NUECES US 77 (0102-16-001)

Items: 247

County: NUECES
Length: N/A
Highway: US 77
District: CORPUS CHRISTI
Control Number: 0102-16-001
DBE Goal: N/A
Project: STP 2018(201)
Guaranty: N/A
Time: 917 WORKING DAYS
Engineer's Estimate: $120,620,669.87
Date: 07/11/2018 (7 years ago)
Contract Number: N/A
Type: CONSTRUCT RELIEF ROUTE AROUND DRISCOLL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$120,620,669.87
$118,322,898.17
Over/Under Est: -1.9% -$2,297,771.70
Over/Under Est: 1.99% $2,400,650.45
Amt Left: 3.97% $4,698,422.15
Over/Under Est: 3.55% $4,283,097.96
Amt Left: 5.56% $6,580,869.66
Delta: -1.53% -$1,882,447.51
Over/Under Est: 11.7% $14,116,239.02
Amt Left: 13.87% $16,414,010.72
Delta: -7.87% -$9,833,141.06
$143,075,075.00
Over/Under Est: 18.62% $22,454,405.13
Amt Left: 20.92% $24,752,176.83
Delta: -6.19% -$8,338,166.11
Subcontractor Percentage Amount
BAY LTD. 15.29% $19,458,760.34
BEAVER CONTRACTORS, LLC 5.86% $7,457,706.71
TEXAS HIGHWAY WALLS 5.61% $7,139,545.16
MICA CORPORATION 3.85% $4,899,687.86
MATERIAL PRODUCERS CONSTRUCTION SERVICES, LLC 1.96% $2,494,386.54
ROADWAY SPECIALTIES, INC. 1.28% $1,628,987.13
JB PINNACLE GROUP, LLC 1.02% $1,298,099.12
FUQUAY, INC. 0.94% $1,196,287.42
HIGHWAY BARRICADES AND SERVICES, LLC 0.45% $572,690.79
PANTHER CREEK TRANSPORTATION, INC. 0.34% $432,699.71
A.Z. REBAR CONSTRUCTION, INC. 0.31% $394,520.32
ABC EROSION CONTROL, INC 0.27% $343,614.47
PRODUCTION EQUIPMENT COMPANY OF SOUTH TEXAS, INC. 0.25% $318,161.55
GEOSOURCE, INC. 0.22% $279,982.16
SOIL TECH ADVANCE INC. 0.17% $216,349.85
INDUSTRIAL VACUUM TRANSFER SERVICES USA, LLC 0.14% $178,170.47
A BROTHERS MILLING, LLC 0.11% $139,991.08
CAPITAL PUMPING, LP 0.10% $127,264.62
M & D FOUNDATION DRILLING INDUSTRIES, INC. 0.09% $114,538.16
SOUTH TEXAS PAINTING 0.09% $114,538.16
GUERRA UNDERGROUND LLC 0.07% $89,085.23
PRIMATE CONSTRUCTION, LP 0.05% $63,632.31
BREDA COMPANY, INC. 0.02% $25,452.92
TEXAS CUTTING & CORING GP, INC. 0.01% $12,726.46
WEST TEXAS ROCK RESOURCES, LLC 0.01% $12,726.46
TNT CRANE & RIGGING, INC. 0.00% $0.00
PERFORMANCE EQUIPMENT SERVICE 0.00% $0.00
Total: 38.51% $49,009,605.00

Bid Items & Bid Tabulations

247 Total 0 of 247
NUECES  |  US 77  |  CORPUS CHRISTI  |  0102-16-001  |  07/11/2018  |  $120,620,669.87  |  STP 2018(201)  |  CONSTRUCT RELIEF ROUTE AROUND DRISCO...  |  917 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ZACHRY CONSTRUCTION CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
ANDERSON COLUMBIA CO., INC.
