Show Job Controls
Bid Cobra

PARKER IH0020 (6349-72-001)

Items: 38

County: PARKER
Length: N/A
Highway: IH0020
District: FORT WORTH
Control Number: 6349-72-001
DBE Goal: N/A
Project: RMC - 634972001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $938,794.76
Date: 01/10/2020 (6 years ago)
Contract Number: N/A
Type: GUARDRAIL AND CABLE BARRIER REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$938,794.76
$880,650.00
Over/Under Est: -6.19% -$58,144.76
Over/Under Est: -1.21% -$11,344.76
Amt Left: 5.31% $46,800.00
$1,173,340.00
Over/Under Est: 24.98% $234,545.24
Amt Left: 33.24% $292,690.00
Delta: -26.51% -$245,890.00
Over/Under Est: 48.91% $459,205.24
Amt Left: 58.75% $517,350.00
Delta: -19.15% -$224,660.00

Bid Items & Bid Tabulations

38 Total 0 of 38
PARKER  |  IH0020  |  FORT WORTH  |  6349-72-001  |  01/10/2020  |  $938,794.76  |  RMC - 634972001  |  GUARDRAIL AND CABLE BARRIER REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VANN/ELLI, INC.
ELITE CASTLE RESOURCES LLC
SJ&J CONSTRUCTION, LLC
MARCOM'S MOWING SERVICE, LLC
MOBILIZATION (CALLOUT)
EA 24.000 $1,176.560 $100.000 $1.000 $150.000 $500.000
MOBILIZATION (EMERGENCY)
EA 5.000 $866.190 $300.000 $500.000 $3,000.000 $1,000.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 250.000 $25.000 $105.000 $20.000 $33.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,794.250 $2,000.000 $800.000 $2,000.000 $1,950.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 25.000 $1,645.680 $1,100.000 $800.000 $1,650.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $2.560 $2.000 $2.000 $3.250 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,902.940 $2,700.000 $3,500.000 $3,000.000 $3,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $2,000.000 $2,000.000 $1,000.000 $2,900.000 $4,000.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 15,000.000 $11.250 $10.500 $18.000 $23.000 $22.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 100.000 $24.280 $40.000 $22.000 $50.000 $55.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $26.370 $40.000 $30.000 $50.000 $55.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 100.000 $25.960 $20.000 $25.000 $23.000 $50.000
RAISE RAIL ELEMENT
LF 2,500.000 $6.120 $5.000 $10.000 $10.000 $10.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 1,500.000 $43.400 $40.000 $5.000 $55.000 $80.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 50.000 $39.560 $50.000 $55.000 $63.000 $85.000
REALIGN POSTS
EA 250.000 $7.350 $15.000 $10.000 $21.000 $20.000
REMOVE & REPLACE BLOCKOUT
EA 800.000 $22.590 $25.000 $100.000 $12.000 $20.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 2,000.000 $10.860 $15.000 $4.000 $50.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 160.000 $87.630 $50.000 $80.000 $53.000 $100.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 60.000 $2,701.740 $2,800.000 $3,000.000 $3,100.000 $3,750.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 20.000 $830.300 $780.000 $550.000 $950.000 $1,200.000
REM & RESET SGT IMPACT HEAD
EA 10.000 $32.500 $100.000 $100.000 $250.000 $250.000
REPLACE SGT CABLE ASSEMBLY
EA 40.000 $77.060 $20.000 $50.000 $3.000 $110.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $73.560 $90.000 $50.000 $8.000 $110.000
REPLACE SGT STRUT
EA 20.000 $60.640 $90.000 $50.000 $80.000 $110.000
REPLACE SGT OBJECT MARKER
EA 20.000 $94.140 $40.000 $40.000 $35.000 $50.000
REPLACE POSTS (TL-3)
EA 1,500.000 $130.000 $140.000 $150.000 $130.000 $200.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 5.000 $238.890 $300.000 $50.000 $220.000 $250.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 5.000 $73.810 $50.000 $50.000 $210.000 $250.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 6.000 $1,016.670 $1,000.000 $80.000 $1,400.000 $1,500.000
REPLACE CABLE (TL-3)
LF 1,000.000 $3.500 $4.000 $2.000 $5.000 $4.000
CHECK / RE-TENSION CABLE
EA 25.000 $763.890 $400.000 $100.000 $180.000 $500.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 20.000 $16.820 $50.000 $50.000 $60.000 $60.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 200.000 $7.000 $10.000 $6.000 $5.000 $5.000
REPAIR (TRACC)
EA 2.000 $3,458.330 $5,000.000 $1,500.000 $3,300.000 $5,000.000
REPAIR (WIDE TRACC)
EA 4.000 $4,666.670 $6,000.000 $850.000 $70.000 $7,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 4.000 $73.140 $200.000 $924.000 $200.000 $500.000
TMA (STATIONARY)
DAY 200.000 $273.360 $50.000 $1.000 $125.000 $300.000
Totals: $938,794.760 $880,650.000 $927,450.000 $1,173,340.000 $1,398,000.000