OCHILTREE US 83 (0030-02-052)
Items: 53
County: OCHILTREE
Length: N/A
Highway: US 83
District: AMARILLO
Control Number: 0030-02-052
DBE Goal: N/A
Project: STP 2019(603)
Guaranty: N/A
Time: 134 WORKING DAYS
Engineer's Estimate: $14,148,589.76
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$14,148,589.76 | |||
| $13,814,377.45 |
-2.36%
-$334,212.31
|
|||
| $15,556,417.92 |
9.95%
$1,407,828.16
|
12.61%
$1,742,040.47
|
||
| $16,053,019.38 |
13.46%
$1,904,429.62
|
16.21%
$2,238,641.93
|
-3.19%
-$496,601.46
|
|
| $16,133,482.79 |
14.03%
$1,984,893.03
|
16.79%
$2,319,105.34
|
-0.50%
-$80,463.41
|
|
| $16,501,942.70 |
16.63%
$2,353,352.94
|
19.45%
$2,687,565.25
|
-2.28%
-$368,459.91
|
|
| $16,833,932.42 |
18.98%
$2,685,342.66
|
21.86%
$3,019,554.97
|
-2.01%
-$331,989.72
|
|
| $17,975,791.37 |
27.05%
$3,827,201.61
|
30.12%
$4,161,413.92
|
-6.78%
-$1,141,858.95
|
E
Engineer's Estimate
$14,148,589.76
1
Awarded
$13,814,377.45
Over/Under Est:
-2.36%
-$334,212.31
$15,556,417.92
Over/Under Est:
9.95%
$1,407,828.16
Amt Left:
12.61%
$1,742,040.47
$16,053,019.38
Over/Under Est:
13.46%
$1,904,429.62
Amt Left:
16.21%
$2,238,641.93
Delta:
-3.19%
-$496,601.46
$16,133,482.79
Over/Under Est:
14.03%
$1,984,893.03
Amt Left:
16.79%
$2,319,105.34
Delta:
-0.50%
-$80,463.41
$16,501,942.70
Over/Under Est:
16.63%
$2,353,352.94
Amt Left:
19.45%
$2,687,565.25
Delta:
-2.28%
-$368,459.91
$16,833,932.42
Over/Under Est:
18.98%
$2,685,342.66
Amt Left:
21.86%
$3,019,554.97
Delta:
-2.01%
-$331,989.72
$17,975,791.37
Over/Under Est:
27.05%
$3,827,201.61
Amt Left:
30.12%
$4,161,413.92
Delta:
-6.78%
-$1,141,858.95
Bid Items & Bid Tabulations
53
Total
0 of 53