PALO PINTO SH 16 (0362-02-029)
Items: 65
County: PALO PINTO
Length: 0.5000 MILES
Highway: SH 16
District: FORT WORTH
Control Number: 0362-02-029
DBE Goal: 0.0%
Project: C 362-2-29
Guaranty: $83,000.00
Time: 168 WORKING DAYS
Engineer's Estimate: $4,142,319.40
Date: 10/09/2025 (8 months ago)
Contract Number: 10253217
Type: BRIDGE MAINTENANCE
Project ID: A00214078
Project Description: FOR THE CONSTRUCTION OF BRIDGE MAINTENANCE CONSISTING OF CONCRETE STRUCTURAL REPAIR, RIPRAP, CLEAN & SEAL EXISTING JOINT, CLEAN & PAINT EXISTING STRUCTURE & PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JUSTIN THOMEY
RAUL OROZCO
PALO PINTO SH 16 (0362-02-029)
Project Name: N/A
Project: C 362-2-29
Length: 0.2000 MILES
Project Type: CONSTRUCTION
Limits From: BRIDGE STRUCTURE
Limits To: BRIDGE STRUCTURE
Project Description: FOR THE CONSTRUCTION OF BRIDGE MAINTENANCE CONSISTING OF CONCRETE STRUCTURAL REPAIR, RIPRAP, CLEAN & SEAL EXISTING JOINT, CLEAN & PAINT EXISTING STRUCTURE & PAVEMENT MARKINGS
PALO PINTO FM 4 (0391-08-012)
Project Name: FM 4: 3.5 MI N OF SH 254
Project: C 391-8-12
Length: 0.3000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: BRIDGE STRUCTURE
Limits To: BRIDGE STRUCTURE
Project Description: FUA ON SIMPLE SPAN PS CONCRETE BEAM BRIDGE ON CONCRETE SUBSTRUCTURE
TARRANT VARIOUS (0902-00-363)
Project Name: VARIOUS BRIDGE STRUCTURES (2026)
Project: C 902-00-363
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: VARIOUS LOCATIONS
Limits To: .
Project Description: FOLLOW UP ACTION ITEMS TO VARIOUS BRIDGE STRUCTURES THROUGHOUT THE DISTRICT.
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,142,319.40 | |||
| $4,272,843.10 |
3.15%
$130,523.70
|
|||
| $4,539,237.50 |
9.58%
$396,918.10
|
6.23%
$266,394.40
|
||
| $5,759,345.00 |
39.04%
$1,617,025.60
|
34.79%
$1,486,501.90
|
-26.88%
-$1,220,107.50
|
|
| $6,213,078.75 |
49.99%
$2,070,759.35
|
45.41%
$1,940,235.65
|
-7.88%
-$453,733.75
|
|
| $7,211,509.20 |
74.09%
$3,069,189.80
|
68.78%
$2,938,666.10
|
-16.07%
-$998,430.45
|
E
Engineer's Estimate
$4,142,319.40
1
Awarded
$4,272,843.10
Over/Under Est:
3.15%
$130,523.70
$4,539,237.50
Over/Under Est:
9.58%
$396,918.10
Amt Left:
6.23%
$266,394.40
$5,759,345.00
Over/Under Est:
39.04%
$1,617,025.60
Amt Left:
34.79%
$1,486,501.90
Delta:
-26.88%
-$1,220,107.50
$6,213,078.75
Over/Under Est:
49.99%
$2,070,759.35
Amt Left:
45.41%
$1,940,235.65
Delta:
-7.88%
-$453,733.75
$7,211,509.20
Over/Under Est:
74.09%
$3,069,189.80
Amt Left:
68.78%
$2,938,666.10
Delta:
-16.07%
-$998,430.45
Bid Items & Bid Tabulations
65
Total
0 of 65
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $6,878.88 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $6,878.88 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $98,005.95 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $98,005.95 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $1,844.79 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $100,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $1,844.79 |
| Total: | $313,459.24 |