WEBBER, LLC
PREPARING ROW
STA 504.000 $3,000.000 $4,969.240 $10,300.000 $550.000 $3,100.000 $27,750.000
REMOVING CONC (RIPRAP)
SY 305.000 $10.000 $5.500 $14.490 $11.000 $5.000 $13.400
REMOVING CONCRETE(MOW STRIP)
LF 5,890.000 $5.000 $7.270 $3.150 $9.000 $7.000 $3.550
EXCAVATION (ROADWAY)
CY 440,702.000 $8.000 $2.840 $3.000 $4.000 $5.000 $3.650
EXCAVATION (CHANNEL)
CY 14,486.000 $15.000 $2.870 $6.980 $11.000 $8.500 $1.500
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,994,239.000 $8.000 $4.670 $7.500 $7.000 $7.400 $7.150
EMBANKMENT (FINAL)(DC)(TY C)(RWAL FND)
CY 7,310.000 $8.000 $70.000 $60.000 $68.000 $80.000 $61.750
BACKFILL (TY A OR B)
STA 331.500 $100.000 $102.790 $175.700 $200.000 $225.000 $172.000
FURNISHING AND PLACING TOPSOIL (4")
SY 1,463,612.000 $1.600 $0.360 $0.350 $1.000 $1.600 $0.200
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 1,495,366.000 $0.200 $0.080 $0.130 $0.250 $0.100 $0.100
DRILL SEED (TEMP)(WARM OR COOL)
SY 1,495,366.000 $0.120 $0.030 $0.070 $0.150 $0.070 $0.050
FERTILIZER
TON 116.000 $1,000.000 $599.970 $856.400 $600.000 $875.000 $856.000
VEGETATIVE WATERING
MG 48,198.000 $25.000 $17.540 $22.720 $10.000 $10.000 $28.700
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 68,531.000 $1.000 $0.780 $1.500 $0.700 $0.950 $0.950
PLANT MATERIAL (5-GAL)
EA 335.000 $30.000 $30.000 $31.030 $30.000 $30.000 $31.000
PLANT MATERIAL (15-GAL)
EA 169.000 $200.000 $144.990 $212.750 $145.000 $145.000 $213.000
PLANT MATERIAL (30-GAL)
EA 112.000 $350.000 $349.980 $367.050 $350.000 $350.000 $367.000
PLANT MATERIAL (65-GAL)
EA 24.000 $675.000 $749.960 $704.030 $494.810 $750.000 $704.000
PLANT SOIL MIX
CY 1,229.000 $50.000 $40.000 $81.190 $40.000 $40.000 $81.250
LANDSCAPE EDGE
LF 1,314.000 $15.000 $20.160 $10.000 $10.000 $20.000 $15.400
PLANT BED PREPARATION
SY 3,684.000 $5.000 $2.750 $24.520 $2.750 $2.750 $24.500
PLANT MAINTENANCE
MO 9.000 $1,000.000 $6,799.670 $4,067.500 $6,800.000 $6,200.000 $4,070.000
VEGETATIVE WATERING
MG 563.000 $35.000 $26.000 $163.860 $12.690 $35.000 $170.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 182,884.000 $60.000 $65.000 $42.800 $61.500 $48.000 $47.000
LIME (HYDRATED LIME (SLURRY))
TON 12,721.000 $150.000 $250.000 $176.080 $165.000 $130.000 $173.000
LIME TRT (SUBGRADE)(8")
SY 642,774.000 $2.500 $4.000 $3.270 $3.000 $2.500 $4.400
CEMENT
TON 5,126.000 $135.000 $225.000 $147.590 $170.000 $169.000 $149.000
CEMENT TREAT (NEW BASE)(12")
SY 417,264.000 $2.000 $4.000 $3.620 $2.000 $3.500 $3.300
PRIME COAT (MC-30)
GAL 119,178.000 $3.500 $3.630 $3.630 $3.000 $4.000 $4.250
ASPH (MULTI OPTION)
GAL 295,387.000 $2.200 $2.380 $2.380 $3.500 $4.000 $2.900
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 7,679.000 $65.000 $85.780 $85.750 $80.000 $95.000 $90.000
D-GR HMA TY-D SAC-B PG70-22
TON 30,459.000 $60.000 $78.930 $80.070 $80.000 $96.000 $85.750
SUPERPAVE MIXTURES SP-B PG70-22
TON 106,982.000 $75.000 $73.830 $75.000 $80.000 $92.000 $81.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 70,163.000 $90.000 $105.630 $107.070 $112.000 $131.000 $114.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(18")
SY 4,000.000 $140.000 $83.490 $74.820 $70.000 $100.000 $75.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 100,558.000 $1.250 $0.670 $1.280 $1.300 $1.600 $1.450
PLAN & TEXT ASPH CONC PAV(0" TO 3")
SY 689.000 $1.600 $6.000 $6.190 $2.000 $1.600 $6.400
CEM STABIL BKFL
CY 5,445.000 $100.000 $101.630 $71.920 $65.000 $80.000 $66.750
TRENCH EXCAVATION PROTECTION
LF 974.000 $8.000 $2.910 $3.000 $1.000 $1.000 $3.000
