PANOLA CR (0919-13-018)

Items: 43

County: PANOLA
Length: N/A
Highway: CR
District: ATLANTA
Control Number: 0919-13-018
DBE Goal: N/A
Project: BR 1902(372)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $450,451.40
Date: 03/03/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (9)
E
Engineer's Estimate
$450,451.40
$489,997.75
Over/Under Est: 8.78% $39,546.35
Over/Under Est: 10.9% $49,119.08
Amt Left: 1.95% $9,572.73
$524,224.24
Over/Under Est: 16.38% $73,772.84
Amt Left: 6.99% $34,226.49
Delta: -4.93% -$24,653.76
Over/Under Est: 18.51% $83,394.60
Amt Left: 8.95% $43,848.25
Delta: -1.84% -$9,621.76
Over/Under Est: 22.49% $101,309.35
Amt Left: 12.6% $61,763.00
Delta: -3.36% -$17,914.75
Over/Under Est: 30.47% $137,272.60
Amt Left: 19.94% $97,726.25
Delta: -6.52% -$35,963.25
Over/Under Est: 32.92% $148,298.60
Amt Left: 22.19% $108,752.25
Delta: -1.88% -$11,026.00
Over/Under Est: 40.86% $184,060.60
Amt Left: 29.49% $144,514.25
Delta: -5.97% -$35,762.00
Over/Under Est: 77.17% $347,591.80
Amt Left: 62.87% $308,045.45
Delta: -25.77% -$163,531.20

