PANOLA FM 699 (0394-03-045)
Items: 40
County: PANOLA
Length: 0.2000 MILES
Highway: FM 699
District: ATLANTA
Control Number: 0394-03-045
DBE Goal: 0.0%
Project: F 2026(413)
Guaranty: $13,000.00
Time: 63 WORKING DAYS
Engineer's Estimate: $672,433.75
Date: 03/05/2026 (3 months ago)
Contract Number: 3263221
Type: REPLACE CULVERT
Project ID: A00218351
Contract Type: Federal Waived
Project Description: REPLACE CULVERT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JACOB VISE
RYAN GRIFFIN
PANOLA FM 699 (0394-03-045)
Project Name: N/A
Project: F 2026(413)
Length: 0.1000 MILES
Project Type: CONSTRUCTION
Limits From: AT TRIBUTARY OF EIGHT MILE CREEK
Limits To: .
Project Description: REPLACE CULVERT
HARRISON FM 1998 (1920-01-024)
Project Name: FM 1998 AT TRIBUTARY OF EIGHT MILE CREEK
Project: F 2026(413)
Length: 0.1000 MILES
Project Type: CULVERT & STORM DRAINAGE WORK
Limits From: AT TRIBUTARY OF EIGHT MILE CREEK
Limits To: .
Project Description: REPLACE CULVERT
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$672,433.75 | |||
| $492,767.90 |
-26.72%
-$179,665.85
|
|||
| $548,178.40 |
-18.48%
-$124,255.35
|
11.24%
$55,410.50
|
||
| $632,424.03 |
-5.95%
-$40,009.72
|
28.34%
$139,656.13
|
-15.37%
-$84,245.63
|
|
| $710,480.56 |
5.66%
$38,046.81
|
44.18%
$217,712.66
|
-12.34%
-$78,056.53
|
|
| $718,648.00 |
6.87%
$46,214.25
|
45.84%
$225,880.10
|
-1.15%
-$8,167.44
|
|
| $740,406.98 |
10.11%
$67,973.23
|
50.25%
$247,639.08
|
-3.03%
-$21,758.98
|
|
| $796,466.40 |
18.45%
$124,032.65
|
61.63%
$303,698.50
|
-7.57%
-$56,059.42
|
|
| $798,778.00 |
18.79%
$126,344.25
|
62.1%
$306,010.10
|
-0.29%
-$2,311.60
|
|
| $867,807.12 |
29.05%
$195,373.37
|
76.11%
$375,039.22
|
-8.64%
-$69,029.12
|
|
| $905,465.00 |
34.65%
$233,031.25
|
83.75%
$412,697.10
|
-4.34%
-$37,657.88
|
E
Engineer's Estimate
$672,433.75
1
Awarded
$492,767.90
Over/Under Est:
-26.72%
-$179,665.85
$548,178.40
Over/Under Est:
-18.48%
-$124,255.35
Amt Left:
11.24%
$55,410.50
$632,424.03
Over/Under Est:
-5.95%
-$40,009.72
Amt Left:
28.34%
$139,656.13
Delta:
-15.37%
-$84,245.63
$710,480.56
Over/Under Est:
5.66%
$38,046.81
Amt Left:
44.18%
$217,712.66
Delta:
-12.34%
-$78,056.53
$718,648.00
Over/Under Est:
6.87%
$46,214.25
Amt Left:
45.84%
$225,880.10
Delta:
-1.15%
-$8,167.44
$740,406.98
Over/Under Est:
10.11%
$67,973.23
Amt Left:
50.25%
$247,639.08
Delta:
-3.03%
-$21,758.98
$796,466.40
Over/Under Est:
18.45%
$124,032.65
Amt Left:
61.63%
$303,698.50
Delta:
-7.57%
-$56,059.42
$798,778.00
Over/Under Est:
18.79%
$126,344.25
Amt Left:
62.1%
$306,010.10
Delta:
-0.29%
-$2,311.60
$867,807.12
Over/Under Est:
29.05%
$195,373.37
Amt Left:
76.11%
$375,039.22
Delta:
-8.64%
-$69,029.12
$905,465.00
Over/Under Est:
34.65%
$233,031.25
Amt Left:
83.75%
$412,697.10
Delta:
-4.34%
-$37,657.88
Bid Items & Bid Tabulations
40
Total
0 of 40
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| Total: | $7,000.00 |