ORANGE FM 1442 (6486-15-001)

Items: 27

County: ORANGE
Length: 0.0100 MILES
Highway: FM 1442
District: BEAUMONT
Control Number: 6486-15-001
DBE Goal: 0.0%
Project: RMC - A00216203
Guaranty: $26,000.00
Time: 24 WORKING DAYS
Engineer's Estimate: $1,067,994.07
Date: 09/05/2025 (9 months ago) Changed
Contract Number: 7252003
Type: ACP OVERLAY
Project ID: A00216203
Project Description: EDGE MILL, UNDERSEAL, 1.5" SMA-F INLAY, PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JIM GRISSOM
BRYCE BROUSSARD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$1,067,994.07
$1,190,491.45
Over/Under Est: 11.47% $122,497.38
Over/Under Est: 15.24% $162,794.53
Amt Left: 3.38% $40,297.15
Subcontractor Percentage Amount
DUSTROL, INC. 2.64% $34,334.13
TRP CONSTRUCTION GROUP, LLC 2.33% $30,302.47
CPAVE, INC. 1.35% $17,557.23
STRUCTURAL INTEGRITY GROUP LLC 0.65% $8,453.48
LONESTAR TRAFFIC SAFETY, LLC 0.34% $4,421.82
Total: 7.31% $95,069.13

Bid Items & Bid Tabulations

27 Total 0 of 27
ORANGE  |  FM 1442  |  BEAUMONT  |  6486-15-001  |  09/05/2025  |  $1,067,994.07  |  RMC - A00216203  |  ACP OVERLAY  |  24 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
ASPH (AC-20-5TR)
GAL 12,535.000 $5.000 $3.400 $4.250
AGGR (TY-PB, GR-4)(SAC-A)
CY 266.000 $180.000 $278.000 $216.000
STONE-MTRX-ASPH SMA-F SAC-A PG76-22
TON 3,046.000 $225.000 $291.750 $292.000
TACK COAT
GAL 1,414.000 $5.000 $3.450 $4.000
PLANE CONC PAV(0" TO 0.5")
SY 5,908.000 $4.500 $5.800 $5.500
PLANE CONC PAV(0" TO 1")
SY 340.000 $6.000 $5.800 $5.500
MOBILIZATION
LS 1.000 $97,090.370 $43,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $6,000.000 $928.000 $4,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $4,500.000 $2,350.000 $4,000.000
TMA (STATIONARY)
DAY 24.000 $650.000 $255.000 $50.000
TMA (MOBILE OPERATION)
DAY 2.000 $650.000 $691.500 $50.000
CONC CURB (MONO) (TY II)
LF 20.000 $225.000 $293.000 $300.000
INTERSECTIONS (ACP)
SY 189.000 $155.000 $108.500 $132.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 830.000 $1.500 $0.500 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,842.000 $1.000 $0.500 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,121.000 $3.500 $1.600 $1.500
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 2,410.000 $0.650 $1.100 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 1,610.000 $0.650 $1.100 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 7,888.000 $0.650 $1.000 $0.950
PREFAB PM TY C (W)(24")(SLD)
LF 191.000 $20.000 $19.500 $18.500
PREFAB PM TY C (W)(ARROW)
EA 26.000 $275.000 $297.000 $280.000
PREFAB PM TY C (W)(DBL ARROW)
EA 2.000 $325.000 $318.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $325.000 $429.000 $405.000
REFL PAV MRKR TY I-C
EA 212.000 $7.000 $6.400 $6.000
REFL PAV MRKR TY II-A-A
EA 334.000 $7.000 $6.400 $6.000
CRACK CLEANING AND SEALING (JCP)
LF 3,545.000 $7.000 $5.250 $5.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 6.000 $275.000 $635.000 $600.000
Totals: $1,067,994.070 $1,190,491.450 $1,230,788.600