PANOLA SH 43 (0207-04-038)

Items: 47

County: PANOLA
Length: 20.5900 MILES
Highway: SH 43
District: ATLANTA
Control Number: 0207-04-038
DBE Goal: 3.0%
Project: STP 2B25(087)HES
Guaranty: $69,000.00
Time: 205 WORKING DAYS
Engineer's Estimate: $3,577,550.21
Date: 07/02/2025 (11 months ago) Changed
Contract Number: 7253241
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00192923
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$3,577,550.21
$2,328,377.27
Over/Under Est: -34.92% -$1,249,172.94
$2,620,762.16
Over/Under Est: -26.74% -$956,788.05
Amt Left: 12.56% $292,384.89
Over/Under Est: -23.45% -$838,923.93
Amt Left: 17.62% $410,249.01
Delta: -4.50% -$117,864.12
Over/Under Est: -19.93% -$712,850.16
Amt Left: 23.03% $536,322.78
Delta: -4.60% -$126,073.77
Over/Under Est: -17.24% -$616,761.73
Amt Left: 27.16% $632,411.21
Delta: -3.35% -$96,088.43
Over/Under Est: -12.38% -$442,785.90
Amt Left: 34.63% $806,387.04
Delta: -5.88% -$173,975.83
Over/Under Est: -10.9% -$389,815.71
Amt Left: 36.91% $859,357.23
Delta: -1.69% -$52,970.19
Over/Under Est: -6.33% -$226,280.71
Amt Left: 43.93% $1,022,892.23
Delta: -5.13% -$163,535.00
Over/Under Est: -2.19% -$78,407.68
Amt Left: 50.28% $1,170,765.26
Delta: -4.41% -$147,873.03
$3,539,500.95
Over/Under Est: -1.06% -$38,049.26
Amt Left: 52.02% $1,211,123.68
Delta: -1.15% -$40,358.42
Over/Under Est: 7.9% $282,559.52
Amt Left: 65.79% $1,531,732.46
Delta: -9.06% -$320,608.78
Subcontractor Percentage Amount
JOSH & ERICA ENTERPRISES LLC 31.13% $725,555.40
J. H. ODEN CONTRACTING COMPANY 7.70% $179,466.00
SOUTHWEST ENVIRONMENT SERVICES LLC 2.81% $65,493.44
FLORES CONCRETE 2.63% $61,298.13
DUSTIN ALLEN, INC. 0.92% $21,442.69
PANOLA SIGN & BARRICADE, INC. 0.72% $16,781.24
Total: 45.91% $1,070,036.90

Bid Items & Bid Tabulations

47 Total 0 of 47
PANOLA  |  SH 43  |  ATLANTA  |  0207-04-038  |  07/02/2025  |  $3,577,550.21  |  STP 2B25(087)HES  |  HAZARD ELIM & SAFETY  |  205 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. V. CAVER, INC.
THK CONSTRUCTION LLC
BAKER & COMPANY CONSTRUCTION, LLC
GARRET SHIELDS INFRASTRUCTURE
TRUE ROADS CONSTRUCTION, LLC
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
GREY SKY CONSTRUCTION LLC
LONGVIEW BRIDGE AND ROAD, LTD.
