ORANGE FM 105 (0883-02-095)

Items: 29

County: ORANGE
Length: 0.2840 MILES
Highway: FM 105
District: BEAUMONT
Control Number: 0883-02-095
DBE Goal: 0.0%
Project: STP 2026(613)HES
Guaranty: $2,000.00
Time: 23 WORKING DAYS
Engineer's Estimate: $120,196.33
Date: 05/06/2026 (5 weeks ago) Changed
Contract Number: 5263234
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206438
Contract Type: Federal
Project Description: BMT_FM0105_1(2023 HSIP) INCREASE SUPERELEVATION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
JIM GRISSOM
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$120,196.33
$220,722.50
Over/Under Est: 83.63% $100,526.17

Bid Items & Bid Tabulations

29 Total 0 of 29
ORANGE  |  FM 105  |  BEAUMONT  |  0883-02-095  |  05/06/2026  |  $120,196.33  |  STP 2026(613)HES  |  HAZARD ELIM & SAFETY  |  23 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A OR B)
STA 15.000 $167.000 $1,400.000
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 1,667.000 $0.750 $2.000
HYDRO MULCH SEED (TEMP_WARM)
SY 1,667.000 $0.410 $2.000
VEGETATIVE WATERING
TGL 13.800 $50.000 $110.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 1,680.000 $3.200 $10.000
AGGR (TY-PD OR PL, GR-4)
CY 36.000 $200.000 $550.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 190.000 $150.000 $350.000
TACK COAT
GAL 280.000 $15.250 $6.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 23.000 $98.000 $500.000
PLANE ASPH CONC PAV(0" TO 2")
SY 622.000 $8.000 $1.000
MOBILIZATION
LS 1.000 $12,986.030 $22,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,000.000 $2,000.000
TMA (STATIONARY)
DAY 16.000 $300.000 $400.000
TMA (MOBILE OPERATION)
DAY 5.000 $250.000 $1,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $5.250 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $2.700 $1.250
INTERSECTIONS (ACP)
SY 128.000 $70.000 $81.000
DRIVEWAYS (ACP)
SY 182.000 $83.000 $65.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 3,000.000 $0.430 $1.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 1,500.000 $0.400 $1.250
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 3,008.000 $0.210 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 117.000 $2.000 $0.600
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 470.000 $1.400 $0.600
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 78.000 $1.100 $1.500
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 3,008.000 $0.710 $1.100
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 260.000 $0.710 $1.200
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 2,025.000 $0.750 $1.100
PREFAB PM TY C (W)(24")(SLD)
LF 12.000 $20.300 $30.000
REFL PAV MRKR TY II-A-A
EA 33.000 $6.590 $10.000
Totals: $120,196.330 $220,722.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $1,500.00