NEWTON COUNTY ROAD 2018 (0920-06-040)

Items: 54

County: NEWTON
Length: 0.1100 MILES
Highway: COUNTY ROAD 2018
District: BEAUMONT
Control Number: 0920-06-040
DBE Goal: 0.0%
Project: BR 2B24(527)
Guaranty: $36,000.00
Time: 190 WORKING DAYS
Engineer's Estimate: $1,795,624.50
Date: 03/05/2026 (3 months ago)
Contract Number: 3263211
Type: BRIDGE REPLACEMENT
Project ID: A00200904
Contract Type: Federal
Project Description: CR 2018 @ HACKBERRY BRANCH BRIDGE REPLACEMENT (TXDOTCONNECT ERROR ON MAP*HIGHWAY NAME CR 229 IS ACTUALLY CR 2018)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE BROUSSARD
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$1,795,624.50
Over/Under Est: -17.25% -$309,828.76
Over/Under Est: -2.85% -$51,129.90
Amt Left: 17.41% $258,698.86
Over/Under Est: -1.1% -$19,713.30
Amt Left: 19.53% $290,115.46
Delta: -1.80% -$31,416.60
Over/Under Est: 4.15% $74,581.40
Amt Left: 25.87% $384,410.16
Delta: -5.31% -$94,294.70
$1,872,637.68
Over/Under Est: 4.29% $77,013.18
Amt Left: 26.04% $386,841.94
Delta: -0.13% -$2,431.78
Over/Under Est: 16.53% $296,834.50
Amt Left: 40.83% $606,663.26
Delta: -11.74% -$219,821.32
Over/Under Est: 23.64% $424,435.62
Amt Left: 49.42% $734,264.38
Delta: -6.10% -$127,601.12
$2,733,805.77
Over/Under Est: 52.25% $938,181.27
Amt Left: 84% $1,248,010.03
Delta: -23.14% -$513,745.65

