Show Job Controls
Bid Cobra

PALO PINTO US 180 (0008-01-047)

Items: 22

County: PALO PINTO
Length: N/A
Highway: US 180
District: FORT WORTH
Control Number: 0008-01-047
DBE Goal: 0.0%
Project: F 2B24(228)
Guaranty: N/A
Time: 67 WORKING DAYS
Engineer's Estimate: $337,843.63
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
KOREY COBURN
CHADWICK DABBS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$337,843.63
$263,354.90
Over/Under Est: -22.05% -$74,488.73
$266,888.61
Over/Under Est: -21% -$70,955.02
Amt Left: 1.34% $3,533.71
Over/Under Est: -19.42% -$65,617.47
Amt Left: 3.37% $8,871.26
Delta: -2.00% -$5,337.55
Over/Under Est: -8.69% -$29,344.63
Amt Left: 17.14% $45,144.10
Delta: -13.32% -$36,272.84
Over/Under Est: -5.64% -$19,062.29
Amt Left: 21.05% $55,426.44
Delta: -3.33% -$10,282.34

Bid Items & Bid Tabulations

22 Total 0 of 22
PALO PINTO  |  US 180  |  FORT WORTH  |  0008-01-047  |  07/09/2024  |  $337,843.63  |  F 2B24(228)  |  LANDSCAPE DEVELOPMENT  |  67 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TIGHT LINE CONSTRUCTION, LLC
HJC FARMS, INC.
RARE EARTH LANDSCAPE SOLUTIONS LLC
CENTRAL NORTH CONSTRUCTION, LLC
TEXAS ROAD CONSTRUCTION, LLC
PREPARING ROW
STA 23.000 $1,000.000 $1,000.000 $420.650 $1,386.790 $2,400.000 $1,000.000
PREP ROW (TREE) (2" TO 12" DIA)
EA 8.000 $400.000 $750.000 $432.900 $857.490 $500.000 $550.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
AC 0.201 $5,000.000 $2,500.000 $6,016.840 $1,000.000 $500.000 $5,000.000
FERTILIZER
AC 0.216 $5,000.000 $2,500.000 $3,707.490 $1,000.000 $500.000 $5,000.000
VEGETATIVE WATERING
MG 34.000 $200.000 $50.000 $225.000 $50.000 $5.000 $1.000
IRRIGATION SYSTEM
LS 1.000 $50,000.000 $65,000.000 $19,638.960 $32,848.880 $82,318.910 $100,000.000
PLANT MATERIAL (5-GAL)
EA 458.000 $65.000 $40.000 $58.710 $12.000 $35.000 $35.000
LANDSCAPE EDGE
LF 561.000 $20.000 $15.000 $11.290 $12.000 $10.000 $20.000
PLANT BED PREPARATION
SY 1,046.890 $10.000 $10.000 $15.260 $50.083 $6.000 $6.000
PLANT MAINTENANCE
MO 12.000 $1,500.000 $1,000.000 $468.750 $833.330 $3,250.000 $1,000.000
IRRIGATION SYSTEM OPER AND MAINT
MO 12.000 $1,000.000 $750.000 $468.750 $600.000 $950.000 $750.000
RIPRAP (CONC)(4 IN)
CY 1.150 $1,000.000 $2,500.000 $2,847.180 $3,700.000 $10,000.000 $2,000.000
RIPRAP (SPECIAL)
CY 25.310 $550.000 $350.000 $284.010 $200.000 $625.000 $1,000.000
MOBILIZATION
LS 1.000 $30,000.000 $25,000.000 $15,000.000 $25,000.000 $30,000.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $9,000.000 $3,000.000 $1,095.600 $9,310.300 $800.000 $3,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 4,136.000 $4.500 $3.000 $7.000 $0.010 $0.750 $1.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,136.000 $1.650 $1.000 $1.000 $0.010 $0.100 $1.000
TREE PROTECTION
EA 15.000 $500.000 $350.000 $168.750 $50.000 $10.000 $150.000
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
CY 99.350 $169.000 $200.000 $291.880 $210.000 $150.000 $300.000
LOOSE AGGR FOR GROUNDCOVER (TYPE II)
CY 49.720 $169.000 $200.000 $291.610 $196.000 $95.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $1,500.000 $2,500.000 $19,000.000 $2,134.000 $1,500.000 $75.000
TMA (STATIONARY)
DAY 67.000 $300.000 $1.000 $238.000 $1.000 $10.000 $100.000
Totals: $337,843.630 $263,354.900 $266,888.651 $272,226.162 $308,499.000 $318,781.340