PARKER MCVOID RD (0902-38-136)
Items: 45
County: PARKER
Length: 0.0000 MILES
Highway: MCVOID RD
District: FORT WORTH
Control Number: 0902-38-136
DBE Goal: 4.0%
Project: BR 2021(857)
Guaranty: $19,000.00
Time: 83 WORKING DAYS
Engineer's Estimate: $940,442.64
Date: 08/08/2025 (10 months ago)
Contract Number: 8253223
Type: BRIDGE REPLACEMENT
Project ID: A00065636
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PARKER MCVOID RD (0902-38-136)
Project Name: N/A
Project: BR 2021(857)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: MCVOID RD @ TRIB. OF WALNUT CREEK
Limits To: .
Project Description: BRIDGE REPLACEMENT
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$940,442.64 | |||
| $829,672.57 |
-11.78%
-$110,770.07
|
|||
| $870,896.00 |
-7.4%
-$69,546.64
|
4.97%
$41,223.43
|
||
| $919,219.55 |
-2.26%
-$21,223.09
|
10.79%
$89,546.98
|
-5.55%
-$48,323.55
|
|
| $938,906.27 |
-0.16%
-$1,536.37
|
13.17%
$109,233.70
|
-2.14%
-$19,686.72
|
|
| $1,045,741.84 |
11.2%
$105,299.20
|
26.04%
$216,069.27
|
-11.38%
-$106,835.57
|
|
| $1,053,361.70 |
12.01%
$112,919.06
|
26.96%
$223,689.13
|
-0.73%
-$7,619.86
|
|
| $1,210,337.05 |
28.7%
$269,894.41
|
45.88%
$380,664.48
|
-14.90%
-$156,975.35
|
|
| $1,311,653.31 |
39.47%
$371,210.67
|
58.09%
$481,980.74
|
-8.37%
-$101,316.26
|
E
Engineer's Estimate
$940,442.64
1
Awarded
$829,672.57
Over/Under Est:
-11.78%
-$110,770.07
$870,896.00
Over/Under Est:
-7.4%
-$69,546.64
Amt Left:
4.97%
$41,223.43
$919,219.55
Over/Under Est:
-2.26%
-$21,223.09
Amt Left:
10.79%
$89,546.98
Delta:
-5.55%
-$48,323.55
$938,906.27
Over/Under Est:
-0.16%
-$1,536.37
Amt Left:
13.17%
$109,233.70
Delta:
-2.14%
-$19,686.72
$1,045,741.84
Over/Under Est:
11.2%
$105,299.20
Amt Left:
26.04%
$216,069.27
Delta:
-11.38%
-$106,835.57
$1,053,361.70
Over/Under Est:
12.01%
$112,919.06
Amt Left:
26.96%
$223,689.13
Delta:
-0.73%
-$7,619.86
$1,210,337.05
Over/Under Est:
28.7%
$269,894.41
Amt Left:
45.88%
$380,664.48
Delta:
-14.90%
-$156,975.35
$1,311,653.31
Over/Under Est:
39.47%
$371,210.67
Amt Left:
58.09%
$481,980.74
Delta:
-8.37%
-$101,316.26
| Subcontractor | Percentage | Amount |
|---|---|---|
| PEACHTREE CONSTRUCTION, LTD. | 6.29% | $52,186.40 |
| HODGES AND SON CONSTRUCTION COMPANY, INC. | 5.89% | $48,867.71 |
| TUCAN CONTRACTING, LLC | 5.18% | $42,977.04 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 2.31% | $19,165.44 |
| FORTSON CONTRACTING, INC. | 2.30% | $19,082.47 |
| TEXOP CONSTRUCTION | 0.82% | $6,803.32 |
| TORO BRAVO CONSTRUCTION, LLC | 0.00% | $0.00 |
| LINEAR TRAFFIC MARKINGS LLC | 0.00% | $0.00 |
| Total: | 22.79% | $189,082.38 |
Bid Items & Bid Tabulations
45
Total
0 of 45
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $15,000.00 |