PANOLA CR (0919-13-017)

Items: 46

County: PANOLA
Length: N/A
Highway: CR
District: ATLANTA
Control Number: 0919-13-017
DBE Goal: N/A
Project: BR 1902(367)
Guaranty: N/A
Time: 53 WORKING DAYS
Engineer's Estimate: $803,557.63
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$803,557.63
$968,856.50
Over/Under Est: 20.57% $165,298.87
Over/Under Est: 62.17% $499,572.37
Amt Left: 34.5% $334,273.50
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 6.93% $67,141.76
J. H. ODEN CONTRACTING COMPANY 3.44% $33,328.66
DUSTIN ALLEN, INC. 1.89% $18,311.39
PANOLA SIGN & BARRICADE, INC. 0.70% $6,782.00
Total: 12.96% $125,563.81

Bid Items & Bid Tabulations

46 Total 0 of 46
PANOLA  |  CR  |  ATLANTA  |  0919-13-017  |  06/27/2023  |  $803,557.63  |  BR 1902(367)  |  BRIDGE REPL  |  53 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRUE ROADS CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 3.550 $5,215.000 $2,500.000 $30,000.000
EXCAVATION (ROADWAY)
CY 556.000 $17.000 $18.500 $30.000
EXCAVATION (CHANNEL)
CY 250.000 $27.500 $22.000 $30.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 97.000 $18.000 $28.000 $50.000
BLADING
STA 0.600 $300.000 $6,000.000 $1,000.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,280.000 $1.850 $5.000 $3.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 2,280.000 $0.600 $1.600 $2.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 1,140.000 $0.700 $1.600 $2.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 1,140.000 $0.600 $1.600 $2.000
VEGETATIVE WATERING
MG 73.000 $15.900 $13.000 $15.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 50.000 $1.450 $6.500 $3.000
CEMENT
TON 14.000 $255.000 $400.000 $400.000
CEMENT TREAT (SUBGRADE)(6")
SY 766.000 $25.000 $30.000 $20.000
PRIME COAT (MC-30)
GAL 241.000 $6.500 $19.500 $20.000
CEM STABIL BKFL
CY 80.000 $275.000 $400.000 $400.000
TEMPORARY SPL SHORING
SF 600.000 $58.000 $115.000 $45.000
DRILL SHAFT (36 IN)
LF 168.000 $285.000 $435.000 $600.000
CL C CONC (ABUT)
CY 31.400 $1,075.000 $3,200.000 $4,000.000
SHEAR KEY
CY 7.300 $864.250 $1,600.000 $3,000.000
PRESTR CONC BOX BEAM (4B20)
LF 218.000 $315.250 $500.000 $600.000
PRESTR CONC BOX BEAM (5B20)
LF 109.000 $327.250 $500.000 $600.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 276.000 $275.000 $235.000 $300.000
BEDDING MATERIAL (6 IN)
CY 44.000 $242.250 $325.000 $300.000
CLEANING AND SEALING JOINTS (CL 7)
LF 53.000 $75.000 $75.000 $75.000
MULTI-LAYER POLYMER OVERLAY
SY 147.000 $59.250 $220.000 $100.000
RAIL (TY T631LS)
LF 110.000 $71.250 $110.000 $90.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $23,500.000 $10,000.000
MOBILIZATION
LS 1.000 $73,100.000 $95,000.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $8,375.000 $2,200.000 $16,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $36.000 $52.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 80.000 $10.000 $26.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,410.000 $3.640 $6.500 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,410.000 $1.000 $2.000 $2.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 80.000 $75.000 $64.000 $100.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 80.000 $75.000 $64.000 $100.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 80.000 $100.000 $24.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $338.000 $24.000 $10.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 80.000 $100.000 $64.000 $100.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 80.000 $108.000 $64.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 25.000 $25.250 $52.000 $40.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,620.000 $2,400.000 $2,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,300.000 $4,000.000 $3,600.000
WIRE FENCE (TY C)
LF 750.000 $34.000 $25.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $43.500 $65.000 $60.000
ASPHALT-STABILIZED FLEXIBLE BASE
TON 337.000 $180.000 $190.000 $250.000
TMA (MOBILE OPERATION)
DAY 4.000 $491.000 $325.000 $500.000
Totals: $803,557.625 $968,856.500 $1,303,130.000