ORANGE S BURTON RD (0920-30-090)
Items: 55
County: ORANGE
Length: 0.0000 MILES
Highway: S BURTON RD
District: BEAUMONT
Control Number: 0920-30-090
DBE Goal: 0.0%
Project: BR 2024(171)
Guaranty: $36,000.00
Time: 216 WORKING DAYS
Engineer's Estimate: $1,780,484.90
Date: 05/07/2026 (4 weeks ago)
Contract Number: 5263222
Type: BRIDGE REPLACEMENT
Project ID: A00178374
Contract Type: Federal
Project Description: S BURTON RD @ SANDY CREEK BRIDGE REPLACEMENT (STR#201810AA0237001)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
JIM GRISSOM
ORANGE S BURTON RD (0920-30-090)
Project Name: N/A
Project: BR 2024(171)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: S. BURTON RD @ SANDY CREEK
Limits To: (STR#201810AA0237001)
Project Description: S BURTON RD @ SANDY CREEK BRIDGE REPLACEMENT (STR#201810AA0237001)
ORANGE TRAM (0920-30-092)
Project Name: NORTH TRAM RD@CANEY CREEK (BRIDGE REPLAC
Project: BR 2024(172)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: NORTH TRAM RD@CANEY CREEK
Limits To: (STR#201810AA0443001)
Project Description: NORTH TRAM RD @ CANEY CREEK-BRIDGE REPLACEMENT (STR#201810AA0443001)
ORANGE S TERRY RD (0920-30-091)
Project Name: TERRY RD @ ANDERSON GULLY(BRIDGE REPLACE
Project: BR 2024(183)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: TERRY RD @ ANDERSON GULLY
Limits To: (STR#201810AA0364002)
Project Description: TERRY RD @ ANDERSON GULLY-BRIDGE REPLACEMENT (STR#201810AA0364002)
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,780,484.90 | |||
| $1,783,411.33 |
0.16%
$2,926.43
|
|||
| $1,972,580.50 |
10.79%
$192,095.60
|
10.61%
$189,169.17
|
||
| $2,067,591.15 |
16.13%
$287,106.25
|
15.93%
$284,179.82
|
-4.82%
-$95,010.65
|
E
Engineer's Estimate
$1,780,484.90
1
Awarded
$1,783,411.33
Over/Under Est:
0.16%
$2,926.43
$1,972,580.50
Over/Under Est:
10.79%
$192,095.60
Amt Left:
10.61%
$189,169.17
$2,067,591.15
Over/Under Est:
16.13%
$287,106.25
Amt Left:
15.93%
$284,179.82
Delta:
-4.82%
-$95,010.65
Bid Items & Bid Tabulations
55
Total
0 of 55
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $30,000.00 |