NUECES OCEAN DR (0916-35-231)

Items: 75

County: NUECES
Length: 0.0000 MILES
Highway: OCEAN DR
District: CORPUS CHRISTI
Control Number: 0916-35-231
DBE Goal: 0.0%
Project: BR 2024(181)
Guaranty: $100,000.00
Time: 428 WORKING DAYS
Engineer's Estimate: $14,038,390.99
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263008
Type: BRIDGE REPLACEMENT
Project ID: A00176646
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT OF THE CAYO DEL OSO BRIDGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ERIC MARTINEZ
RICARDO BRAVO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$14,038,390.99
$14,868,485.21
Over/Under Est: 5.91% $830,094.22
Over/Under Est: 14.63% $2,053,461.29
Amt Left: 8.23% $1,223,367.07
$16,945,200.80
Over/Under Est: 20.71% $2,906,809.81
Amt Left: 13.97% $2,076,715.59
Delta: -5.30% -$853,348.52
$17,320,000.00
Over/Under Est: 23.38% $3,281,609.01
Amt Left: 16.49% $2,451,514.79
Delta: -2.21% -$374,799.20
Over/Under Est: 27.82% $3,905,165.13
Amt Left: 20.68% $3,075,070.91
Delta: -3.60% -$623,556.12
$20,053,645.21
Over/Under Est: 42.85% $6,015,254.22
Amt Left: 34.87% $5,185,160.00
Delta: -11.76% -$2,110,089.09
Over/Under Est: 46.88% $6,581,112.91
Amt Left: 38.68% $5,751,018.69
Delta: -2.82% -$565,858.69

Bid Items & Bid Tabulations

75 Total 0 of 75
NUECES  |  OCEAN DR  |  CORPUS CHRISTI  |  0916-35-231  |  05/06/2026  |  $14,038,390.99  |  BR 2024(181)  |  BRIDGE REPL  |  428 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
J E CONSTRUCTION SERVICES, LLC
MCMILLEN, INC.
ORION CONSTRUCTION, LLC
RAGLE CONSTRUCTION, INC.
COPASA INC
REYTEC CONSTRUCTION RESOURCES, INC.
PREPARING ROW
STA 13.000 $10,000.000 $1,480.000 $49,630.000 $25,000.000 $115,000.000 $135,000.000 $154,258.818 $10,000.000
REMOV CONC (RIPRAP)
SY 1,721.000 $20.000 $18.000 $29.000 $30.000 $80.000 $15.000 $17.250 $16.000
REMOVING STAB BASE & ASPH PAV(12"-27")
SY 7,832.000 $15.000 $12.000 $12.000 $14.000 $40.000 $9.000 $33.330 $18.000
EXCAV (ROADWAY)
CY 4,961.000 $15.000 $11.000 $18.000 $30.000 $22.000 $23.000 $18.670 $30.000
EMBANK (FNL)(OC)(TY C)
CY 2,349.000 $35.000 $15.000 $14.000 $55.000 $38.000 $14.000 $29.330 $40.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 3,504.000 $0.400 $1.500 $5.000 $2.000 $2.000 $1.500 $1.500 $0.250
BROADCAST SEED (TEMP_WARM)
SY 876.000 $0.200 $3.950 $3.000 $5.000 $3.600 $3.500 $3.500 $0.250
BROADCAST SEED (TEMP_COOL)
SY 876.000 $0.200 $3.950 $3.000 $5.000 $3.600 $3.500 $3.500 $0.250
VEGETATIVE WATERING
TGL 197.000 $100.000 $50.000 $38.000 $65.000 $100.000 $65.000 $25.000 $63.000
SOIL RET BLKT(SL_MOD_SAND_LONG)
SY 3,504.000 $1.100 $1.750 $4.000 $2.000 $2.300 $1.650 $1.650 $4.200
FL BS (CMP IN PLC)(TY A GR 1-2) (8")
SY 28.000 $35.000 $50.000 $41.000 $260.000 $200.000 $350.000 $133.330 $40.000
PRIME COAT (MC-30)
GAL 1,794.000 $5.250 $7.700 $9.000 $7.000 $7.500 $8.000 $7.000 $7.000
ASPH(AC-15P, HFRS-2P OR CRS-2P)
GAL 8,451.000 $4.000 $4.000 $9.000 $5.000 $5.500 $7.000 $5.000 $5.250
AGGR (TY-PB, GR-3 OR 3S)(SAC-B)
CY 81.000 $500.000 $240.000 $782.000 $290.000 $350.000 $175.000 $290.000 $315.000
AGGR (TY-PB, GR-4S OR 4)(SAC-B)
CY 197.000 $500.000 $263.000 $761.000 $285.000 $340.000 $175.000 $285.000 $330.000
D-GR HMA TY-B SAC-B PG70-22
TON 2,467.000 $86.000 $127.000 $144.000 $207.000 $245.000 $142.000 $206.170 $285.000
D-GR HMA TY-D SAC-B PG70-22
TON 903.000 $104.000 $153.000 $158.000 $230.000 $275.000 $163.000 $230.060 $295.000
