Show Job Controls
Bid Cobra

POLK FM0350 (6331-09-001)

Items: 34

County: POLK
Length: N/A
Highway: FM0350
District: LUFKIN
Control Number: 6331-09-001
DBE Goal: N/A
Project: RMC - 633109001
Guaranty: N/A
Time: 50 W
Engineer's Estimate: $393,819.00
Date: 03/05/2020 (6 years ago)
Contract Number: N/A
Type: DRAINAGE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$393,819.00
$390,243.00
Over/Under Est: -0.91% -$3,576.00

Bid Items & Bid Tabulations

34 Total 0 of 34
POLK  |  FM0350  |  LUFKIN  |  6331-09-001  |  03/05/2020  |  $393,819.00  |  RMC - 633109001  |  DRAINAGE REPAIR  |  50 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
SJ&J CONSTRUCTION, LLC
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 1,156.000 $35.000 $30.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 44.000 $130.000 $100.000
BLOCK SODDING
SY 416.000 $15.000 $4.000
VEGETATIVE WATERING
MG 4.300 $150.000 $10.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 496.000 $4.000 $3.500
CEM STABIL BKFL
CY 143.000 $150.000 $180.000
CUT & RESTORE ASPH PAVING
SY 83.000 $200.000 $95.000
TRENCH EXCAVATION PROTECTION
LF 134.000 $30.000 $35.000
TEMPORARY SPL SHORING
SF 882.000 $30.000 $35.000
CL C CONC (COLLAR)
EA 1.000 $700.000 $500.000
CL E CONC (SEAL SLAB)
CY 3.000 $500.000 $500.000
RIRRAP (STONE COMMON)(DRY)(15 IN)
CY 44.000 $225.000 $180.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 17.000 $330.000 $220.000
CONC BOX CULV (8 FT X 4 FT)
LF 120.000 $492.000 $800.000
RC PIPE (CL III)(24 IN)
LF 148.000 $120.000 $120.000
INLET (COMPL)(PSL)(RC)(3FTX3FT)
EA 1.000 $7,000.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 60 IN)
EA 1.000 $10,000.000 $12,000.000
HEADWALL (CH - PW - 0) (DIA= 66 IN)
EA 1.000 $12,500.000 $15,000.000
HEADWALL (CH - PW - 0) (DIA= 72 IN)
EA 1.000 $13,500.000 $15,000.000
WINGWALL (PW - 2) (HW=5 FT)
EA 2.000 $12,000.000 $9,000.000
SET (REPLACE PIPE RUNNER ASSEMBLY)
EA 2.000 $2,500.000 $1,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,300.000 $1,500.000
REMOV & RE - LAY PIPE (24 IN)
LF 8.000 $100.000 $90.000
REMOV STR (PIPE)
LF 177.000 $30.000 $35.000
MOBILIZATION
LS 1.000 $40,000.000 $37,200.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $4,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,400.000 $4.500 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,400.000 $1.500 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $25.000 $29.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $2.700 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,500.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $500.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 10.000 $75.000 $40.000
TMA (STATIONARY)
DAY 42.000 $400.000 $150.000
Totals: $393,819.000 $390,243.000