PRESTR CONC PIL (18 IN SQ)
LF 47,150.000 $70.000 $75.950 $75.040 $79.500 $110.000 $80.500
DRILL SHAFT (24 IN)
LF 379.000 $110.000 $134.540 $134.650 $150.000 $135.000 $110.000
DRILL SHAFT (30 IN)
LF 190.000 $130.000 $229.860 $230.050 $160.000 $232.000 $230.000
DRILL SHAFT (48 IN)
LF 108.000 $280.000 $441.640 $442.000 $400.000 $442.000 $442.000
DRILL SHAFT (SIGN MTS) (36 IN)
LF 32.000 $325.000 $595.520 $596.000 $400.000 $596.000 $596.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 80.000 $325.000 $507.590 $508.000 $420.000 $508.000 $508.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 500.000 $660.000 $496.850 $497.250 $510.000 $500.000 $497.000
CL C CONC (ABUT)
CY 917.600 $800.000 $694.610 $918.230 $850.000 $950.000 $998.000
CL C CONC (CAP)
CY 1,075.800 $1,000.000 $927.130 $987.750 $925.000 $1,115.000 $945.000
CL C CONC (COLUMN)
CY 602.000 $1,000.000 $714.840 $893.480 $840.000 $805.000 $842.000
CL C CONC (FOOTING)
CY 825.600 $800.000 $640.250 $771.220 $700.000 $600.000 $821.000
CL C CONC (RAIL FOUNDATION)
CY 1,343.000 $500.000 $444.280 $381.390 $450.000 $370.000 $563.000
REINF CONC SLAB
SF 306,059.000 $13.500 $16.520 $14.500 $15.250 $17.400 $17.600
APPROACH SLAB
CY 1,113.800 $425.000 $650.000 $388.160 $425.000 $550.000 $423.000
RETAINING WALL (MSE) (ASHLAR STONE FIN)
SF 241,688.000 $50.000 $58.030 $60.700 $68.250 $62.000 $60.000
RETAINING WALL (TEMP WALL)
SF 24,650.000 $10.000 $9.610 $0.100 $12.500 $30.000 $41.250
PRESTR CONC SLAB BEAM (4SB15)
LF 3,106.500 $125.000 $122.710 $118.850 $145.000 $145.000 $140.000
PRESTR CONC GIRDER (TX46)
LF 13,120.980 $120.000 $118.280 $116.090 $130.000 $145.000 $120.000
PRESTR CONC GIRDER (TX54)
LF 23,252.570 $125.000 $122.710 $120.950 $135.000 $145.000 $130.000
RIPRAP (CONC)(4 IN)
CY 38.000 $450.000 $350.000 $431.540 $425.000 $460.000 $444.000
RIPRAP (CONC)(5 IN)
CY 1,931.000 $500.000 $600.000 $375.010 $325.000 $400.000 $395.000
RIPRAP (CONC)(6 IN)
CY 38.000 $550.000 $536.710 $421.010 $325.000 $460.000 $434.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 4,128.000 $550.000 $480.000 $366.670 $325.000 $400.000 $336.000
RIPRAP (MOW STRIP)(4 IN)
CY 194.000 $450.000 $450.000 $386.760 $450.000 $400.000 $491.000
RIPRAP (MOW STRIP)(5 IN)
CY 748.000 $500.000 $500.000 $382.370 $450.000 $400.000 $415.000
RIPRAP (MOW STRIP)(6 IN)
CY 284.000 $450.000 $456.320 $379.480 $450.000 $400.000 $322.000
RAIL (TY T223)
LF 9,899.300 $75.000 $103.070 $121.730 $85.000 $98.000 $133.000
RAIL (TY SSTR)
LF 29,223.100 $50.000 $35.130 $38.640 $40.000 $55.000 $52.000
RETROFIT RAIL (TY T223)
LF 336.000 $200.000 $300.000 $201.310 $72.000 $250.000 $249.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 1,808.000 $80.000 $80.990 $91.000 $100.000 $75.000 $66.000
CONC BOX CULV (4 FT X 2 FT)
LF 924.000 $150.000 $161.580 $138.100 $300.000 $170.000 $155.000
CONC BOX CULV (5 FT X 2 FT)
LF 4,470.000 $300.000 $204.880 $183.050 $360.000 $210.000 $184.000
CONC BOX CULV (5 FT X 5 FT)
LF 1,137.000 $350.000 $251.960 $227.190 $460.000 $340.000 $228.000
CONC BOX CULV (6 FT X 3 FT)
LF 132.000 $150.000 $264.370 $231.750 $530.000 $345.000 $241.000
CONC BOX CULV (6 FT X 4 FT)
LF 915.000 $50.000 $278.240 $252.910 $535.000 $345.000 $258.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 24.000 $525.000 $421.610 $397.030 $650.000 $960.000 $697.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 864.000 $550.000 $518.680 $284.290 $445.000 $300.000 $674.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 997.000 $600.000 $505.670 $279.570 $520.000 $310.000 $746.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 928.000 $650.000 $468.750 $322.100 $545.000 $310.000 $756.000
