NUECES VA (0916-00-281)

Items: 19

County: NUECES
Length: N/A
Highway: VA
District: CORPUS CHRISTI
Control Number: 0916-00-281
DBE Goal: 0.0%
Project: STP 2B24(265)HES
Guaranty: N/A
Time: 48 WORKING DAYS
Engineer's Estimate: $1,549,989.60
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: INSTALL/REPLACE SIGNS
Mail/Deliver Bids To: N/A
ERNEST LONGORIA
FIDENCIO LOPEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,549,989.60
$1,347,670.08
Over/Under Est: -13.05% -$202,319.52
Over/Under Est: -3.25% -$50,443.60
Amt Left: 11.27% $151,875.92
Over/Under Est: -3.09% -$47,894.60
Amt Left: 11.46% $154,424.92
Delta: -0.17% -$2,549.00
Over/Under Est: -2.78% -$43,159.45
Amt Left: 11.81% $159,160.07
Delta: -0.32% -$4,735.15
$1,522,744.50
Over/Under Est: -1.76% -$27,245.10
Amt Left: 12.99% $175,074.42
Delta: -1.06% -$15,914.35
$1,632,223.00
Over/Under Est: 5.31% $82,233.40
Amt Left: 21.11% $284,552.92
Delta: -7.19% -$109,478.50
Over/Under Est: 9.58% $148,494.59
Amt Left: 26.03% $350,814.11
Delta: -4.06% -$66,261.19
Subcontractor Percentage Amount
SAFETY FIRST TRAFFIC SOLUTIONS, LLC 2.19% $29,513.97
Total: 2.19% $29,513.97

Bid Items & Bid Tabulations

19 Total 0 of 19
NUECES  |  VA  |  CORPUS CHRISTI  |  0916-00-281  |  06/06/2024  |  $1,549,989.60  |  STP 2B24(265)HES  |  INSTL/REPLACE SIGNS  |  48 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MALDONADO-BURKETT, LLP
HIGHWAY BARRICADES AND SERVICES, LLC
SYNERGY SIGNS & SERVICES LLC
E-Z BEL CONSTRUCTION, LLC
THE LEVY COMPANY, INC.
LIGHT IT UP ELECTRIC
THIRD COAST SERVICES LLC
REMOVING CONC (FOUNDATIONS)
CY 0.600 $456.000 $5,950.000 $350.000 $1,000.000 $675.000 $2,100.000 $600.000 $525.600
MOBILIZATION
LS 1.000 $130,000.000 $134,767.000 $30,000.000 $75,000.000 $101,000.000 $147,000.000 $150,000.000 $169,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $15,000.000 $1,639.000 $10,000.000 $20,000.000 $2,100.000 $24,700.000 $8,000.000 $2,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 40.000 $8.000 $6.820 $1.500 $10.000 $6.000 $5.000 $8.000 $62.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 50.000 $10.500 $4.470 $3.000 $15.000 $7.000 $5.000 $13.000 $64.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $2.250 $2.250 $1.000 $5.000 $1.000 $1.500 $3.000 $53.000
ALUMINUM SIGNS (TY O)
SF 352.000 $49.000 $94.640 $38.000 $35.000 $125.000 $103.000 $49.000 $930.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 3.000 $897.750 $684.290 $875.000 $625.000 $700.000 $850.000 $800.000 $998.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 13.000 $1,162.500 $817.940 $1,200.000 $875.000 $1,000.000 $1,050.000 $1,000.000 $1,176.000
RELOCATE SM RD SN SUP&AM TY S80
EA 16.000 $1,390.000 $577.370 $650.000 $750.000 $600.000 $960.000 $1,300.000 $1,417.000
REMOVE SM RD SN SUP&AM
EA 5.000 $104.250 $69.500 $85.000 $150.000 $190.000 $230.000 $150.000 $788.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 22.000 $142.000 $10.690 $50.000 $150.000 $103.000 $45.000 $125.000 $210.000
PED POLE ASSEMBLY
EA 39.000 $5,600.000 $2,825.850 $1,700.000 $2,850.000 $3,600.000 $3,000.000 $5,600.000 $2,110.000
REMOVE PED POLE ASSEMBLY
EA 19.000 $643.000 $1,876.470 $200.000 $750.000 $610.000 $500.000 $850.000 $315.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 96.000 $85.000 $43.320 $50.000 $150.000 $55.000 $100.000 $600.000 $210.000
TMA (STATIONARY)
DAY 64.000 $427.500 $78.940 $85.000 $150.000 $225.000 $210.000 $1,250.000 $210.000
SOLAR POWERED LED ROADSIDE SIGN
EA 25.000 $5,263.000 $2,886.840 $4,500.000 $4,500.000 $3,000.000 $2,500.000 $4,500.000 $2,271.000
LED WRONG WAY DRIVER SYSTEM (REMOVE)
EA 3.330 $1,500.000 $1,029.790 $2,000.000 $2,500.000 $255.000 $1,450.000 $1,500.000 $1,051.000
LED WRONG WAY DRIVER SYSTEM (THERMAL)
EA 13.000 $70,000.000 $70,554.050 $92,000.000 $81,000.000 $83,000.000 $77,920.000 $70,000.000 $73,205.000
Totals: $1,549,989.600 $1,347,670.081 $1,499,546.000 $1,502,095.000 $1,506,830.150 $1,522,744.500 $1,632,223.000 $1,698,484.190