Show Job Controls
Bid Cobra

PARKER IH 20 (0314-07-081)

Items: 20

County: PARKER
Length: N/A
Highway: IH 20
District: FORT WORTH
Control Number: 0314-07-081
DBE Goal: N/A
Project: F 2024(054)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $449,681.00
Date: 11/01/2023 (2 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
KOREY COBURN
CHADWICK DABBS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$449,681.00
$394,915.00
Over/Under Est: -12.18% -$54,766.00
Over/Under Est: 7.85% $35,319.00
Amt Left: 22.81% $90,085.00
Over/Under Est: 16.94% $76,193.80
Amt Left: 33.16% $130,959.80
Delta: -8.43% -$40,874.80
Over/Under Est: 28.23% $126,939.32
Amt Left: 46.01% $181,705.32
Delta: -9.65% -$50,745.52
Over/Under Est: 46.9% $210,905.00
Amt Left: 67.27% $265,671.00
Delta: -14.56% -$83,965.68
Subcontractor Percentage Amount
JC DIRECTIONAL DRILLING 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

20 Total 0 of 20
PARKER  |  IH 20  |  FORT WORTH  |  0314-07-081  |  11/01/2023  |  $449,681.00  |  F 2024(054)  |  LANDSCAPE DEVELOPMENT  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TIGHT LINE CONSTRUCTION, LLC
CENTRAL NORTH CONSTRUCTION, LLC
C. GREEN SCAPING, L.P.
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
TEXAS ROAD CONSTRUCTION, LLC
PREPARING ROW
AC 0.480 $15,000.000 $30,000.000 $74,000.000 $27,080.000 $54,757.000 $5,000.000
PREP ROW (TREE) (2" TO 12" DIA)
EA 38.000 $500.000 $350.000 $400.000 $731.000 $441.000 $300.000
GENERAL USE COMPOST (2")
SY 1,998.000 $4.000 $3.000 $4.000 $31.500 $8.000 $15.000
IRRIGATION SYSTEM
LS 1.000 $65,000.000 $65,000.000 $127,525.700 $95,400.000 $86,296.000 $155,000.000
WILDFLOWER SEEDING
AC 0.380 $2,000.000 $7,500.000 $5,000.000 $5,800.000 $49,842.000 $3,500.000
PLANT MATERIAL (3-GAL)
EA 3,177.000 $24.000 $20.000 $16.000 $15.000 $32.000 $27.000
MULCH
SY 1,998.000 $4.000 $5.000 $3.000 $5.400 $8.000 $23.000
PLANT MATERIAL (45 GAL) (TREE)
EA 100.000 $400.000 $400.000 $500.000 $445.000 $554.000 $1,000.000
PLANT MATERIAL (65 GAL) (TREE)
EA 35.000 $650.000 $525.000 $900.000 $625.000 $935.000 $1,500.000
CONC LNDSCP EDG (12 IN WIDTH)
LF 1,944.000 $34.000 $20.000 $38.000 $32.000 $26.000 $22.000
PLANT MAINTENANCE
MO 12.000 $1,450.000 $1,500.000 $1,900.000 $3,800.000 $201.000 $750.000
IRRIGATION SYSTEM OPER AND MAINT
MO 12.000 $700.000 $1,000.000 $700.000 $1,100.000 $171.000 $750.000
MOBILIZATION
LS 1.000 $40,880.000 $60,000.000 $25,000.000 $31,800.000 $57,666.000 $60,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,500.000 $4,500.000 $2,500.000 $3,600.000 $13,373.000 $3,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 312.000 $25.000 $5.000 $25.000 $18.000 $68.000 $42.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $10.000 $2.000 $5.000 $9.000 $35.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 2,163.000 $8.500 $3.000 $1.000 $5.400 $3.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,163.000 $2.500 $1.000 $0.100 $2.000 $1.000 $1.000
CONDT (PVC) (SCH 40) (4") (BORE)
LF 75.000 $50.000 $90.000 $43.000 $44.000 $103.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $150.000 $25.000 $100.000 $140.000 $88.000 $75.000
Totals: $449,681.000 $394,915.000 $485,000.000 $525,874.800 $576,620.320 $660,586.000