Show Job Controls
Bid Cobra

NUECES FM 24 (1556-01-029)

Items: 55

County: NUECES
Length: 0.2980 MILES
Highway: FM 24
District: CORPUS CHRISTI
Control Number: 1556-01-029
DBE Goal: 2.0%
Project: STP 2025(329)HES
Guaranty: $18,000.00
Time: 41 WORKING DAYS
Engineer's Estimate: $877,733.36
Date: 01/08/2025 (1 year ago)
Contract Number: 1253235
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184668
Contract Type: Federal
Project Description: INSTALL LEFT TURN LANE
Mail/Deliver Bids To: N/A
ERNEST LONGORIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$877,733.36
Over/Under Est: -3.55% -$31,157.52
$895,502.05
Over/Under Est: 2.02% $17,768.69
Amt Left: 5.78% $48,926.21
Over/Under Est: 6.99% $61,337.64
Amt Left: 10.93% $92,495.16
Delta: -4.87% -$43,568.95
Over/Under Est: 9.32% $81,820.64
Amt Left: 13.35% $112,978.16
Delta: -2.18% -$20,483.00
Over/Under Est: 11.92% $104,668.64
Amt Left: 16.04% $135,826.16
Delta: -2.38% -$22,848.00
$998,389.85
Over/Under Est: 13.75% $120,656.49
Amt Left: 17.93% $151,814.01
Delta: -1.63% -$15,987.85
Over/Under Est: 22.62% $198,559.44
Amt Left: 27.13% $229,716.96
Delta: -7.80% -$77,902.95
Subcontractor Percentage Amount
HIGHWAY BARRICADES AND SERVICES, LLC 5.21% $46,340.86
THE LEVY COMPANY, LLC 3.46% $30,775.31
Total: 8.67% $77,116.17