TACK COAT
GAL 897.000 $8.000 $3.900 $8.000 $5.000 $5.700 $10.240 $5.000 $7.000
CEM STABIL BKFL
CY 190.000 $157.000 $129.000 $154.000 $235.000 $400.000 $150.000 $150.000 $118.000
TEMPORARY SPL SHORING
SF 2,052.000 $50.000 $62.000 $62.000 $86.000 $165.000 $171.000 $71.220 $100.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 2,100.000 $50.000 $35.000 $184.000 $68.000 $60.000 $105.000 $64.450 $45.000
PRESTR CONC PIL (18 IN SQ)
LF 252.000 $220.000 $232.000 $178.000 $457.000 $190.000 $118.000 $145.270 $250.000
PRESTR CONC PIL (24 IN SQ)
LF 7,194.000 $250.000 $213.000 $191.000 $200.000 $205.000 $201.000 $162.200 $280.000
CL C CONC (ABUT)
CY 70.800 $2,000.000 $3,110.000 $1,680.000 $1,685.000 $1,900.000 $1,345.000 $1,882.900 $2,500.000
CL C CONC (CAP)
CY 261.000 $2,000.000 $2,460.000 $1,994.000 $2,050.000 $2,500.000 $1,481.000 $2,758.670 $3,000.000
REINF CONC SLAB
SF 46,800.000 $27.000 $39.410 $32.000 $37.000 $29.500 $30.000 $36.670 $50.000
APPROACH SLAB
CY 93.200 $1,500.000 $1,280.000 $1,429.000 $1,000.000 $1,100.000 $915.000 $1,690.210 $1,500.000
PRESTR CONC GIRDER (TX34)
LF 6,200.160 $186.500 $246.000 $278.000 $255.000 $250.000 $164.000 $224.930 $300.000
RIPRAP (CONC)(4 IN)
CY 192.000 $618.000 $643.000 $773.000 $660.000 $850.000 $620.000 $525.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 115.000 $576.000 $606.000 $703.000 $625.000 $900.000 $610.000 $557.750 $750.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 2,182.000 $227.500 $167.000 $319.000 $250.000 $345.000 $225.000 $257.360 $250.000
RAIL (TY T551)
LF 1,612.000 $130.000 $104.000 $106.000 $86.000 $130.000 $63.000 $104.680 $80.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 300.000 $254.000 $217.000 $265.000 $260.000 $50.000 $198.000 $300.000 $200.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $1,000,000.000 $1,658,000.000 $1,463,420.000 $1,638,000.000 $2,100,000.000 $1,500,000.000 $1,994,843.000 $1,800,000.000
MOBILIZATION
LS 1.000 $1,000,000.000 $1,400,000.000 $1,557,464.000 $1,500,000.000 $1,600,000.000 $1,700,000.000 $2,005,364.634 $2,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 27.000 $6,000.000 $4,650.000 $3,290.000 $52,000.000 $15,000.000 $25,000.000 $51,990.934 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,500.000 $27,800.000 $13,210.000 $24,000.000 $36,279.600 $25,000.000 $17,366.521 $5,250.000
TMA (STATIONARY)
DAY 240.000 $250.000 $339.000 $410.000 $300.000 $500.000 $260.000 $200.000 $150.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 620.000 $33.000 $29.000 $54.000 $45.000 $60.000 $50.000 $36.000 $100.000
CONSTRUCTION EXITS (REMOVE)
SY 620.000 $14.000 $6.400 $12.000 $14.000 $15.000 $20.000 $26.274 $5.000
CONSTRUCTION PERIMETER FENCE
LF 940.000 $5.750 $7.000 $32.000 $4.000 $12.000 $6.250 $6.250 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,560.000 $5.000 $4.650 $6.000 $4.250 $8.000 $4.250 $4.250 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,560.000 $1.500 $2.400 $2.000 $2.250 $2.300 $2.250 $2.250 $1.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 2,100.000 $95.000 $20.000 $46.000 $70.000 $85.000 $42.000 $42.000 $100.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $120.000 $20.000 $47.000 $84.000 $125.000 $57.000 $42.000 $25.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,100.000 $12.000 $9.510 $10.000 $3.000 $5.000 $7.000 $10.