PARKER IH 20 (0314-07-069)

Items: 38

County: PARKER
Length: N/A
Highway: IH 20
District: FORT WORTH
Control Number: 0314-07-069
DBE Goal: N/A
Project: NH 2019(721)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $1,191,209.70
Date: 04/02/2019 (7 years ago)
Contract Number: N/A
Type: BASE RPR, MILL, OVERLAY, PAVMT MARK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,191,209.70
$925,967.11
Over/Under Est: -22.27% -$265,242.59
Over/Under Est: -21.93% -$261,242.17
Amt Left: 0.43% $4,000.42
Over/Under Est: -18.3% -$217,967.71
Amt Left: 5.11% $47,274.88
Delta: -4.65% -$43,274.46
Over/Under Est: -3.56% -$42,409.70
Amt Left: 24.06% $222,832.89
Delta: -18.04% -$175,558.01
Over/Under Est: -1.24% -$14,792.95
Amt Left: 27.05% $250,449.64
Delta: -2.40% -$27,616.75
Over/Under Est: 6.36% $75,735.25
Amt Left: 36.82% $340,977.84
Delta: -7.70% -$90,528.20
$1,498,861.00
Over/Under Est: 25.83% $307,651.30
Amt Left: 61.87% $572,893.89
Delta: -18.31% -$231,916.05

Bid Items & Bid Tabulations

38 Total 0 of 38
PARKER  |  IH 20  |  FORT WORTH  |  0314-07-069  |  04/02/2019  |  $1,191,209.70  |  NH 2019(721)  |  BASE RPR, MILL, OVERLAY, PAVMT MARK  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NORTHEASTERN PAVERS, LLC
FOUTSCO PAVING COMPANY, LLC
PEACHTREE CONSTRUCTION, LTD.
ED BELL CONSTRUCTION COMPANY
TEXAS MATERIALS GROUP, INC.
EUROVIA ATLANTIC COAST LLC
FNH CONSTRUCTION, LLC
BACKFILL (TY B)
STA 65.000 $190.000 $125.000 $200.000 $235.000 $610.000 $301.000 $350.000 $300.000
D-GR HMA TY-C SAC-A, PG70-28
TON 6,350.000 $120.000 $100.000 $97.500 $86.000 $92.000 $105.000 $114.000 $122.000
FLEX PAVEMNT STRUCT REPAIR (O" TO 12")
SY 442.000 $100.000 $95.000 $80.000 $85.000 $107.000 $66.000 $100.000 $100.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 44,173.000 $2.000 $1.500 $1.500 $2.450 $2.400 $2.300 $2.000 $5.000
RIPRAP (CONC)(4 IN)
CY 35.000 $550.000 $700.000 $675.000 $675.000 $750.000 $500.000 $820.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 24.000 $600.000 $700.000 $675.000 $550.000 $750.000 $500.000 $820.000 $550.000
MOBILIZATION
LS 1.000 $98,800.000 $65,000.000 $65,000.000 $85,000.000 $123,304.320 $115,000.000 $105,000.000 $140,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $16,000.000 $1,500.000 $3,000.000 $4,500.000 $25,000.000 $33,900.000 $18,000.000 $15,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $5.000 $0.010 $2.750 $2.000 $3.750 $3.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $2.500 $0.010 $1.000 $1.000 $2.700 $1.000 $1.500 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $8.000 $0.010 $4.000 $5.000 $4.250 $5.000 $10.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $2.500 $0.010 $1.000 $2.000 $1.100 $1.000 $3.000 $9.000
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $25.000 $23.000 $19.000 $23.000 $57.500 $22.000 $21.750 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 175.000 $35.000 $29.000 $21.000 $25.500 $50.000 $24.000 $24.250 $35.000
TERMINAL ANCHOR SECTION
EA 3.000 $2,100.000 $1,025.000 $950.000 $800.000 $1,350.000 $760.000 $1,100.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 375.000 $5.000 $2.250 $3.000 $2.200 $3.500 $2.250 $3.450 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,500.000 $2,570.000 $2,500.000 $3,250.000 $4,000.000 $3,000.000 $3,000.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $270.000 $230.000 $250.000 $220.000 $275.000 $205.000 $290.000 $1,500.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,870.000 $1.500 $0.950 $0.950 $1.300 $1.000 $0.900 $1.350 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 880.000 $8.000 $5.960 $6.000 $8.500 $6.260 $5.500 $8.600 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 6.000 $135.000 $120.000 $120.000 $170.000 $126.000 $155.050 $175.000 $250.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 2.000 $320.000 $213.000 $210.000 $300.000 $225.000 $310.100 $310.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $155.000 $135.000 $135.000 $190.000 $142.500 $155.050 $200.000 $250.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 2,551.000 $0.400 $0.380 $0.380 $0.530 $0.400 $1.050 $0.550 $1.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 11,602.000 $0.400 $0.320 $0.320 $0.450 $0.340 $1.050 $0.450 $1.000
REFL PAV MRK TY II (W) 8" (SLD)
LF 3,870.000 $0.500 $0.550 $0.550 $0.750 $0.600 $0.550 $0.800 $6.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 880.000 $3.000 $4.000 $4.000 $5.600 $4.250 $2.850 $5.750 $20.000
REFL PAV MRK TY II (W) (ARROW)
EA 6.000 $40.000 $85.000 $85.000 $120.000 $90.000 $51.700 $122.000 $250.000
REFL PAV MRK TY II (W) (DBL ARROW)
EA 2.000 $55.000 $130.000 $130.000 $185.000 $137.500 $77.550 $200.000 $250.000
REFL PAV MRK TY II (W) (WORD)
EA 6.000 $50.000 $113.000 $113.000 $155.000 $120.000 $51.700 $165.000 $250.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 12,120.000 $0.400 $0.320 $0.320 $0.450 $0.340 $1.050 $0.450 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,551.000 $0.500 $0.550 $0.550 $0.750 $0.580 $1.050 $0.800 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,602.000 $0.500 $0.480 $0.480 $0.680 $0.510 $0.650 $0.700 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 12,120.000 $0.500 $0.480 $0.480 $0.680 $0.510 $0.650 $0.700 $1.000
REFL PAV MRKR TY II-C-R
EA 194.000 $7.000 $5.000 $5.000 $7.000 $5.250 $5.200 $7.200 $15.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $120.000 $0.010 $85.000 $75.000 $157.500 $100.000 $400.000 $150.000
TMA (STATIONARY)
EA 3.000 $5,000.000 $0.010 $4,000.000 $13,500.000 $10,000.000 $5,628.000 $18,000.000 $10,000.000
CURB INLET SEDIMENT PROTECTION
LF 100.000 $20.000 $15.000 $10.000 $25.000 $10.000 $10.000 $35.000 $20.000
Totals: $1,191,209.700 $925,967.110 $929,967.530 $973,241.990 $1,148,800.000 $1,176,416.750 $1,266,944.950 $1,498,861.000