PARKER IH0020 (6331-16-001)

Items: 50

County: PARKER
Length: N/A
Highway: IH0020
District: FORT WORTH
Control Number: 6331-16-001
DBE Goal: N/A
Project: RMC - 633116001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $685,827.86
Date: 09/06/2018 (7 years ago)
Contract Number: N/A
Type: GUARDRAIL AND CABLE BARRIER REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$685,827.86
$702,677.20
Over/Under Est: 2.46% $16,849.34
$739,804.00
Over/Under Est: 7.87% $53,976.14
Amt Left: 5.28% $37,126.80
$861,300.00
Over/Under Est: 25.59% $175,472.14
Amt Left: 22.57% $158,622.80
Delta: -16.42% -$121,496.00
Over/Under Est: 26.35% $180,692.14
Amt Left: 23.32% $163,842.80
Delta: -0.61% -$5,220.00
Over/Under Est: 59.6% $408,772.14
Amt Left: 55.78% $391,922.80
Delta: -26.32% -$228,080.00

Bid Items & Bid Tabulations

50 Total 0 of 50
PARKER  |  IH0020  |  FORT WORTH  |  6331-16-001  |  09/06/2018  |  $685,827.86  |  RMC - 633116001  |  GUARDRAIL AND CABLE BARRIER REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ELITE CASTLE RESOURCES LLC
DBI SERVICES, LLC
VANN/ELLI, INC.
SJ&J CONSTRUCTION, LLC
MARCOM'S MOWING SERVICE, LLC
MOBILIZATION (CALLOUT)
EA 24.000 $427.190 $2.800 $500.000 $1,000.000 $600.000 $500.000
MOBILIZATION (EMERGENCY)
EA 24.000 $467.010 $2.500 $700.000 $1,000.000 $1,800.000 $1,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,000.000 $22.140 $28.000 $17.000 $23.000 $22.000 $24.500
MTL THRIE-BEAM GD FEN (TIM POST)
LF 500.000 $25.250 $25.000 $26.000 $30.000 $80.000 $50.000
TERMINAL ANCHOR SECTION
EA 4.000 $127.760 $200.000 $600.000 $600.000 $1,796.000 $750.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,464.450 $1,800.000 $1,220.000 $1,900.000 $1,750.000 $1,950.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 200.000 $8.780 $15.000 $2.500 $20.000 $12.000 $8.000
TERMINAL ANCHOR SECTION ADJUSTMENT
EA 2.000 $76.760 $250.000 $165.000 $500.000 $60.000 $550.000
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $2.600 $6.000 $2.000 $2.000 $3.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $264.760 $500.000 $41.000 $100.000 $250.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,448.450 $4,000.000 $2,950.000 $3,000.000 $2,879.000 $3,500.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 1.000 $356.670 $1,000.000 $650.000 $1,200.000 $1,000.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $157.240 $800.000 $165.000 $100.000 $300.000 $500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $752.780 $2,000.000 $165.000 $1,000.000 $800.000 $3,500.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 10,000.000 $13.880 $18.000 $11.000 $18.000 $19.330 $21.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 100.000 $20.210 $5.000 $16.000 $40.000 $21.250 $45.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $16.190 $5.000 $30.000 $40.000 $22.000 $50.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 100.000 $26.710 $10.000 $27.000 $20.000 $28.000 $40.000
RAISE RAIL ELEMENT
LF 100.000 $4.620 $5.000 $3.500 $15.000 $2.800 $8.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 1,000.000 $33.070 $20.000 $32.000 $65.000 $74.000 $65.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 30.000 $29.290 $50.000 $60.000 $70.000 $55.000 $75.000
REPAIR STEEL POST WITH BASE PLATE
EA 4.000 $168.310 $200.000 $320.000 $300.000 $180.000 $350.000
REALIGN POSTS
EA 250.000 $25.000 $1.000 $8.000 $20.000 $25.000 $25.000
REMOVE & REPLACE BLOCKOUT
EA 800.000 $9.230 $15.000 $15.000 $20.000 $11.500 $20.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 2,000.000 $29.570 $10.000 $20.000 $25.000 $24.500 $25.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 160.000 $32.720 $100.000 $40.000 $100.000 $52.000 $80.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 2.000 $24.030 $50.000 $80.000 $100.000 $21.000 $300.000
REPLACE TERMINAL ANCHOR POSTS
EA 10.000 $65.730 $50.000 $16.000 $500.000 $84.000 $300.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 30.000 $2,639.300 $2,900.000 $2,500.000 $2,750.000 $2,850.000 $3,500.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 20.000 $921.630 $1,000.000 $900.000 $800.000 $910.000 $1,100.000
REM & RESET SGT IMPACT HEAD
EA 20.000 $58.780 $100.000 $80.000 $100.000 $70.000 $250.000
REPLACE SGT CABLE ASSEMBLY
EA 40.000 $75.880 $60.000 $120.000 $100.000 $80.000 $125.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $83.130 $60.000 $110.000 $100.000 $68.000 $125.000
REPLACE SGT STRUT
EA 20.000 $81.850 $80.000 $90.000 $100.000 $85.000 $125.000
REPLACE SGT OBJECT MARKER
EA 20.000 $22.650 $20.000 $40.000 $50.000 $75.000 $50.000
REPLACE POSTS (TL-3)
EA 1,300.000 $78.680 $125.000 $81.000 $100.000 $83.000 $125.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 6.000 $160.960 $200.000 $380.000 $300.000 $145.000 $250.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 6.000 $188.880 $50.000 $200.000 $50.000 $300.000 $200.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 6.000 $595.270 $500.000 $1,400.000 $1,500.000 $475.000 $2,500.000
REPLACE CABLE (TL-3)
LF 1,000.000 $3.940 $3.000 $4.000 $4.000 $1.480 $4.000
CHECK / RE-TENSION CABLE
EA 5.000 $119.720 $500.000 $25.000 $1,000.000 $170.000 $500.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 1,000.000 $5.730 $15.000 $18.000 $10.000 $5.890 $8.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 1,000.000 $40.450 $15.000 $85.000 $30.000 $47.000 $60.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 200.000 $3.130 $15.000 $5.000 $2.000 $3.500 $8.000
RMV/REPL(VIA-SAND FILL PLASTIC BARRELS)
EA 10.000 $408.340 $350.000 $350.000 $500.000 $428.000 $500.000
REPAIR (TRACC)
EA 2.000 $2,315.000 $5,000.000 $3,300.000 $8,000.000 $2,915.000 $8,000.000
REPAIR (WIDE TRACC)
EA 4.000 $1,901.000 $5,000.000 $4,700.000 $11,000.000 $3,000.000 $8,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 4.000 $161.470 $500.000 $540.000 $200.000 $150.000 $250.000
TMA (STATIONARY)
EA 255.000 $254.920 $50.000 $340.000 $100.000 $225.000 $500.000
TMA (MOBILE OPERATION)
DAY 5.000 $309.580 $1,000.000 $340.000 $100.000 $85.000 $1,500.000
Totals: $685,827.860 $702,677.200 $739,804.000 $861,300.000 $866,520.000 $1,094,600.000