Bid Items & Bid Tabulations

55 Total 0 of 55
NUECES  |  FM 24  |  CORPUS CHRISTI  |  1556-01-029  |  01/08/2025  |  $877,733.36  |  STP 2025(329)HES  |  HAZARD ELIM & SAFETY  |  41 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
BAY LTD.
LCR TOTAL TRANSPORT LLC
J E CONSTRUCTION SERVICES, LLC
ANDERSON COLUMBIA CO., INC.
CK NEWBERRY, LLC
J. CARROLL WEAVER, INC.
REMOV CONC (RIPRAP)
CY 5.000 $520.000 $482.990 $3,300.000 $445.000 $114.000 $402.000 $750.000 $336.000
RMV (16"-20") TRT/UNTRT BASE & ASPH PAV
SY 1,134.000 $10.000 $21.620 $11.000 $11.500 $33.000 $25.000 $25.000 $18.330
EXCAV (ROADWAY)
CY 1,703.000 $20.000 $22.190 $11.750 $18.000 $16.000 $14.000 $30.000 $14.090
EMBANK (FNL)(DC)(TY C)
CY 1,167.000 $30.000 $10.140 $10.750 $28.000 $19.000 $59.000 $20.000 $9.010
COMPOST MANUF TOPSOIL (4")
SY 5,724.000 $4.000 $3.960 $8.100 $11.500 $5.000 $6.150 $2.000 $15.450
DRILL SEED (PERM_RURAL_CLAY)
SY 5,724.000 $0.500 $0.550 $0.650 $1.000 $0.500 $0.550 $0.500 $1.850
VEGETATIVE WATERING
TGL 105.000 $50.000 $36.580 $19.250 $84.000 $40.000 $51.000 $20.000 $30.840
FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS
CY 1,181.000 $140.000 $107.900 $150.000 $168.000 $128.000 $103.000 $150.000 $125.250
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 90.000 $350.000 $379.660 $460.000 $330.000 $340.000 $393.000 $375.000 $374.680
LIME TRT (EXIST MATL)(8")
SY 4,534.000 $5.000 $4.770 $6.300 $8.000 $11.000 $6.250 $7.000 $6.040
PRIME COAT (MC-30)
GAL 794.000 $8.000 $7.450 $6.200 $6.500 $8.000 $6.300 $8.000 $5.920
ASPH (CRS-2)
GAL 1,864.000 $8.000 $5.150 $4.600 $5.000 $5.000 $3.600 $5.000 $4.580
AGGR (TY-PB, GR-3 OR 3S)(SAC-B)
CY 57.000 $700.000 $305.500 $260.000 $203.000 $330.000 $341.000 $450.000 $459.920
D-GR HMA TY-B SAC-B PG64-22
TON 468.000 $175.000 $145.170 $210.000 $146.000 $128.000 $163.000 $230.000 $190.400
D-GR HMA TY-D SAC-B PG70-22
TON 737.000 $160.000 $116.510 $140.000 $159.000 $132.000 $153.000 $180.000 $179.200
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 99.000 $350.000 $146.330 $371.500 $158.000 $340.000 $500.000 $325.000 $560.000
TACK COAT
GAL 715.000 $12.000 $5.970 $4.800 $5.400 $8.000 $4.100 $4.000 $6.100
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 468.000 $75.000 $90.700 $49.500 $65.000 $131.000 $71.000 $85.000 $98.830
PLANE ASPH CONC PAV(0" TO 3")
SY 791.000 $4.000 $12.410 $3.600 $4.500 $13.000 $21.000 $8.500 $11.190
PLANE ASPH CONC PAV (0" TO 1.5")
SY 1,000.000 $4.000 $9.220 $9.100 $1.500 $13.000 $16.000 $8.500 $11.190
CLEAN EXIST CULVERTS
EA 3.000 $1,000.000 $3,297.410 $3,900.000 $985.000 $4,100.000 $1,610.000 $3,000.000 $2,464.000
MOBILIZATION
LS 1.000 $78,975.760 $143,749.880 $23,000.000 $90,400.000 $86,480.000 $90,000.000 $95,000.000 $140,932.400
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $3,824.740 $18,000.000 $7,700.000 $12,140.000 $15,000.000 $15,000.000 $7,280.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 96.000 $100.000 $99.540 $130.000 $118.000 $66.000 $122.000 $75.000 $106.400
TMA (STATIONARY)
DAY 31.000 $200.000 $322.420 $390.000 $200.000 $490.000 $379.000 $325.000 $308.000
TMA (MOBILE OPERATION)
DAY 10.000 $300.000 $653.590 $760.000 $350.000 $840.000 $572.000 $100.000 $560.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 260.000 $5.000 $4.660 $7.600 $8.500 $9.000 $7.400 $8.000 $11.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 260.000 $10.000 $1.770 $6.200 $3.400 $7.000 $4.150 $4.000 $5.600
DRIVEWAYS (ACP) (TY 1)
SY 254.000 $75.000 $52.150 $12.250 $37.000 $86.000 $59.000 $40.000 $138.880
DRIVEWAYS (ACP) (TY 2)
SY 28.000 $110.000 $206.180 $38.000 $108.000 $222.000 $306.000 $150.000 $173.600
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 3,925.000 $0.100 $0.710 $0.800 $1.850 $2.000 $1.350 $0.500 $0.840
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 955.000 $0.100 $2.500 $3.200 $5.800 $3.000 $3.650 $2.250 $2.240
REMOVE RD IL ASM (TRANS-BASE)
EA 12.000 $680.000 $1,196.360 $1,700.000 $1,420.000 $1,640.000 $2,110.000 $1,250.000 $1,344.000
REMOVE GROUND BOX
EA 1.000 $400.000 $779.840 $930.000 $1,108.000 $720.000 $748.000 $700.000 $1,265.600
REMOVE ELECTRICAL SERVICES
EA 1.000 $660.000 $1,378.340 $1,800.000 $1,705.000 $1,370.000 $1,420.000 $1,300.000 $1,344.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $750.000 $1,534.330 $2,000.000 $1,650.000 $1,660.000 $1,720.000 $1,600.000 $1,624.000
RELOCATE SM RD SN SUP&AM TY S80
EA 3.000 $500.000 $1,114.330 $1,500.000 $1,200.000 $1,210.000 $1,250.000 $1,200.000 $1,176.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND(BI)
EA 9.000 $125.000 $221.830 $280.000 $230.000 $230.000 $237.000 $225.000 $224.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 3.000 $20.000 $64.330 $70.000 $57.000 $58.000 $59.000 $60.000 $56.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 185.000 $4.000 $8.510 $10.500 $8.500 $9.000 $8.900 $8.000 $8.400
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 14,650.000 $1.000 $0.530 $0.650 $0.550 $0.600 $0.550 $0.500 $0.540
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 14,650.000 $1.000 $0.530 $0.650 $0.550 $0.600 $0.550 $0.500 $0.540
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 163.000 $2.000 $3.000 $3.700 $2.750 $4.000 $3.300 $1.000 $2.280
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 170.000 $2.000 $2.900 $3.600 $2.750 $4.000 $3.200 $2.000 $3.430
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 204.000 $0.900 $1.740 $1.550 $1.250 $1.000 $1.300 $1.150 $1.230
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 150.000 $0.900 $1.940 $1.550 $1.250 $2.000 $1.300 $1.150 $1.230
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 3,924.000 $0.500 $0.950 $1.250 $1.000 $1.000 $1.050 $1.000 $0.990
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 5,220.000 $0.500 $0.950 $1.250 $1.000 $1.000 $1.050 $1.000 $0.990
PREFAB PM TY C (W)(24")(SLD)
LF 17.000 $35.000 $30.720 $22.000 $18.000 $17.000 $19.000 $20.000 $17.920
PREFAB PM TY C (W)(ARROW)
EA 2.000 $250.000 $269.170 $280.000 $228.000 $230.000 $237.000 $225.000 $224.000
PREFAB PM TY C (W)(WORD)
EA 2.000 $250.000 $321.670 $350.000 $284.000 $290.000 $297.000 $275.000 $280.000
PREFAB PM TY C (Y)(12")(SLD)
LF 338.000 $7.000 $9.450 $11.250 $9.000 $9.000 $9.500 $10.000 $8.960
REFL PAV MRKR TY I-C
EA 8.000 $6.000 $15.270 $10.500 $8.500 $8.000 $8.900 $8.000 $8.400
REFL PAV MRKR TY II-A-A
EA 239.000 $7.000 $8.370 $10.500 $8.500 $9.000 $8.900 $8.000 $8.400
REMOVAL OF CABLES
LF 7,500.000 $1.000 $2.010 $2.700 $2.850 $2.000 $2.200 $2.000 $2.070
Totals: $877,733.360 $846,575.840 $895,502.050 $939,071.000 $959,554.000 $982,402.000 $998,389.850 $1,076,292.800