STX CIVIL
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 381.910 $3,000.000 $2,050.000 $2,000.000 $2,340.000 $2,100.000 $2,775.000 $3,300.000 $2,500.000 $1,000.000 $3,500.000 $1,500.000 $3,000.000
REMOV CONC (MOWSTRIP)
SY 187.000 $40.000 $24.750 $20.000 $45.400 $50.000 $55.000 $15.000 $25.000 $50.000 $30.000 $20.000 $30.000
REMOV CONC (RIPRAP)
SY 62.000 $65.000 $25.000 $30.000 $68.500 $50.000 $64.000 $25.000 $25.000 $50.000 $100.000 $20.000 $50.000
REMOV CONC (DRIVEWAYS)
SY 81.000 $32.000 $24.750 $50.000 $105.000 $50.000 $50.000 $25.000 $35.000 $20.000 $25.000 $20.000 $38.000
EMBANK (VEH)(OC)(TY C)
CY 429.250 $66.000 $35.000 $20.000 $31.000 $50.000 $40.000 $35.000 $55.000 $50.000 $230.000 $60.000 $50.000
BLADING
STA 131.750 $200.000 $100.000 $200.000 $473.000 $100.000 $225.000 $300.000 $350.000 $450.000 $95.000 $100.000 $300.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 104,276.000 $0.150 $0.100 $0.130 $0.150 $0.150 $0.120 $0.120 $0.250 $0.300 $0.150 $0.130 $0.500
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 303,621.000 $0.550 $0.520 $0.620 $0.800 $0.550 $0.620 $0.570 $0.450 $0.300 $0.650 $0.670 $1.000
VEGETATIVE WATERING
TGL 5,523.180 $7.000 $0.010 $10.000 $1.000 $20.000 $13.000 $4.000 $10.000 $30.000 $36.000 $50.000 $0.010
CUT & RESTORE ASPH PAVING
SY 396.000 $120.000 $150.000 $150.000 $176.000 $150.000 $90.000 $100.000 $350.000 $200.000 $160.000 $120.000 $225.000
CL C CONC (COLLAR)
EA 33.000 $900.000 $800.000 $1,000.000 $2,875.000 $1,000.000 $1,925.000 $1,500.000 $1,500.000 $1,500.000 $1,500.000 $800.000 $850.000
RIPRAP (CONC)(4 IN)
CY 7.000 $900.000 $600.000 $1,000.000 $1,100.000 $600.000 $1,125.000 $1,000.000 $1,000.000 $550.000 $900.000 $1,000.000 $1,200.000
RIPRAP (MOW STRIP)(4 IN)
CY 40.000 $775.000 $397.650 $800.000 $715.000 $600.000 $855.000 $800.000 $550.000 $550.000 $550.000 $850.000 $1,200.000
RC PIPE (CL III)(18 IN)
LF 2,236.000 $60.000 $47.170 $75.000 $49.000 $60.000 $68.000 $60.000 $52.000 $85.000 $58.000 $100.000 $80.000
RC PIPE (CL III)(24 IN)
LF 286.000 $90.000 $81.680 $100.000 $82.000 $80.000 $90.000 $80.000 $72.000 $105.000 $88.000 $115.000 $190.000
RC PIPE (CL III)(30 IN)
LF 50.000 $125.000 $110.070 $160.000 $245.000 $150.000 $135.000 $120.000 $160.000 $125.000 $118.000 $150.000 $225.000
RC PIPE (CL III)(36 IN)
LF 26.000 $200.000 $154.530 $200.000 $269.000 $200.000 $220.000 $175.000 $184.000 $150.000 $288.000 $260.000 $250.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 504.000 $900.000 $720.000 $900.000 $804.000 $1,200.000 $925.000 $875.000 $950.000 $1,250.000 $820.000 $1,950.000 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 47.000 $1,500.000 $1,175.000 $1,200.000 $1,257.000 $1,200.000 $1,350.000 $1,375.000 $1,325.000 $2,000.000 $1,230.000 $2,650.000 $2,500.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 2.000 $3,500.000 $2,130.000 $3,000.000 $2,850.000 $2,000.000 $2,550.000 $2,500.000 $2,430.000 $4,000.000 $2,000.000 $4,250.000 $5,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $6,600.000 $5,945.150 $3,000.000 $5,993.000 $6,000.000 $5,850.000 $6,000.000 $6,000.000 $8,000.000 $4,000.000 $8,200.000 $5,000.000
CLEAN EXIST CULVERTS
EA 126.000 $2,500.000 $1,050.000 $1,000.000 $505.000 $500.000 $1,175.000 $800.000 $1,000.000 $1,500.000 $1,200.000 $1,500.000 $2,500.000
REMOV STR (HEADWALL)
EA 47.000 $2,025.000 $200.000 $250.000 $1,077.000 $500.000 $255.000 $500.000 $1,000.000 $2,500.000 $1,100.000 $1,000.000 $1,500.000
REMOV STR (PIPE)
LF 2,206.000 $25.000 $20.000 $10.000 $7.700 $10.000 $20.000 $20.000 $50.000 $50.000 $45.000 $25.000 $40.000
MOBILIZATION
