NUECES SH 44 (0102-01-126)
Items: 25
County: NUECES
Length: 0.0000 MILES
Highway: SH 44
District: CORPUS CHRISTI
Control Number: 0102-01-126
DBE Goal: 0.0%
Project: STP 2025(775)HES
Guaranty: $9,000.00
Time: 59 WORKING DAYS
Engineer's Estimate: $533,197.71
Date: 05/02/2025 (1 year ago)
Contract Number: 5253232
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193518
Contract Type: Federal
Project Description: INSTALL WRONG WAY ADVANCED TECHNOLOGIES, SIGNS, AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ERNEST LONGORIA
RICARDO BRAVO
NUECES SH 44 (0102-01-126)
Project Name: N/A
Project: STP 2025(775)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: SH 358
Limits To: 0.5 MI WEST OF INTERNATIONAL DR
Project Description: INSTALL WRONG WAY ADVANCED TECHNOLOGIES, SIGNS, AND PAVEMENT MARKINGS
NUECES SH 358 (0617-01-212)
Project Name: CRP_SH0358_1_NUECES_HSIP
Project: STP 2025(775)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: LEOPARD ST.
Limits To: SH 44
Project Description: INSTALL WRONG WAY ADVANCED TECHNOLOGIES, SIGNS, AND PAVEMENT MARKINGS
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$533,197.71 | |||
| $419,929.51 |
-21.24%
-$113,268.20
|
|||
| $467,552.02 |
-12.31%
-$65,645.69
|
11.34%
$47,622.51
|
||
| $536,632.50 |
0.64%
$3,434.79
|
27.79%
$116,702.99
|
-14.77%
-$69,080.48
|
|
| $537,439.16 |
0.8%
$4,241.45
|
27.98%
$117,509.65
|
-0.15%
-$806.66
|
|
| $594,880.63 |
11.57%
$61,682.92
|
41.66%
$174,951.12
|
-10.69%
-$57,441.47
|
|
| $763,695.63 |
43.23%
$230,497.92
|
81.86%
$343,766.12
|
-28.38%
-$168,815.00
|
E
Engineer's Estimate
$533,197.71
1
Awarded
$419,929.51
Over/Under Est:
-21.24%
-$113,268.20
$467,552.02
Over/Under Est:
-12.31%
-$65,645.69
Amt Left:
11.34%
$47,622.51
$536,632.50
Over/Under Est:
0.64%
$3,434.79
Amt Left:
27.79%
$116,702.99
Delta:
-14.77%
-$69,080.48
$537,439.16
Over/Under Est:
0.8%
$4,241.45
Amt Left:
27.98%
$117,509.65
Delta:
-0.15%
-$806.66
$594,880.63
Over/Under Est:
11.57%
$61,682.92
Amt Left:
41.66%
$174,951.12
Delta:
-10.69%
-$57,441.47
$763,695.63
Over/Under Est:
43.23%
$230,497.92
Amt Left:
81.86%
$343,766.12
Delta:
-28.38%
-$168,815.00
Bid Items & Bid Tabulations
25
Total
0 of 25
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| RAILROAD FORCE ACCOUNT WORK (PART) | $3,700.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $11,200.00 |
| Total: | $20,900.00 |