Show Job Controls
Bid Cobra

PANOLA US0059 (6476-98-001)

Items: 13

County: PANOLA
Length: 0.0100 MILES
Highway: US0059
District: ATLANTA
Control Number: 6476-98-001
DBE Goal: N/A
Project: RMC - A00212915
Guaranty: $5,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $248,620.00
Date: 02/20/2025 (1 year ago)
Contract Number: 2251905
Type: TREE REMOVAL
Project ID: A00212915
Contract Type: Waived
Project Description: TREE & STUMP REMOVAL WITH TREE TRIMMING - CARTHAGE MAINTENANCE SECTIONTASK #19I17636
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
701 E MAIN, ATLANTA, TX 75551
JASON DUPREE
CHARLOTTE ASLIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$248,620.00
$196,557.00
Over/Under Est: -20.94% -$52,063.00
$227,423.06
Over/Under Est: -8.53% -$21,196.94
Amt Left: 15.7% $30,866.06
Over/Under Est: -5.22% -$12,989.96
Amt Left: 19.88% $39,073.04
Delta: -3.61% -$8,206.98
$247,062.00
Over/Under Est: -0.63% -$1,558.00
Amt Left: 25.69% $50,505.00
Delta: -4.85% -$11,431.96
$317,960.00
Over/Under Est: 27.89% $69,340.00
Amt Left: 61.76% $121,403.00
Delta: -28.70% -$70,898.00
$349,745.00
Over/Under Est: 40.67% $101,125.00
Amt Left: 77.94% $153,188.00
Delta: -10.00% -$31,785.00
$542,618.00
Over/Under Est: 118.25% $293,998.00
Amt Left: 176.06% $346,061.00
Delta: -55.15% -$192,873.00
Subcontractor Percentage Amount
J&H EXCAVATION INC. 100.00% $262,182.00
Total: 100.00% $262,182.00

Bid Items & Bid Tabulations

13 Total 0 of 13
PANOLA  |  US0059  |  ATLANTA  |  6476-98-001  |  02/20/2025  |  $248,620.00  |  RMC - A00212915  |  TREE RMVL  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RHINO EQUITY, LLC
CEHAND SERVICES LLC
CROSS PLUS CONSTRUCTION, LLC
LAKEY, INC.
H. V. CAVER, INC.
CATOCON, INC.
ARBORTRUE LLC
MOBILIZATION (CALLOUT)
EA 3.000 $1,000.000 $1.000 $0.001 $1.000 $500.000 $500.000 $1,000.000 $5,000.000
TMA (STATIONARY)
DAY 50.000 $200.000 $75.000 $0.001 $1.000 $250.000 $250.000 $1,000.000 $1,400.000
TREE TRIMMING / BRUSH REMOVAL
MI 34.560 $2,000.000 $1,800.000 $2,300.000 $1,709.000 $1,700.000 $2,250.000 $3,500.000 $3,300.000
STUMP REMOVAL
EA 10.000 $100.000 $100.000 $0.001 $50.000 $275.000 $75.000 $1.000 $260.000
TREE REMOVAL (4" - 12" DIA)
EA 833.000 $100.000 $70.000 $75.000 $65.000 $40.000 $150.000 $80.000 $110.000
TREE REMOVAL (12" - 18" DIA)
EA 333.000 $100.000 $85.000 $95.000 $95.000 $80.000 $150.000 $95.000 $210.000
TREE REMOVAL (18" - 24" DIA)
EA 200.000 $125.000 $115.000 $125.000 $159.000 $200.000 $150.000 $150.000 $390.000
TREE REMOVAL (24" - 30" DIA)
EA 83.000 $150.000 $125.000 $175.000 $298.000 $400.000 $150.000 $225.000 $580.000
TREE REMOVAL (30" - 36" DIA)
EA 33.000 $150.000 $200.000 $250.000 $500.000 $600.000 $150.000 $425.000 $690.000
TREE REMOVAL (36" - 42" DIA)
EA 8.000 $250.000 $200.000 $300.000 $700.000 $700.000 $150.000 $600.000 $850.000
TREE REMOVAL (42" - 48" DIA)
EA 7.000 $300.000 $200.000 $350.000 $800.000 $1,000.000 $150.000 $700.000 $1,200.000
TREE REMOVAL (48" - 60" DIA)
EA 3.000 $400.000 $1.000 $400.000 $1,000.000 $1,000.000 $150.000 $800.000 $2,300.000
TREE REMOVAL (60" - 72" DIA)
EA 3.000 $400.000 $1.000 $0.001 $1,000.000 $1,000.000 $150.000 $900.000 $2,800.000
Totals: $248,620.000 $196,557.000 $227,423.066 $235,630.040 $247,062.000 $317,960.000 $349,745.000 $542,618.000