NOLAN US 84 (0053-12-065)
Items: 35
County: NOLAN
Length: N/A
Highway: US 84
District: ABILENE
Control Number: 0053-12-065
DBE Goal: N/A
Project: NH 2018(551)
Guaranty: N/A
Time: 97 WORKING DAYS
Engineer's Estimate: $3,418,804.83
Date: 02/01/2018 (8 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION / ARMORING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,418,804.83 | |||
| $3,160,245.06 |
-7.56%
-$258,559.77
|
|||
| $3,687,664.28 |
7.86%
$268,859.45
|
16.69%
$527,419.22
|
||
| $3,747,408.71 |
9.61%
$328,603.88
|
18.58%
$587,163.65
|
-1.62%
-$59,744.43
|
|
| $3,856,039.53 |
12.79%
$437,234.70
|
22.02%
$695,794.47
|
-2.90%
-$108,630.82
|
|
| $3,875,910.42 |
13.37%
$457,105.59
|
22.65%
$715,665.36
|
-0.52%
-$19,870.89
|
|
| $3,950,219.95 |
15.54%
$531,415.12
|
25%
$789,974.89
|
-1.92%
-$74,309.53
|
|
| $3,988,571.72 |
16.67%
$569,766.89
|
26.21%
$828,326.66
|
-0.97%
-$38,351.77
|
|
| $4,729,638.62 |
38.34%
$1,310,833.79
|
49.66%
$1,569,393.56
|
-18.58%
-$741,066.90
|
E
Engineer's Estimate
$3,418,804.83
1
Awarded
$3,160,245.06
Over/Under Est:
-7.56%
-$258,559.77
$3,687,664.28
Over/Under Est:
7.86%
$268,859.45
Amt Left:
16.69%
$527,419.22
$3,747,408.71
Over/Under Est:
9.61%
$328,603.88
Amt Left:
18.58%
$587,163.65
Delta:
-1.62%
-$59,744.43
$3,856,039.53
Over/Under Est:
12.79%
$437,234.70
Amt Left:
22.02%
$695,794.47
Delta:
-2.90%
-$108,630.82
$3,875,910.42
Over/Under Est:
13.37%
$457,105.59
Amt Left:
22.65%
$715,665.36
Delta:
-0.52%
-$19,870.89
$3,950,219.95
Over/Under Est:
15.54%
$531,415.12
Amt Left:
25%
$789,974.89
Delta:
-1.92%
-$74,309.53
$3,988,571.72
Over/Under Est:
16.67%
$569,766.89
Amt Left:
26.21%
$828,326.66
Delta:
-0.97%
-$38,351.77
$4,729,638.62
Over/Under Est:
38.34%
$1,310,833.79
Amt Left:
49.66%
$1,569,393.56
Delta:
-18.58%
-$741,066.90