CONC BOX CULV (6 FT X 2 FT) (EXTEND)
LF 225.000 $800.000 $267.840 $259.610 $475.000 $420.000 $883.000
RC PIPE (CL III)(18 IN)
LF 4,256.000 $60.000 $50.320 $44.230 $55.000 $44.000 $51.750
RC PIPE (CL III)(24 IN)
LF 1,666.000 $70.000 $57.470 $41.800 $68.000 $57.000 $56.750
INLET (COMPL)(TY MSE1)
EA 51.000 $7,000.000 $2,910.730 $3,417.760 $3,500.000 $3,400.000 $3,560.000
WINGWALL (FW - 0) (HW=2 FT)
EA 1.000 $3,500.000 $3,392.250 $25,861.840 $4,000.000 $7,200.000 $3,490.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $7,700.000 $12,289.640 $25,861.840 $21,000.000 $18,500.000 $11,970.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $13,000.000 $16,210.120 $54,833.050 $45,000.000 $25,000.000 $15,072.100
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 4.000 $5,500.000 $8,753.520 $2,088.510 $6,300.000 $4,000.000 $4,890.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (C)
EA 18.000 $6,200.000 $9,303.790 $2,908.450 $7,700.000 $5,700.000 $7,580.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
EA 2.000 $3,000.000 $8,132.550 $3,743.240 $8,000.000 $7,800.000 $7,680.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 15.000 $6,000.000 $12,731.780 $2,056.240 $8,300.000 $4,000.000 $7,480.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
EA 45.000 $7,000.000 $7,384.680 $2,910.860 $10,000.000 $5,700.000 $6,980.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (C)
EA 4.000 $6,500.000 $9,906.870 $4,175.570 $11,000.000 $8,000.000 $8,580.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(6:1) (C)
EA 4.000 $9,900.000 $10,365.040 $5,402.820 $13,500.000 $10,000.000 $10,100.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1) (C)
EA 6.000 $7,050.000 $9,078.010 $4,814.470 $14,000.000 $8,700.000 $7,980.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(6:1) (C)
EA 6.000 $8,200.000 $11,759.650 $7,079.920 $15,500.000 $12,500.000 $9,980.000
SET (TY I)(S= 6 FT)(HW= 2 FT)(4:1) (C)
EA 1.000 $2,500.000 $9,334.000 $1,944.660 $12,000.000 $6,300.000 $6,980.000
SET (TY I)(S= 6 FT)(HW= 3 FT)(4:1) (C)
EA 1.000 $7,300.000 $9,435.260 $2,879.660 $15,000.000 $5,900.000 $6,680.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 9.000 $7,250.000 $8,069.930 $3,370.220 $19,000.000 $6,500.000 $4,490.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C)
EA 5.000 $6,000.000 $9,888.740 $3,558.940 $21,000.000 $7,400.000 $8,680.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(6:1) (C)
EA 5.000 $9,600.000 $10,630.430 $11,733.570 $25,500.000 $10,500.000 $10,470.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $900.000 $976.190 $721.360 $2,100.000 $850.000 $998.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 87.000 $1,000.000 $1,105.290 $820.150 $2,200.000 $900.000 $956.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 11.000 $1,200.000 $1,105.300 $820.150 $2,200.000 $1,000.000 $798.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 8.000 $1,600.000 $1,434.170 $1,173.550 $2,750.000 $1,500.000 $1,750.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 40.000 $1,500.000 $1,434.170 $1,173.550 $2,750.000 $1,500.000 $1,150.000
CLEAN EXIST CULVERTS
EA 6.000 $2,000.000 $1,914.200 $18,150.000 $18,250.000 $16,000.000 $10,000.000
REMOV STR (SET)
EA 41.000 $400.000 $681.070 $385.260 $1,800.000 $650.000 $425.000
REMOV STR (WINGWALL)
EA 5.000 $1,500.000 $2,702.210 $4,488.530 $4,000.000 $1,000.000 $1,250.000
REMOV STR (PIPE)
LF 2,745.000 $20.000 $14.940 $11.280 $18.000 $12.000 $16.000