Bid Items & Bid Tabulations

43 Total 0 of 43
PANOLA  |  CR  |  ATLANTA  |  0919-13-018  |  03/03/2022  |  $450,451.40  |  BR 1902(372)  |  BRIDGE REPL  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAYFORD'S TRUCK & TRACTOR
HIGHWAY 19 CONSTRUCTION LLC
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
THK CONSTRUCTION LLC
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
ENCINO LANDSCAPE, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
PREPARING ROW
STA 5.100 $3,000.000 $1,450.000 $1,500.000 $2,000.000 $3,500.000 $1,500.000 $3,000.000 $2,500.000 $5,000.000 $6,800.000
EXCAVATION (ROADWAY)
CY 744.000 $9.000 $14.250 $25.000 $12.000 $20.000 $18.000 $20.000 $20.000 $20.000 $18.000
EXCAVATION (CHANNEL)
CY 447.000 $10.000 $16.000 $25.000 $12.000 $20.000 $18.000 $20.000 $30.000 $20.000 $28.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 353.000 $23.000 $15.250 $30.000 $18.000 $20.000 $18.000 $25.000 $37.000 $40.000 $28.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,000.000 $1.000 $3.000 $3.000 $2.500 $2.000 $2.300 $3.000 $6.000 $1.000 $4.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 2,000.000 $0.680 $0.600 $0.550 $0.610 $1.000 $0.580 $0.700 $1.000 $0.150 $1.050
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 500.000 $0.600 $0.600 $0.550 $0.710 $1.000 $0.580 $0.600 $1.000 $0.150 $2.100
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 500.000 $0.600 $0.600 $0.550 $0.710 $1.000 $0.580 $0.600 $1.000 $0.150 $2.100
VEGETATIVE WATERING
MG 48.000 $7.000 $12.000 $10.000 $25.000 $1.000 $10.000 $10.000 $32.000 $1.000 $45.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 500.000 $1.500 $1.300 $2.000 $1.500 $3.000 $1.250 $1.500 $1.500 $4.000 $1.150
CEMENT
TON 16.000 $170.000 $240.000 $250.000 $275.000 $300.000 $300.000 $250.000 $265.000 $300.000 $218.000
CEMENT TREAT (SUBGRADE)(6")
SY 1,026.000 $4.000 $6.250 $18.000 $12.000 $10.000 $21.000 $6.000 $7.000 $4.000 $11.000
PRIME COAT (MC-30)
GAL 257.000 $4.500 $8.000 $25.000 $16.000 $15.000 $20.000 $12.000 $7.500 $10.000 $9.500
CEM STABIL BKFL
CY 31.000 $120.000 $290.000 $180.000 $225.000 $250.000 $330.000 $300.000 $275.000 $200.000 $220.000
DRILL SHAFT (30 IN)
LF 264.000 $125.000 $285.000 $144.920 $275.000 $230.000 $237.000 $280.000 $355.000 $300.000 $273.000
CL C CONC (ABUT)(HPC)
CY 25.200 $1,000.000 $1,195.000 $1,303.000 $1,100.000 $1,000.000 $950.000 $1,200.000 $1,450.000 $1,100.000 $1,850.000
REINF CONC SLAB (BOX BEAM)(HPC)
SF 1,308.000 $20.000 $21.000 $19.000 $24.000 $26.000 $21.000 $20.000 $22.500 $60.000 $26.500
APPROACH SLAB (HPC)
CY 38.500 $550.000 $590.000 $600.000 $700.000 $650.000 $555.000 $700.000 $760.000 $600.000 $973.000
SHEAR KEY
CY 6.600 $325.000 $425.000 $350.000 $600.000 $600.000 $900.000 $500.000 $605.000 $600.000 $707.000
PRESTR CONC BOX BEAM (4B20)
LF 198.000 $200.000 $268.000 $285.000 $227.000 $270.000 $258.500 $350.000 $300.000 $200.000 $219.000
PRESTR CONC BOX BEAM (5B20)
LF 99.000 $205.000 $268.000 $285.000 $244.000 $270.000 $301.000 $350.000 $300.000 $200.000 $219.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 200.000 $125.000 $154.000 $180.000 $170.000 $150.000 $160.000 $190.000 $190.000 $200.000 $208.000
BEDDING MATERIAL (6 IN)
CY 90.000 $99.960 $155.000 $180.000 $170.000 $150.000 $200.000 $190.000 $185.000 $200.000 $165.000
RAIL (TY T223)(HPC)
LF 132.000 $125.000 $135.000 $120.000 $130.000 $130.000 $200.000 $125.000 $125.000 $100.000 $281.000
ARMOR JOINT
LF 24.000 $78.000 $125.000 $180.000 $125.000 $100.000 $125.000 $150.000 $118.000 $100.000 $155.000
ARMOR JOINT (SEALED)
LF 44.300 $95.000 $125.000 $180.000 $125.000 $100.000 $125.000 $130.000 $155.000 $100.000 $160.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $5,500.000 $10,000.000 $7,000.000 $8,000.000 $4,000.000 $10,000.000 $15,000.000 $30,000.000 $16,000.000
MOBILIZATION
LS 1.000 $45,000.000 $38,000.000 $30,000.000 $48,000.000 $48,000.000 $50,000.000 $40,000.000 $20,000.000 $40,000.000 $146,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,000.000 $1,400.000 $2,000.000 $2,000.000 $2,500.000 $1,275.000 $4,000.000 $2,000.000 $5,000.000 $1,950.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 110.000 $30.000 $35.000 $45.000 $34.000 $5.000 $35.000 $35.000 $40.000 $50.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 110.000 $8.000 $11.000 $10.000 $11.000 $1.000 $1.000 $11.000 $12.000 $10.000 $8.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,850.000 $2.750 $3.300 $3.000 $3.200 $1.000 $3.000 $3.500 $3.500 $5.000 $3.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,850.000 $0.750 $0.550 $1.000 $0.600 $1.000 $1.000 $1.000 $1.000 $1.000 $1.050
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $23.000 $32.000 $29.000 $31.000 $30.000 $31.190 $33.000 $32.000 $30.000 $35.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,425.000 $1,225.000 $1,125.000 $1,300.000 $1,300.000 $1,313.000 $1,400.000 $1,380.000 $2,500.000 $1,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,150.000 $1,450.000 $1,318.000 $1,475.000 $1,500.000 $1,470.000 $1,550.000 $1,550.000 $1,500.000 $1,500.000
GDRAIL END TRT(INST)(WOOD POST)(TY I)
EA 2.000 $2,700.000 $3,200.000 $1,318.000 $3,325.000 $3,200.000 $3,334.000 $3,500.000 $3,500.000 $2,600.000 $3,300.000
WIRE FENCE (TY C)
LF 520.000 $18.000 $11.500 $15.000 $17.000 $15.000 $40.000 $22.000 $18.000 $20.000 $16.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $20.000 $20.500 $25.000 $30.000 $30.000 $16.000 $20.000 $17.000 $30.000 $16.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $28.000 $43.500 $35.000 $50.000 $30.000 $47.250 $50.000 $50.000 $40.000 $39.000
ASPHALT-STABILIZED FLEXIBLE BASE
TON 282.000 $160.000 $120.000 $130.000 $165.000 $200.000 $164.000 $175.000 $192.000 $200.000 $395.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 1.000 $250.000 $400.000 $700.000 $432.740 $500.000 $500.000 $500.000 $745.000 $400.000 $1,200.000
TMA (STATIONARY)
DAY 11.000 $110.000 $150.000 $250.000 $150.000 $100.000 $400.000 $300.000 $265.000 $300.000 $200.000
Totals: $450,451.400 $489,997.750 $499,570.480 $524,224.240 $533,846.000 $551,760.750 $587,724.000 $598,750.000 $634,512.000 $798,043.200