  IH 40  |  AMARILLO  |  0090-05-097  |  11/02/2017  |  $1,939,896.84  |  NH 2018(284)  |  INTERS & SAFETY IMPRVS ADDING TRUN L...  |  57 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
L A FULLER & SONS CONSTRUCTION, LTD.
RK HALL, LLC
HOLMES CONSTRUCTION CO., L.P.
GILVIN-TERRILL, LTD.
PREPARING ROW
STA 63.120 $200.000 $77.000 $50.000 $200.000 $250.000 $160.000
REMOVING CONC (RIPRAP)
SY 723.000 $20.000 $13.000 $6.500 $27.000 $30.000 $62.000
REMOVING CONC (DRIVEWAYS)
SY 58.000 $24.000 $33.000 $31.600 $55.000 $40.000 $77.000
REMOVING CONC (CURB AND GUTTER)
LF 97.000 $6.000 $5.800 $9.400 $25.000 $20.000 $48.000
REMOVING STAB BASE & ASPH PAV (18")
SY 2,059.000 $8.000 $9.000 $11.900 $11.000 $12.000 $15.000
EXCAVATION (ROADWAY)
CY 105.000 $24.000 $17.200 $46.500 $57.320 $50.000 $30.000
SUBGRADE WIDENING (DENS CONT)
STA 84.630 $550.000 $1,335.000 $615.000 $690.000 $2,000.000 $420.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 692.930 $28.000 $46.000 $48.000 $50.000 $40.000 $22.000
BACKFILL (TY A)
STA 45.700 $150.000 $430.000 $295.000 $435.000 $400.000 $400.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 1.650 $800.000 $1,050.000 $1,360.000 $1,097.800 $4,000.000 $1,000.000
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 1.650 $500.000 $1,050.000 $1,360.000 $1,097.800 $4,000.000 $1,000.000
FL BS (CMP IN PLC)(TY A GR 4)(12")
SY 3,023.000 $25.000 $40.650 $19.200 $50.000 $30.000 $101.000
FLY ASH (CLASS CS)
TON 63.000 $100.000 $81.250 $100.000 $115.000 $100.000 $87.000
FA TREAT SUBGRADE (8")
SY 5,800.000 $7.000 $5.600 $2.600 $9.000 $10.000 $9.000
PRIME COAT (MC-30)
GAL 1,450.000 $5.000 $4.800 $5.800 $4.200 $8.000 $10.000
EMULS ASPH (EROSN CONT)(MS-2)
GAL 581.000 $3.000 $7.600 $6.600 $6.000 $10.000 $14.000
ASPH (AC-10)
GAL 2,181.000 $5.000 $3.200 $4.100 $5.000 $10.000 $21.000
AGGR(TY-B GR-4 SAC-B)
CY 64.000 $200.000 $290.000 $310.000 $375.000 $175.000 $170.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
TON 6,142.000 $130.000 $95.500 $128.000 $130.000 $145.000 $94.000
PLAN & TEXT ASPH CONC PAV(0" TO 1")
SY 667.000 $3.000 $7.100 $7.000 $4.430 $5.200 $8.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 400.000 $5.000 $11.900 $7.200 $8.150 $9.600 $9.000
PLAN & TEXT ASPH CONC PAV(0" TO 3")
SY 2,674.000 $5.000 $7.550 $8.000 $4.800 $5.400 $9.000
PLAN & TEXT CONC PAV(0" TO 1-1/2")
SY 185.000 $5.000 $10.250 $8.000 $18.220 $24.000 $15.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,512.000 $5.000 $9.450 $8.400 $8.580 $11.000 $10.000
PLAN & TEXT ASPH CONC PAV (1.5")
SY 200.000 $5.000 $7.600 $7.800 $17.170 $22.000 $14.000
CUT & RESTORING PAV
SY 11.000 $150.000 $540.000 $220.000 $355.000 $300.000 $2,182.000
FLOWABLE BACKFILL
CY 14.000 $200.000 $285.000 $185.000 $475.000 $500.000 $255.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 32.000 $250.000 $160.000 $380.000 $165.000 $330.000 $300.000
CL A CONC (FLUME)
CY 136.000 $1,115.000 $685.000 $830.000 $668.250 $700.000 $745.000
RIPRAP (CONC)(4 IN)
CY 117.000 $450.000 $605.000 $720.000 $579.150 $600.000 $530.000
CMP (GAL STL 24 IN)
LF 6.000 $60.000 $310.000 $235.000 $90.000 $150.000 $1,085.000
RC PIPE (CL III)(18 IN)
LF 45.000 $150.000 $135.000 $150.000 $100.000 $150.000 $130.000
RC PIPE (CL III)(30 IN)
LF 24.000 $250.000 $250.000 $240.000 $150.000 $300.000 $160.000
INLET (COMPL)(TY A)
EA 1.000 $1,300.000 $5,800.000 $5,860.000 $5,325.000 $7,500.000 $25,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $10,000.000 $11,000.000 $6,890.000 $12,000.000 $6,000.000 $31,100.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 1.000 $1,500.000 $4,000.000 $1,985.000 $1,600.000 $3,500.000 $3,765.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,200.000 $3,000.000 $3,640.000 $2,250.000 $4,000.000 $5,265.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $1,600.000 $4,800.000 $14,400.000 $3,100.000 $5,000.000 $5,260.000
REMOV STR (INLET)
EA 2.000 $1,000.000 $1,750.000 $1,750.000 $2,000.000 $1,500.000 $2,000.000
REMOV STR (SET)
EA 2.000 $750.000 $1,750.000 $1,450.000 $2,000.000 $500.000 $2,000.000
REMOV STR (PIPE)
LF 41.000 $50.000 $86.000 $54.000 $40.000 $30.000 $200.000
MOBILIZATION
LS 1.000 $187,000.000 $176,000.000 $149,901.460 $190,000.000 $142,000.000 $215,700.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $15,000.000 $14,750.000 $15,650.000 $5,000.000 $5,000.000 $25,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 880.000 $12.000 $9.900 $4.000 $2.500 $15.000 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 880.000 $12.000 $2.500 $0.900 $1.000 $5.000 $1.000
CONC CURB & GUTTER (TY II)
LF 2,026.000 $25.000 $18.450 $23.800 $27.000 $20.000 $18.000