REMOV STR (BOX CULVERT)
LF 426.000 $40.000 $47.540 $77.300 $80.000 $12.000 $50.000
REMOV STR (SMALL FENCE)
LF 2,543.000 $4.000 $1.050 $5.120 $2.500 $1.000 $4.000
MOBILIZATION
LS 1.000 $7,650,000.000 $8,500,000.000 $12,289,829.900 $10,975,000.000 $12,250,000.000 $14,280,075.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 54.000 $3,000.000 $10,978.840 $8,000.000 $10,000.000 $7,500.000 $32,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
CY 86.000 $100.000 $75.000 $75.000 $110.000 $82.000 $231.000
ROCK FILTER DAMS (REMOVE)
CY 86.000 $40.000 $15.000 $15.000 $38.000 $16.000 $65.500
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,111.000 $25.000 $15.000 $15.000 $15.000 $16.000 $31.250
CONSTRUCTION EXITS (REMOVE)
SY 1,111.000 $8.000 $2.000 $2.000 $10.150 $2.200 $9.550
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,878.000 $2.000 $4.000 $4.000 $2.000 $4.300 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,758.000 $0.750 $2.000 $1.500 $0.400 $1.700 $1.550
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,120.000 $7.000 $5.000 $5.000 $4.500 $5.400 $5.800
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,120.000 $1.500 $1.500 $1.500 $1.270 $1.600 $1.050
CONSTRUCTING DETOURS
SY 8,636.000 $50.000 $49.050 $34.680 $35.000 $70.000 $40.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 7,470.000 $45.000 $6.670 $21.750 $55.000 $90.000 $72.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 15,270.000 $10.000 $3.000 $6.000 $5.000 $8.000 $4.800
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 7,470.000 $10.000 $2.930 $6.310 $5.000 $15.000 $4.600
CONC CURB & GUTTER (TY II)
LF 624.000 $22.000 $11.080 $25.000 $30.000 $32.000 $29.700
DRIVEWAYS (ACP)
SY 2,542.000 $30.000 $65.000 $51.330 $35.000 $75.000 $19.000
INTERSECTIONS (ACP) (TYPE 1)
SY 2,078.000 $13.000 $79.940 $63.490 $55.000 $110.000 $47.250
INTERSECTIONS (ACP) (TYPE 2)
SY 2,891.000 $61.000 $39.970 $33.860 $45.000 $70.000 $28.100
RUMBLE STRIPS (SHOULDER)
LF 105,000.000 $0.200 $0.080 $0.080 $0.120 $0.200 $0.100
MTL W-BEAM GD FEN (TIM POST)
LF 1,275.000 $20.000 $23.350 $23.350 $23.000 $25.000 $23.400
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $1,500.000 $1,660.000 $1,660.000 $1,575.000 $1,800.000 $1,660.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,000.000 $1,115.000 $1,115.000 $2,156.870 $1,200.000 $1,120.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 1,375.000 $52.000 $57.500 $57.500 $65.000 $8.000 $57.500
REMOVE METAL BEAM GUARD FENCE
LF 3,130.000 $2.000 $1.500 $1.500 $8.880 $1.600 $1.500
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 5,160.000 $12.000 $11.500 $11.500 $11.000 $12.000 $12.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 16.000 $2,500.000 $2,899.990 $2,350.000 $2,490.000 $2,700.000 $2,500.000
REMOVE CABLE BARRIER
LF 5,890.000 $4.000 $3.500 $3.500 $3.500 $4.000 $3.500
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $2,100.000 $2,949.990 $2,950.000 $2,745.000 $3,200.000 $2,950.000
CRASH CUSH ATTEN (INSTL)
EA 49.000 $16,000.000 $19,289.750 $16,485.120 $10,000.000 $20,000.000 $17,070.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 18.000 $2,700.000 $1,250.000 $1,125.770 $1,750.000 $2,720.000 $1,250.000
CRASH CUSH ATTEN (REMOVE)
EA 5.000 $1,000.000 $750.000 $516.550 $1,000.000 $815.000 $750.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 12.000 $745.000 $1,310.000 $1,310.000 $1,310.000 $1,420.000 $1,310.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 19.000 $3,500.000 $3,279.990 $3,280.000 $3,280.000 $3,500.000 $3,280.000
