POLK US0059 (6346-17-001)

Items: 26

County: POLK
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6346-17-001
DBE Goal: N/A
Project: RMC - 634617001
Guaranty: N/A
Time: 64 W
Engineer's Estimate: $432,911.10
Date: 11/05/2019 (6 years ago)
Contract Number: N/A
Type: EROSION REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$432,911.10
$466,419.50
Over/Under Est: 7.74% $33,508.40
Over/Under Est: 30.49% $132,001.90
Amt Left: 21.12% $98,493.50
Over/Under Est: 57.45% $248,712.90
Amt Left: 46.14% $215,204.50
Delta: -20.66% -$116,711.00
$1,037,886.00
Over/Under Est: 139.75% $604,974.90
Amt Left: 122.52% $571,466.50
Delta: -52.27% -$356,262.00

Bid Items & Bid Tabulations

26 Total 0 of 26
POLK  |  US0059  |  LUFKIN  |  6346-17-001  |  11/05/2019  |  $432,911.10  |  RMC - 634617001  |  EROSION REPAIR  |  64 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
AAD CONTRACTING INC.
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
A. L. HELMCAMP, INC.
REMOVING CONC (MISC)
SY 100.000 $125.000 $30.000 $30.000 $30.000 $145.000
EXCAVATION (SPECIAL)
CY 1,954.000 $30.000 $0.500 $30.000 $30.000 $45.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 2,334.000 $40.000 $50.000 $30.000 $50.000 $50.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,323.000 $5.000 $4.000 $5.000 $10.000 $12.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,323.000 $2.000 $0.500 $2.000 $5.000 $2.000
VEGETATIVE WATERING
MG 26.500 $50.000 $10.000 $50.000 $50.000 $200.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,323.000 $5.000 $3.000 $4.000 $8.000 $8.000
TEMPORARY SPL SHORING
SF 1,575.000 $30.000 $25.000 $45.000 $70.000 $90.000
RETAINING WALL (SPREAD FOOTING)
SF 720.000 $75.000 $90.000 $87.000 $150.000 $250.000
RIPRAP (CONC)(6 IN)
CY 74.000 $450.000 $700.000 $500.000 $650.000 $900.000
MOBILIZATION
LS 1.000 $39,310.100 $95,000.000 $50,000.000 $70,000.000 $95,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $6,000.000 $22,000.000 $8,500.000 $35,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 20.000 $30.000 $20.000 $40.000 $30.000 $150.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $10.000 $12.000 $5.000 $15.000 $30.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $30.000 $25.000 $20.000 $40.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $10.000 $10.000 $5.000 $20.000 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 270.000 $10.000 $3.000 $5.000 $4.000 $9.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 270.000 $5.000 $1.000 $1.000 $2.000 $3.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 120.000 $65.000 $60.000 $120.000 $70.000 $200.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 120.000 $15.000 $30.000 $50.000 $30.000 $80.000
CONC CURB (TY I)
LF 280.000 $35.000 $15.000 $50.000 $35.000 $75.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,200.000 $300.000 $2,000.000 $3,000.000 $4,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $10,000.000 $10,000.000 $20,000.000 $17,500.000 $15,000.000
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 720.000 $2.000 $12.000 $3.000 $3.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,000.000 $8,000.000 $15,000.000 $10,000.000 $15,000.000
TMA (STATIONARY)
DAY 50.000 $200.000 $100.000 $300.000 $550.000 $800.000
Totals: $432,911.100 $466,419.500 $564,913.000 $681,624.000 $1,037,886.000