PREP ROW (TREE) (2" TO 12" DIA)
|
EA
|
5.000
|
$500.000
|
$1,475.000
|
$2,750.000
|
$5,000.000
|
|
|
REMOVING CONC (MEDIANS)
|
SY
|
35.000
|
$30.000
|
$53.000
|
$31.270
|
$25.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
2,659.000
|
$30.000
|
$24.800
|
$20.580
|
$25.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
4,332.000
|
$25.000
|
$5.500
|
$12.630
|
$15.000
|
|
|
REMOVING CONC (MISC)
|
SY
|
32.000
|
$50.000
|
$28.500
|
$34.200
|
$25.000
|
|
|
REMOVING CONC (SIDEWALK OR RAMP)
|
SY
|
2,751.000
|
$55.000
|
$17.750
|
$19.890
|
$25.000
|
|
|
REMOVING STAB BASE & ASPH PAV(14")
|
SY
|
11,992.000
|
$15.000
|
$14.500
|
$36.500
|
$20.000
|
|
|
REMOVING STAB BASE & ASPH PAV (0-2")
|
SY
|
14,164.000
|
$5.000
|
$4.000
|
$38.630
|
$7.500
|
|
|
IRRIGATION SYSTEM
|
LS
|
1.000
|
$130,000.000
|
$95,200.000
|
$300,000.000
|
$20,000.000
|
|
|
PLANT MATERIAL (5-GAL)
|
EA
|
92.000
|
$75.000
|
$92.000
|
$33.000
|
$550.000
|
|
|
PLANT BED PREPARATION
|
SY
|
50.000
|
$125.000
|
$110.000
|
$16.500
|
$20.000
|
|
|
VEGETATION BARRIER
|
SY
|
461.000
|
$30.000
|
$7.500
|
$16.500
|
$20.000
|
|
|
PLANT MATERIAL (65 GAL) (TREE)
|
EA
|
35.000
|
$975.000
|
$1,035.000
|
$1,375.000
|
$1,000.000
|
|
|
PLANT BED PREP (TYPE I)
|
SY
|
461.000
|
$50.000
|
$33.700
|
$16.500
|
$20.000
|
|
|
PLANT SOIL MIX (TY 1)
|
CY
|
307.000
|
$135.000
|
$5.000
|
$275.000
|
$40.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 4)(12")
|
SY
|
9,494.000
|
$40.000
|
$27.450
|
$25.380
|
$50.000
|
|
|
LIME (HYDRATED LIME (SLURRY))
|
TON
|
107.000
|
$325.000
|
$725.000
|
$385.000
|
$400.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
9,846.000
|
$7.500
|
$13.250
|
$6.600
|
$50.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
2,462.000
|
$5.000
|
$8.000
|
$6.600
|
$8.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
1,417.000
|
$45.000
|
$98.200
|
$137.500
|
$146.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
135.000
|
$10.000
|
$491.550
|
$357.500
|
$115.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
568.000
|
$350.000
|
$440.000
|
$357.500
|
$350.000
|
|
|
RIPRAP (MOW STRIP)(6 IN)
|
CY
|
30.500
|
$1,796.000
|
$2,613.250
|
$957.380
|
$2,500.000
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
61.000
|
$160.000
|
$373.250
|
$521.020
|
$700.000
|
|
|
JCTBOX(COMPL)(PJB)(3FTX3FT)
|
EA
|
2.000
|
$7,000.000
|
$28,125.000
|
$13,084.500
|
$20,000.000
|
|
|
JCTBOX(COMPL)(PJB)(4FTX4FT)
|
EA
|
3.000
|
$7,500.000
|
$37,068.550
|
$15,493.500
|
$20,000.000
|
|
|
JCTBOX(COMPL)(PJB)(3FTX5FT)
|
EA
|
1.000
|
$7,500.000
|
$41,078.690
|
$20,905.500
|
$25,000.000
|
|
|
JCTBOX(COMPL)(PJB)(5FTX5FT)
|
EA
|
1.000
|
$8,000.000
|
$38,084.850
|
$25,916.000
|
$25,000.000
|
|
|
INLET (COMPL)(PCO)(4FT)(BOTH)
|
EA
|
7.000
|
$11,000.000
|
$24,332.400
|
$22,286.000
|
$30,000.000
|
|
|
ADJUSTING MANHOLES (ELECTRIC BOX)
|
EA
|
5.000
|
$2,000.000
|
$929.500
|
$1,320.000
|
$1,000.000
|
|
|
REMOV STR (INLET)
|
EA
|
7.000
|
$1,500.000
|
$2,149.750
|
$1,650.000
|
$2,000.000
|
|
|