HI MST IL POLE (150 FT)(100 MPH)
EA 11.000 $51,200.000 $33,495.920 $33,496.000 $33,500.000 $36,300.000 $33,500.000
CONDT (PVC) (SCH 40) (2")
LF 13,296.000 $8.000 $10.490 $10.490 $10.500 $11.000 $10.500
CONDT (PVC) (SCH 40) (3")
LF 100,880.000 $16.000 $15.270 $15.270 $15.000 $17.000 $15.300
CONDT (PVC) (SCH 80) (2") (BORE)
LF 4,380.000 $31.000 $22.370 $22.370 $22.000 $25.000 $22.400
CONDT (PVC) (SCH 80) (3") (BORE)
LF 7,620.000 $35.000 $18.550 $18.550 $19.000 $20.000 $18.600
CONDT (RM) (3/4")
LF 60.000 $25.000 $26.050 $26.050 $16.490 $28.000 $26.100
CONDT (RM) (1")
LF 260.000 $20.000 $48.250 $48.250 $13.960 $52.000 $48.250
CONDT (RM) (3")
LF 4,500.000 $39.000 $62.600 $62.600 $21.570 $68.000 $62.500
ELEC CONDR (NO.14) INSULATED
LF 114,210.000 $1.000 $1.250 $1.250 $1.000 $1.400 $1.250
ELEC CONDR (NO.12) BARE
LF 350.000 $1.000 $1.300 $1.300 $1.000 $1.400 $1.300
ELEC CONDR (NO.12) INSULATED
LF 700.000 $2.000 $1.300 $1.300 $1.000 $1.400 $1.300
ELEC CONDR (NO.8) BARE
LF 7,100.000 $2.000 $1.400 $1.400 $1.400 $1.500 $1.400
ELEC CONDR (NO.8) INSULATED
LF 14,200.000 $2.000 $1.510 $1.510 $1.500 $1.600 $1.500
ELEC CONDR (NO.6) BARE
LF 9,300.000 $2.000 $1.540 $1.540 $1.500 $1.600 $1.550
ELEC CONDR (NO.6) INSULATED
LF 32,895.000 $2.000 $1.660 $1.660 $1.500 $1.800 $1.650
GROUND BOX TY A (122311)W/APRON
EA 75.000 $1,000.000 $1,639.000 $1,639.000 $888.120 $1,800.000 $1,640.000
ELC SRV TY A 240/480 060(SS)SS(E)GC(U)
EA 8.000 $6,900.000 $7,953.980 $7,954.000 $8,000.000 $8,600.000 $7,950.000
ELC SRV TY D 120/240 060(NS)SS(N)GC(O)
EA 3.000 $6,300.000 $6,828.030 $6,828.000 $6,800.000 $7,400.000 $6,830.000
ALUMINUM SIGNS (TY A)
SF 45.000 $20.000 $25.500 $25.500 $25.000 $28.000 $25.500
ALUMINUM SIGNS (TY G)
SF 2,032.750 $26.000 $21.400 $21.400 $22.000 $23.000 $21.400
ALUMINUM SIGNS (TY O)
SF 720.000 $28.000 $22.850 $22.850 $22.000 $25.000 $22.900
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 73.000 $450.000 $564.230 $739.000 $740.000 $610.000 $564.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 34.000 $625.000 $615.310 $858.000 $858.000 $665.000 $615.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 108.000 $515.000 $623.970 $798.000 $800.000 $680.000 $624.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 28.000 $800.000 $651.890 $902.000 $900.000 $700.000 $652.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 13.000 $1,000.000 $825.450 $1,215.000 $1,200.000 $900.000 $825.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 9.000 $900.000 $749.430 $1,116.000 $1,100.000 $810.000 $750.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 2.000 $1,000.000 $758.540 $279.000 $805.660 $820.000 $759.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 6.000 $1,600.000 $1,788.200 $2,848.000 $2,800.000 $3,100.000 $2,850.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 5.000 $1,700.000 $1,818.200 $2,847.000 $2,800.000 $3,100.000 $2,850.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 4.000 $2,500.000 $2,870.010 $4,741.000 $2,283.750 $3,100.000 $2,870.000
RELOCATE SM RD SN SUP&AM TY S80
EA 9.000 $375.000 $544.000 $963.000 $228.370 $590.000 $544.000
REMOVE SM RD SN SUP&AM
EA 133.000 $70.000 $85.000 $170.000 $101.500 $71.000 $85.000
INSTALL LRSS (STRUCT STEEL)
LB 11,467.700 $6.000 $3.960 $3.960 $4.000 $4.300 $3.000
INS OH SN SUP(30 FT BAL TEE)
EA 2.000 $28,000.000 $20,905.080 $20,905.000 $21,000.000 $22,600.000 $20,910.000
INS OH SN SUP(60 FT BRDG)
EA 1.000 $18,000.000 $32,745.130 $32,745.000 $32,800.000 $35,500.000 $32,750.000
INS OH SN SUP(65 FT BRDG)
