NEWTON SS 135 (1300-03-003)

Items: 23

County: NEWTON
Length: N/A
Highway: SS 135
District: BEAUMONT
Control Number: 1300-03-003
DBE Goal: N/A
Project: C 1300-3-3
Guaranty: N/A
Time: 36 WORKING DAYS
Engineer's Estimate: $505,591.00
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
BRYCE BROUSSARD
JIM GRISSOM
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$505,591.00
Over/Under Est: 23.87% $120,682.50
Over/Under Est: 40.18% $203,123.81
Amt Left: 13.16% $82,441.31

Bid Items & Bid Tabulations

23 Total 0 of 23
NEWTON  |  SS 135  |  BEAUMONT  |  1300-03-003  |  06/01/2023  |  $505,591.00  |  C 1300-3-3  |  SURF/ROADWAY RESTOR  |  36 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A OR B)
STA 22.200 $450.000 $600.000 $1,093.830
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 736.000 $96.000 $110.000 $128.610
PLANE ASPH CONC PAV(0" TO 2")
SY 557.000 $4.000 $10.000 $26.580
RIPRAP (MOW STRIP)(4 IN)
CY 66.000 $550.000 $1,200.000 $880.000
MOBILIZATION
LS 1.000 $39,736.000 $60,000.000 $62,442.340
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $10,000.000 $4,000.000 $14,138.020
MTL W-BEAM GD FEN (TIM POST)
LF 925.000 $30.000 $30.000 $28.600
SHORT RADIUS
LF 303.000 $50.000 $300.000 $445.500
REMOVE METAL BEAM GUARD FENCE
LF 1,200.000 $3.500 $4.000 $3.300
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,300.000 $3,500.000 $3,190.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 1.000 $32,000.000 $35,000.000 $31,350.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 38.000 $475.000 $650.000 $594.000
REMOVE SM RD SN SUP&AM
EA 38.000 $93.000 $100.000 $104.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $35.000 $35.000 $38.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 222.000 $1.000 $1.500 $3.520
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 4,140.000 $0.650 $1.500 $1.320
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 4,440.000 $0.650 $1.500 $1.320
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 22.000 $20.000 $22.000 $15.950
REFL PAV MRKR TY II-A-A
EA 57.000 $4.000 $8.500 $5.500
TACK COAT
GAL 776.000 $5.000 $4.500 $6.490
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 854.000 $215.000 $180.000 $181.520
TMA (STATIONARY)
DAY 30.000 $225.000 $150.000 $144.510
TMA (MOBILE OPERATION)
DAY 7.000 $650.000 $150.000 $154.830
Totals: $505,591.000 $626,273.500 $708,714.816