LS 1.000 $400,000.000 $193,000.000 $250,000.000 $192,845.000 $300,000.000 $175,000.000 $275,000.000 $350,000.000 $300,000.000 $200,000.000 $250,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $8,000.000 $3,699.870 $1,370.430 $2,382.000 $5,000.000 $3,000.000 $5,000.000 $5,000.000 $15,000.000 $4,500.000 $5,000.000 $1,700.000
TMA (STATIONARY)
DAY 190.000 $375.000 $200.000 $250.000 $362.500 $300.000 $100.000 $300.000 $250.000 $250.000 $236.000 $160.000 $300.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,710.000 $4.750 $3.500 $6.210 $3.850 $5.000 $4.200 $4.000 $4.000 $4.000 $6.500 $5.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,710.000 $2.000 $0.600 $1.610 $1.100 $1.000 $0.700 $0.650 $1.000 $2.000 $1.650 $1.000 $1.000
DRIVEWAYS (CONC) (TY 2)
SY 81.000 $200.000 $153.380 $100.000 $248.000 $120.000 $130.000 $135.000 $120.000 $100.000 $130.000 $150.000 $350.000
MTL W-BEAM GD FEN (TIM POST)
LF 325.000 $30.000 $22.000 $28.400 $24.000 $40.000 $30.000 $28.000 $35.000 $50.000 $29.250 $35.000 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 325.000 $4.000 $4.000 $3.210 $4.500 $5.000 $3.600 $3.250 $5.000 $5.000 $3.300 $3.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $850.000 $400.000 $160.500 $440.000 $500.000 $180.000 $165.000 $250.000 $500.000 $165.000 $285.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,400.000 $2,800.000 $3,210.000 $2,940.000 $3,500.000 $3,600.000 $3,300.000 $3,500.000 $3,850.000 $3,300.000 $3,950.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $450.000 $400.000 $214.000 $440.000 $500.000 $240.000 $220.000 $250.000 $1,500.000 $220.000 $625.000 $350.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 242.000 $340.000 $287.500 $307.090 $316.000 $300.000 $275.000 $325.000 $350.000 $1,000.000 $320.000 $300.000 $300.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 9.000 $450.000 $335.000 $344.540 $355.000 $300.000 $325.000 $355.000 $450.000 $1,000.000 $355.000 $350.000 $375.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 19.000 $850.000 $745.000 $853.860 $878.000 $600.000 $1,055.000 $900.000 $750.000 $1,000.000 $880.000 $1,140.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $820.000 $392.000 $419.440 $431.000 $600.000 $900.000 $450.000 $1,000.000 $1,250.000 $450.000 $960.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $940.000 $490.000 $524.300 $539.000 $700.000 $1,100.000 $550.000 $850.000 $1,250.000 $550.000 $1,180.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 7.000 $1,100.000 $481.000 $514.670 $529.000 $700.000 $1,295.000 $550.000 $850.000 $1,250.000 $530.000 $1,400.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 5.000 $1,100.000 $634.000 $678.380 $697.000 $1,000.000 $1,350.000 $700.000 $850.000 $1,250.000 $700.000 $1,450.000 $1,350.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,100.000 $764.000 $817.480 $840.000 $1,000.000 $1,750.000 $850.000 $1,100.000 $1,250.000 $850.000 $1,900.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 86.000 $600.000 $416.000 $445.120 $458.000 $450.000 $600.000 $465.000 $750.000 $1,250.000 $460.000 $650.000 $600.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 11.000 $800.000 $355.000 $379.850 $390.000 $500.000 $780.000 $400.000 $1,000.000 $1,250.000 $390.000 $845.000 $625.000
REMOVE SM RD SN SUP&AM
EA 121.000 $160.000 $99.000 $105.930 $109.000 $100.000 $130.000 $125.000 $100.000 $50.000 $110.000 $140.000 $150.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 7.000 $45.000 $32.000 $48.150 $35.000 $50.000 $55.000 $50.000 $35.000 $100.000 $50.000 $60.000 $100.000
Totals: $3,577,550.210 $2,328,377.272 $2,620,762.160 $2,738,626.280 $2,864,700.050 $2,960,788.480 $3,134,764.310 $3,187,734.500 $3,351,269.500 $3,499,142.530 $3,539,500.950 $3,860,109.732
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $15,000.00