EA 1.000 $20,000.000 $33,260.130 $33,260.000 $33,260.000 $36,000.000 $33,260.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 200.000 $65.000 $42.290 $42.290 $85.000 $45.000 $42.250
INSTL DEL ASSM (D-SW)SZ 1(FLX)SRF
EA 21.000 $60.000 $73.950 $73.950 $90.000 $80.000 $74.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 339.000 $15.000 $10.750 $10.750 $16.000 $12.000 $10.800
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 20.000 $65.000 $43.110 $43.110 $70.000 $47.000 $43.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 168.000 $15.000 $10.750 $10.750 $16.000 $12.000 $10.800
INSTL DEL ASSM (D-DW)SZ 1(FLX)GND
EA 147.000 $65.000 $42.950 $42.950 $60.000 $47.000 $43.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 30.000 $26.000 $15.530 $15.530 $32.000 $17.000 $15.500
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 11.000 $26.000 $15.530 $15.530 $32.000 $17.000 $15.500
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 36,555.000 $0.250 $0.320 $0.320 $0.190 $0.350 $0.300
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 156,716.000 $0.250 $0.320 $0.320 $0.190 $0.350 $0.300
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 12,985.000 $0.500 $0.650 $0.650 $0.650 $0.700 $0.650
WK ZN PAV MRK NON-REMOV (W)12"(LNDP)
LF 365.000 $0.600 $1.500 $1.500 $1.500 $1.600 $1.500
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 930.000 $0.750 $1.500 $1.500 $1.500 $1.600 $1.500
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 395.000 $0.250 $0.500 $0.500 $0.500 $0.500 $0.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 153,616.000 $0.250 $0.320 $0.320 $0.320 $0.350 $0.300
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 5,002.000 $0.750 $0.400 $0.400 $0.400 $0.430 $0.400
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 57,865.000 $0.500 $0.400 $0.400 $0.400 $0.430 $0.400
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 6,295.000 $1.750 $0.800 $0.800 $0.800 $0.900 $0.800
WK ZN PAV MRK REMOV (W)12"(LNDP)
LF 170.000 $4.000 $11.400 $11.400 $11.500 $13.000 $11.400
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 58,870.000 $1.000 $0.400 $0.400 $0.400 $0.400 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 14,433.000 $1.000 $0.960 $0.650 $1.000 $1.300 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 625.000 $1.000 $1.190 $1.000 $1.100 $1.300 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 18,498.000 $0.450 $0.650 $0.650 $0.650 $0.700 $0.650
REFL PAV MRK TY I (W)12"(LNDP)(090MIL)
LF 635.000 $2.500 $1.200 $1.200 $1.200 $1.300 $1.200
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 827.000 $2.750 $1.200 $1.200 $1.200 $1.300 $1.200
REFL PAV MRK TY II (BLACK) 4"(SHADOW)
LF 922.000 $0.550 $1.250 $1.250 $1.250 $1.400 $1.250
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 48,031.000 $0.200 $0.300 $0.300 $0.300 $0.330 $0.300
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 209,544.000 $0.200 $0.300 $0.300 $0.300 $0.330 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 213,010.000 $0.200 $0.300 $0.300 $0.300 $0.330 $0.300
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 177.000 $11.000 $12.000 $12.000 $12.000 $13.000 $12.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $200.000 $175.000 $175.000 $175.000 $190.000 $175.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $350.000 $290.000 $290.000 $290.000 $320.000 $290.000
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $250.000 $250.000 $250.000 $250.000 $270.000 $250.000
REFL PAV MRKR TY I-C
EA 12.000 $3.000 $3.000 $3.000 $3.000 $3.300 $3.000