CONCRETE CURB (SPECIAL)
LF 453.000 $50.000 $43.750 $56.500 $46.000 $48.000 $42.000
CONC SIDEWALKS (4")
SY 434.000 $50.000 $56.950 $73.500 $59.000 $62.000 $55.000
CURB RAMPS (TY 1)
EA 7.000 $2,000.000 $1,000.000 $1,300.000 $1,100.000 $1,100.000 $955.000
MTL W-BEAM GD FEN (STEEL POST)
LF 345.000 $23.500 $26.350 $34.000 $32.280 $35.000 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,375.000 $1,055.000 $1,360.000 $1,291.370 $1,500.000 $975.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 23.000 $25.500 $26.350 $34.000 $32.280 $30.000 $24.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,308.000 $3,200.000 $4,100.000 $3,874.110 $3,500.000 $2,150.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 2.000 $265.000 $265.000 $340.000 $322.850 $350.000 $485.000
REMOVE RD IL ASM (TRANS-BASE)
EA 2.000 $600.000 $710.000 $2,725.000 $742.500 $700.000 $600.000
REPLACE LUMINAIRE W/LED (250W EQ)
EA 16.000 $700.000 $790.000 $1,020.000 $825.000 $900.000 $800.000
IN RD IL (TY ST) 40T-8 (250W EQ) LED
EA 2.000 $4,000.000 $3,500.000 $4,900.000 $3,630.000 $4,000.000 $3,500.000
IN RD IL (TY ST) 40T-8-8(250W EQ) LED
EA 2.000 $3,600.000 $3,600.000 $5,450.000 $3,740.000 $5,000.000 $4,500.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 100.000 $30.000 $31.600 $48.000 $33.000 $40.000 $35.000
DCT CBL (3 NO.8) (2 INSULATED 1 BARE)
LF 1,790.000 $15.000 $6.050 $13.600 $6.330 $8.000 $12.000
GROUND BOX TY A (122311)
EA 1.000 $600.000 $740.000 $1,225.000 $770.000 $600.000 $500.000
GROUND BOX TY A (122311)W/APRON
EA 1.000 $1,000.000 $950.000 $2,040.000 $990.000 $1,000.000 $750.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 28.000 $23.000 $31.650 $41.000 $38.740 $175.000 $150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $650.000 $900.000 $1,160.000 $1,097.670 $700.000 $554.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $750.000 $950.000 $1,225.000 $1,162.240 $800.000 $604.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $650.000 $1,530.000 $1,975.000 $1,872.490 $850.000 $627.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $750.000 $1,055.000 $1,360.000 $1,291.370 $1,000.000 $808.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $800.000 $1,185.000 $1,530.000 $1,452.790 $1,000.000 $804.000
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $480.000 $900.000 $1,160.000 $1,097.670 $600.000 $506.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 17.000 $130.000 $160.000 $204.000 $193.710 $150.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 8.000 $130.000 $160.000 $204.000 $193.710 $200.000 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 25.000 $19.000 $15.800 $20.000 $19.370 $30.000 $20.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 14,400.000 $0.500 $0.110 $0.140 $0.110 $0.130 $0.100
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 7,960.000 $0.700 $0.110 $0.140 $0.110 $0.130 $0.100
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 24,000.000 $1.200 $0.820 $1.000 $0.860 $0.900 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 48,000.000 $1.200 $0.820 $1.000 $0.860 $0.900 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,480.000 $1.500 $1.150 $2.000 $1.000 $3.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,323.000 $3.000 $0.890 $1.150 $0.920 $0.990 $1.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 126.000 $5.000 $10.550 $13.600 $11.000 $12.000 $10.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 7.000 $100.000 $100.150 $130.000 $104.500 $105.000 $95.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 7.000 $300.000 $190.000 $245.000 $198.000 $210.000 $180.000
REF PAV MRK TY I(W)18"(YLD TRI)(090MIL)
EA 26.000 $25.000 $12.650 $16.300 $13.200 $14.000 $12.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 600.000 $5.000 $10.550 $13.600 $11.000 $12.000 $10.000
REFL PAV MRK TY I(Y)(MED NOSE)(090MIL)
EA 2.000 $300.000 $285.000 $370.000 $297.000 $320.000 $270.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 1,748.000 $0.300 $0.440 $0.600 $0.460 $0.480 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 6,266.000 $0.300 $0.440 $0.600 $0.460 $0.480 $1.000
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 520.000 $0.300 $0.440 $0.600 $0.460 $0.480 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 17,607.000 $0.300 $0.440 $0.600 $0.460 $0.480 $1.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,200.000 $0.500 $0.760 $1.000 $0.790 $1.000 $1.000
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
EA 1.000 $2,200.000 $3,165.000 $4,800.000 $3,300.000 $3,500.000 $3,500.000
Totals: $1,939,896.840 $1,771,160.830 $1,928,386.000 $1,993,861.800 $2,149,537.450 $2,159,191.260