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 40.000 $12.000 $9.510 $11.000 $80.000 $5.000 $9.000 $10.000 $10.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 2,100.000 $21.000 $13.000 $14.000 $21.000 $20.000 $22.000 $15.000 $10.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $21.000 $13.000 $15.000 $21.000 $50.000 $36.000 $15.000 $10.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,050.000 $26.000 $34.000 $32.000 $32.000 $35.000 $26.030 $29.850 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $2,380.000 $4,130.000 $2,200.000 $2,800.000 $2,009.000 $2,110.200 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 2,235.000 $3.000 $3.400 $5.000 $10.000 $4.000 $3.500 $2.000 $5.250
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,409.000 $4,020.000 $4,220.000 $4,100.000 $4,900.000 $3,583.000 $3,985.500 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $500.000 $376.000 $296.000 $550.000 $340.000 $250.000 $250.000 $900.000
CONDT (PVC) (SCH 40) (2")
LF 820.000 $12.000 $13.000 $20.000 $4.500 $15.000 $25.000 $20.000 $21.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $945.000 $1,250.000 $1,000.000 $1,650.000 $1,300.000 $850.000 $805.000 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $840.000 $1,620.000 $1,296.000 $2,400.000 $1,700.000 $1,100.000 $890.000 $840.000
REMOVE SM RD SN SUP&AM
EA 4.000 $110.000 $125.000 $780.000 $207.000 $150.000 $125.000 $75.000 $90.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 18.000 $70.000 $51.000 $6.000 $25.000 $35.000 $95.000 $35.000 $131.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $35.000 $51.000 $113.000 $35.000 $50.000 $95.000 $35.000 $131.000
RE PV MRK TY I(BLACK)6"(SHADOW)(090MIL)
LF 410.000 $0.700 $2.850 $3.000 $5.000 $2.500 $2.500 $5.000 $2.700
RE PM TY II (W) 6" (SLD)
LF 16,700.000 $0.300 $0.320 $1.000 $0.700 $0.280 $0.280 $0.690 $0.300
RE PM TY II (Y) 6" (SLD)
LF 10,000.000 $0.300 $0.320 $1.000 $0.700 $0.280 $0.280 $0.690 $0.300
PAVEMENT SLER 6"
LF 4,100.000 $0.200 $0.590 $1.000 $0.350 $0.520 $0.520 $0.350 $0.550
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 2,400.000 $0.900 $1.000 $1.000 $0.900 $0.880 $0.880 $0.900 $1.000
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 9,600.000 $0.600 $0.780 $1.000 $0.900 $0.680 $0.680 $0.900 $0.710
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 12,000.000 $0.600 $0.780 $1.000 $0.900 $0.680 $0.680 $0.900 $0.710
REFL PAV MRKR TY I-C
EA 127.000 $3.750 $8.550 $9.000 $7.000 $7.500 $7.500 $6.500 $8.000
REFL PAV MRKR TY II-A-A
EA 160.000 $4.000 $8.550 $9.000 $6.500 $7.500 $7.500 $6.500 $8.000
ELIM EXT PM & MRKS (4")
LF 1,560.000 $0.200 $1.800 $12.000 $5.000 $0.750 $0.750 $2.000 $0.200
ELIM EXT PM & MRKS (6")
LF 3,600.000 $1.000 $1.800 $13.000 $5.000 $0.950 $0.950 $2.000 $0.200
PAV SURF PREP FOR MRK (6")
LF 24,410.000 $2.000 $0.060 $0.200 $0.100 $0.050 $0.050 $0.050 $0.060
TEMP CONSTRUCTION ACCESS
LS 1.000 $4,000,000.000 $3,417,600.000 $3,431,519.000 $3,150,000.000 $2,125,000.000 $5,000,000.000 $4,185,512.290 $5,650,000.000
FURNISH AND INSTALL FTB
LF 200.000 $276.000 $177.000 $81.000 $313.000 $275.000 $86.000 $250.000 $170.000
REMOVE FTB
LF 200.000 $15.000 $8.850 $54.000 $45.000 $150.000 $32.000 $25.000 $5.000
Totals: $14,038,390.990 $14,868,485.210 $16,091,852.280 $16,945,200.800 $17,320,000.000 $17,943,556.120 $20,053,645.219 $20,619,503.900
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $65,000.00
Total: $80,000.00