REFL PAV MRKR TY II-A-A
EA 625.000 $3.000 $3.000 $3.000 $3.000 $3.300 $3.000
REFL PAV MRKR TY II-C-R
EA 3,487.000 $2.750 $3.000 $3.000 $3.000 $3.300 $3.000
ELIM EXT PAV MRK & MRKS (4")
LF 107,245.000 $0.750 $0.960 $0.400 $0.800 $0.600 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 4,645.000 $0.800 $0.500 $0.800 $0.800 $0.800 $0.700
FULL - WIDTH MOWING
AC 1,622.000 $175.000 $183.180 $57.890 $90.000 $97.000 $200.000
TREE AND BRUSH REMOVAL
AC 15.600 $10,000.000 $3,635.590 $10,000.000 $5,000.000 $5,000.000 $12,675.000
INSTL TIED CONCRETE EROSN CONTROL MATS
SF 82,097.000 $10.500 $4.300 $4.220 $6.500 $4.000 $4.300
WICK DRAINS
LF 421,200.000 $3.000 $3.040 $4.220 $0.600 $7.000 $4.420
GEOGRID REINFORCE EMBANKMENTS (TY A)
SY 14,500.000 $2.250 $2.680 $2.770 $4.000 $4.000 $3.850
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 2,231.000 $75.000 $31.030 $7.760 $50.000 $35.000 $38.000
ITS SYSTEM SUPPORT EQUIPMENT
LS 1.000 $20,000.000 $7,304.980 $7,305.000 $10,000.000 $8,000.000 $7,310.000
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
LF 2,485.000 $5.500 $2.700 $2.700 $3.000 $3.000 $2.700
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
LF 58,280.000 $4.000 $2.380 $2.380 $3.000 $2.600 $2.400
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 18.000 $2,500.000 $802.000 $802.000 $800.000 $870.000 $802.000
FIBER OPTIC CABLE ROAD MARKER
EA 91.000 $180.000 $89.950 $89.950 $90.000 $98.000 $90.000
FIBER OPTIC PATCH PANEL (144 POSITION)
EA 6.000 $10,000.000 $4,355.990 $4,356.000 $4,400.000 $4,720.000 $4,360.000
FO SPLICE ENCLOSURE (TYPE 3)
EA 6.000 $3,300.000 $2,583.990 $2,584.000 $3,000.000 $2,800.000 $2,580.000
ITS GRND MNT CAB (TY 4) (CONF 2)
EA 5.000 $9,550.000 $15,829.960 $15,830.000 $16,000.000 $17,100.000 $15,830.000
ITS GRND MNT CAB (TY 5) (CONF 2)
EA 1.000 $5,000.000 $17,949.960 $17,950.000 $18,000.000 $19,500.000 $17,950.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 4.000 $9,300.000 $3,109.990 $3,110.000 $3,000.000 $3,400.000 $3,110.000
REMOVE CCTV FIELD EQUIPMENT
EA 1.000 $1,800.000 $1,473.000 $1,473.000 $1,500.000 $1,600.000 $1,470.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 2.000 $18,000.000 $29,564.930 $29,565.000 $30,000.000 $32,000.000 $29,570.000
ITS POLE (50 FT)(130 MPH)
EA 4.000 $13,000.000 $14,494.960 $14,495.000 $15,000.000 $15,700.000 $14,500.000
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 4.000 $6,600.000 $5,779.990 $5,780.000 $6,000.000 $6,300.000 $5,780.000
ETHERNET SWITCH (INSTALL ONLY)
EA 11.000 $900.000 $1,244.000 $1,244.000 $1,250.000 $1,350.000 $1,240.000
MPEG 4 VIDEO ENCODER (INSTALL ONLY)
EA 4.000 $725.000 $1,021.000 $1,021.000 $1,000.000 $1,100.000 $1,020.000
LED HI MST IL ASM (6 FIXT)(SYM)(TY S)
EA 1.000 $31,000.000 $22,484.940 $22,485.000 $22,000.000 $25,000.000 $22,480.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 10.000 $28,500.000 $22,989.940 $22,990.000 $23,000.000 $25,000.000 $22,990.000
TMA (STATIONARY)
DAY 67.000 $250.000 $57.250 $400.000 $230.000 $220.000 $200.000
TMA (MOBILE OPERATION)
DAY 8.000 $200.000 $350.450 $3,500.000 $5,000.000 $220.000 $250.000
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 87.000 $3,200.000 $3,629.990 $3,630.000 $4,000.000 $4,000.000 $3,630.000
ITS GND BOX(PCAST) TY 2 (366036)W/APRN
EA 6.000 $5,000.000 $4,554.990 $4,555.000 $4,500.000 $4,900.000 $4,560.000
SYSTEM INTEGRATION
LS 1.000 $6,000.000 $9,345.980 $9,346.000 $10,000.000 $10,100.000 $9,350.000
Totals: $120,620,669.870 $118,322,898.209 $123,021,320.368 $124,903,767.830 $134,736,908.890 $143,075,075.000