NOLAN IH 20 (0006-03-149)

Items: 20

County: NOLAN
Length: 0.0000 MILES
Highway: IH 20
District: ABILENE
Control Number: 0006-03-149
DBE Goal: 0.0%
Project: C 6-3-149
Guaranty: $19,000.00
Time: 23 WORKING DAYS
Engineer's Estimate: $970,593.50
Date: 04/04/2025 (1 year ago)
Contract Number: 4253224
Type: PREVENTIVE MAINTENANCE
Project ID: A00202528
Project Description: MILL AND FILL FRONTAGE ROADS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RYAN SAYLES
JEREMY ARREGUIN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$970,593.50
$664,504.00
Over/Under Est: -31.54% -$306,089.50
$699,318.50
Over/Under Est: -27.95% -$271,275.00
Amt Left: 5.24% $34,814.50
Over/Under Est: -11.85% -$114,989.50
Amt Left: 28.76% $191,100.00
Delta: -22.35% -$156,285.50
Over/Under Est: -10.16% -$98,592.50
Amt Left: 31.23% $207,497.00
Delta: -1.92% -$16,397.00
Over/Under Est: -8.16% -$79,211.50
Amt Left: 34.14% $226,878.00
Delta: -2.22% -$19,381.00
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 4.12% $27,377.56
BARRICADES UNLIMITED 1.11% $7,375.99
Total: 5.23% $34,753.55

Bid Items & Bid Tabulations

20 Total 0 of 20
NOLAN  |  IH 20  |  ABILENE  |  0006-03-149  |  04/04/2025  |  $970,593.50  |  C 6-3-149  |  PREVENT MAINT  |  23 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CK NEWBERRY, LLC
RK HALL, LLC
J. H. STRAIN & SONS, INC.
BONTKE BROTHERS CONSTRUCTION COMPANY
GREY SKY CONSTRUCTION LLC
SP MIXES SP-C SAC-B PG76-22
TON 950.000 $300.000 $225.000 $295.410 $215.000 $200.000 $300.000
TACK COAT
GAL 1,209.000 $10.000 $5.000 $7.820 $20.000 $10.000 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 3,188.000 $75.000 $70.000 $55.680 $75.000 $72.000 $60.000
PLANE ASPH CONC PAV(0" TO 2")
SY 2,966.000 $10.000 $4.000 $5.750 $15.000 $18.000 $20.000
PLANE ASPH CONC PAV(0" TO 4")
SY 1,680.000 $15.000 $6.000 $9.530 $18.000 $25.000 $20.000
PLANE ASPH CONC PAV(2")
SY 2,826.000 $20.000 $6.000 $8.380 $12.000 $20.000 $20.000
MOBILIZATION
LS 1.000 $98,800.000 $65,000.000 $68,998.970 $75,000.000 $200,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $50,000.000 $25,000.000 $25,000.000 $35,000.000 $15,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $18,000.000 $5,000.000 $4,096.540 $22,000.000 $500.000 $20,000.000
TMA (STATIONARY)
DAY 15.000 $400.000 $500.000 $262.880 $450.000 $300.000 $250.000
TMA (MOBILE OPERATION)
DAY 9.000 $600.000 $500.000 $364.470 $400.000 $550.000 $550.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 123.000 $3.000 $1.000 $7.360 $15.000 $1.000 $6.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 500.000 $8.500 $10.000 $9.200 $10.000 $8.000 $6.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 620.000 $2.500 $2.000 $1.840 $2.000 $8.000 $2.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 4,079.000 $2.500 $2.000 $1.840 $2.000 $2.000 $2.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 4,044.000 $2.500 $2.000 $1.840 $2.000 $2.000 $2.000
PREFAB PM TY C (W)(24")(SLD)
LF 536.000 $23.500 $20.000 $16.100 $17.500 $15.000 $20.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 16.000 $40.000 $90.000 $86.250 $95.000 $820.000 $150.000
REFL PAV MRKR TY I-C
EA 30.000 $9.000 $10.000 $8.630 $10.000 $6.000 $6.000
REFL PAV MRKR TY II-A-A
EA 58.000 $14.500 $10.000 $8.630 $9.500 $6.000 $6.000
Totals: $970,593.500 $664,504.000 $699,318.500 $855,604.000 $872,001.000 $891,382.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
Total: $6,000.00