REMOVE STR (BOLLARD)
|
EA
|
5.000
|
$175.000
|
$206.550
|
$2,040.500
|
$1,500.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$655,000.000
|
$403,129.100
|
$699,006.000
|
$775,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$15,000.000
|
$41,898.950
|
$27,500.000
|
$60,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
1,260.000
|
$8.500
|
$10.000
|
$11.000
|
$8.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,260.000
|
$2.000
|
$3.000
|
$5.500
|
$4.000
|
|
|
LANDSCAPE PAVERS
|
SY
|
1,891.000
|
$234.000
|
$200.850
|
$154.000
|
$100.000
|
|
|
LANDSCAPE PAVERS (TYPE I)
|
SY
|
6.000
|
$360.000
|
$285.250
|
$275.000
|
$100.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
3,119.000
|
$50.000
|
$32.800
|
$62.510
|
$30.000
|
|
|
CONC CURB (SLOTTED)
|
LF
|
751.000
|
$35.000
|
$37.750
|
$62.510
|
$32.000
|
|
|
CONC CURB & GUTTER (VALLEY GUTTER)
|
LF
|
312.000
|
$125.000
|
$48.200
|
$74.740
|
$45.000
|
|
|
CONCRETE CURB (SPECIAL)
|
LF
|
564.000
|
$100.000
|
$51.180
|
$97.110
|
$55.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
2,651.000
|
$120.000
|
$75.150
|
$134.510
|
$125.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
1,311.000
|
$90.000
|
$60.550
|
$120.610
|
$80.000
|
|
|
CONC SIDEWALKS (6")
|
SY
|
2,215.000
|
$120.000
|
$69.500
|
$145.240
|
$85.000
|
|
|
CURB RAMPS (TY 5)
|
EA
|
2.000
|
$3,000.000
|
$2,439.980
|
$3,146.820
|
$2,200.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
33.000
|
$2,250.000
|
$2,005.100
|
$3,146.820
|
$1,550.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
1.000
|
$2,500.000
|
$2,152.750
|
$3,146.820
|
$1,575.000
|
|
|
REMOVE RD IL ASM (SHOE-BASE)
|
EA
|
36.000
|
$100.000
|
$1,760.000
|
$825.000
|
$800.000
|
|
|
IN RD IL (TY SA) 40S-10 (250W EQ) LED
|
EA
|
18.000
|
$9,000.000
|
$6,280.000
|
$5,885.000
|
$5,500.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
4,410.000
|
$20.000
|
$26.500
|
$24.480
|
$25.000
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
2,750.000
|
$30.000
|
$37.600
|
$35.200
|
$32.000
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
215.000
|
$48.000
|
$50.000
|
$46.480
|
$45.000
|
|
|
CONDT (RM) (2")
|
LF
|
15.000
|
$90.000
|
$118.000
|
$110.000
|
$100.000
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
7,260.000
|
$2.200
|
$3.400
|
$2.090
|
$3.000
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
15,660.000
|
$2.850
|
$4.000
|
$3.690
|
$3.500
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
4.000
|
$2,000.000
|
$2,270.000
|
$2,128.500
|
$2,000.000
|
|
|
ELC SRV TY A 240/480 060(NS)SS(E)PS(U)
|
EA
|
1.000
|
$15,000.000
|
$11,300.000
|
$10,587.500
|
$9,650.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$800.000
|
$1,440.000
|
$1,100.000
|
$1,500.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
20.000
|
$500.000
|
$1,440.000
|
$605.000
|
$1,000.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
312.000
|
$0.750
|
$2.850
|
$2.700
|
$5.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
7,959.000
|
$0.350
|
$0.700
|
$0.660
|
$0.200
|
|
|
PAVEMENT SEALER 8"
|
LF
|
312.000
|
$0.400
|
$0.800
|
$0.750
|
$0.200
|
|
|
PAVEMENT SEALER 24"
|
LF
|
1,781.000
|
$2.000
|
$1.750
|
$1.650
|
$2.250
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
1,321.000
|
$0.500
|
$2.600
|
$2.480
|
$2.250
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
1,142.000
|
$0.250
|
$1.500
|
$1.460
|
$2.250
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
5,496.000
|
$1.000
|
$1.500
|
$1.420
|
$2.250
|
|
PREFAB PAV MRK TY B (W)(24")(SLD)
|
LF
|
1,781.000
|
$20.000
|
$41.500
|
$39.600
|
$20.000
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
20.000
|
$850.000
|
$777.000
|
$742.500
|
$250.000
|
|
PREFAB PAV MRK TY C (MULTI) (SHIELD)
|
EA
|
6.000
|
$19,600.000
|
$6,760.000
|
$6,462.500
|
$25,000.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
2.000
|
$15,000.000
|
$6,280.000
|
$5,885.000
|
$5,500.000
|
|
|
INSTALL HWY TRF SIG (UPGRADE)
|
EA
|
2.000
|
$20,000.000
|
$9,115.000
|
$8,541.500
|
$8,000.000
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
16.000
|
$870.000
|
$1,000.000
|
$935.000
|
$850.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
|
LF
|
140.000
|
$5.000
|
$5.250
|
$4.900
|
$5.000
|
|
|
TRF SIG CBL (TY A)(14 AWG)(10 CONDR)
|
LF
|
1,360.000
|
$6.000
|
$7.500
|
$6.990
|
$7.000
|
|
|
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
|
LF
|
2,340.000
|
$2.650
|
$3.800
|
$3.520
|
$3.500
|
|
|
PED POLE ASSEMBLY
|
EA
|
10.000
|
$4,500.000
|
$5,990.000
|
$5,610.000
|
$5,100.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
16.000
|
$950.000
|
$1,145.000
|
$1,072.500
|
$1,000.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
2.000
|
$5,000.000
|
$5,225.000
|
$4,895.000
|
$4,500.000
|
|
|
LANDSCAPE AMENITY (TY 1)
|
EA
|
12.000
|
$750.000
|
$170.000
|
$5,500.000
|
$1,000.000
|
|
|
LANDSCAPE AMENITY (TY 2)
|
EA
|
10.000
|
$2,000.000
|
$870.000
|
$1,650.000
|
$1,000.000
|
|
|
LANDSCAPE AMENITY (TY 3)
|
EA
|
6.000
|
$4,550.000
|
$3,325.000
|
$1,650.000
|
$1,000.000
|
|
|
TREE PROTECTION
|
EA
|
105.000
|
$35.000
|
$368.000
|
$165.000
|
$1,000.000
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
|
CY
|
65.000
|
$500.000
|
$85.000
|
$440.000
|
$100.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
1,394.000
|
$120.000
|
$150.000
|
$214.500
|
$250.000
|
|
|
D-GR HMA TY-D PG70-28
|
TON
|
2,548.000
|
$150.000
|
$160.000
|
$214.500
|
$300.000
|
|
|
TACK COAT
|
GAL
|
3,240.000
|
$4.500
|
$8.810
|
$8.800
|
$6.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
825.000
|
$4.500
|
$1.750
|
$1.650
|
$1.500
|
|
|
GROUND BOX (PREPARE)
|
EA
|
10.000
|
$550.000
|
$675.000
|
$632.500
|
$600.000
|
|
|
TMA (STATIONARY)
|
DAY
|
260.000
|
$225.000
|
$7.900
|
$1.100
|
$850.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
2,080.000
|
$80.000
|
$34.300
|
$1.100
|
$55.000
|
|
|
INSTALL DECORATIVE LIGHTING ASSEMBLY
|
EA
|
53.000
|
$7,500.000
|
$8,140.000
|
$7,628.500
|
$10,000.000
|
|
Totals: |
$6,223,591.950
|
$5,976,375.145
|
$7,496,510.290
|
$7,978,786.700
|