Bid Items & Bid Tabulations

54 Total 0 of 54
NEWTON  |  COUNTY ROAD 2018  |  BEAUMONT  |  0920-06-040  |  03/05/2026  |  $1,795,624.50  |  BR 2B24(527)  |  BRIDGE REPL  |  190 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
R CONSTRUCTION CIVIL, LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
ELITE CONTRACTORS AND EQUIPMENT LTD
SKYLINE BRIDGE LLC
GARRET SHIELDS INFRASTRUCTURE
BLACKSMITH VENTURES LLC
ISI CONTRACTING, INC.
PREPARING ROW
STA 13.130 $5,000.000 $3,800.000 $2,150.000 $2,000.000 $1,000.000 $1,808.540 $1,000.000 $6,000.000 $3,179.000
RMV (0"-10") TRT/UNTRT BASE & ASPH PAV
SY 1,302.000 $10.000 $8.000 $10.000 $20.000 $7.000 $12.000 $40.000 $2.000 $15.050
EXCAV (ROADWAY)
CY 1,113.400 $25.000 $10.000 $66.000 $20.000 $18.000 $16.370 $40.000 $2.000 $33.000
EXCAV (CHANNEL)
CY 1,439.400 $30.000 $12.000 $37.000 $20.000 $23.000 $19.050 $40.000 $2.000 $24.000
EMBANK (FNL)(DC)(TY A)
CY 1,948.200 $50.000 $15.000 $32.000 $30.000 $25.000 $34.190 $40.000 $52.000 $66.000
FURN & PLACE TOPSOIL (4")
SY 5,770.000 $3.500 $4.000 $8.000 $4.000 $2.000 $4.000 $5.000 $2.000 $13.000
BROADCAST SEED (TEMP_WARM)
SY 2,885.000 $0.150 $0.800 $0.500 $0.700 $1.000 $1.200 $0.100 $0.500 $1.200
BROADCAST SEED (TEMP_COOL)
SY 2,885.000 $0.150 $0.700 $0.500 $0.680 $1.000 $1.200 $0.100 $0.500 $1.200
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 5,770.000 $0.750 $0.550 $1.000 $0.540 $1.000 $1.140 $0.100 $3.000 $1.100
VEGETATIVE WATERING
TGL 16.440 $25.000 $1.000 $260.000 $1.000 $200.000 $1.000 $50.000 $0.500 $105.000
PROOF ROLLING
HR 6.000 $100.000 $20.000 $645.000 $100.000 $200.000 $120.480 $200.000 $1,000.000 $119.000
FL BS (CMP IN PLC)(TY A GR 1-2) (10")
SY 2,878.000 $30.000 $45.000 $24.000 $30.000 $50.000 $39.350 $30.000 $90.000 $76.000
CEM STABIL BKFL
CY 259.300 $130.000 $200.000 $69.000 $200.000 $180.000 $287.560 $200.000 $195.000 $291.000
TEMPORARY SPL SHORING
SF 320.000 $30.000 $60.000 $103.000 $30.000 $82.000 $62.820 $50.000 $100.000 $44.000
PRESTR CONC PIL (16 IN SQ)
LF 1,296.000 $250.000 $145.000 $294.000 $260.000 $225.000 $308.380 $250.000 $251.000 $350.000
CL C CONC (ABUT)
CY 96.400 $1,200.000 $1,200.000 $611.000 $1,100.000 $2,000.000 $1,012.080 $1,200.000 $1,750.000 $1,970.000
CL C CONC (RAIL FOUNDATION)
CY 0.900 $1,000.000 $2,000.000 $700.000 $1,000.000 $2,250.000 $7,006.580 $1,000.000 $5,000.000 $11,830.000
REINF CONC SLAB
SF 3,120.000 $27.000 $30.000 $26.000 $25.000 $26.000 $25.020 $30.000 $26.000 $60.000
REINF CONC SLAB (SLAB BEAM)
SF 1,300.000 $27.000 $25.000 $42.000 $25.000 $25.000 $21.980 $25.000 $26.000 $44.000
PRESTR CONC GIRDER (TX28)
LF 476.000 $240.000 $260.000 $230.000 $347.600 $350.000 $372.400 $300.000 $461.000 $342.000
PRESTR CONC SLAB BEAM (5SB15)
LF 247.500 $275.000 $305.000 $270.000 $372.020 $330.000 $402.830 $350.000 $341.000 $438.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 595.000 $195.000 $190.000 $218.000 $175.000 $195.000 $167.740 $200.000 $275.000 $292.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 100.000 $450.000 $585.000 $344.000 $600.000 $650.000 $626.360 $1,000.000 $750.000 $1,633.000
RAIL (TY T223)
LF 130.000 $100.000 $140.000 $404.000 $150.000 $250.000 $137.410 $100.000 $350.000 $290.000
RAIL (TY T631LS)
LF 336.000 $67.000 $67.000 $167.000 $75.000 $72.000 $78.910 $100.000 $98.150 $67.000
TYPE A JOINT
LF 104.000 $50.000 $75.000 $143.000 $125.000 $63.000 $95.690 $75.000 $75.000 $45.000
RC PIPE (CL III)(24 IN)
LF 24.000 $200.000 $85.000 $166.000 $130.000 $120.000 $212.910 $120.000 $85.000 $139.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,000.000 $2,500.000 $2,000.000 $1,500.000 $2,000.000 $2,515.020 $2,000.000 $2,500.000 $2,435.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $15,000.000 $10,000.000 $18,800.000 $25,000.000 $10,000.000 $15,493.730 $80,000.000 $13,333.000 $28,572.000
REMOV STR (PIPE)
EA 1.000 $200.000 $500.000 $2,200.000 $3,000.000 $1,000.000 $1,265.040 $1,000.000 $1.000 $97.000
MOBILIZATION
LS 1.000 $200,000.000 $125,000.000 $70,000.000 $177,575.110 $170,000.000 $150,000.000 $150,000.000 $175,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $2,000.000 $1,320.000 $1,500.000 $3,000.000 $1,930.000 $5,000.000 $1,538.000 $1,454.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 60.000 $50.000 $1.000 $70.000 $40.000 $50.000 $50.600 $20.000 $1.000 $95.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $20.000 $1.000 $10.000 $10.000 $10.000 $12.050 $1.000 $1.000 $14.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 234.000 $37.000 $1.000 $30.000 $40.000 $30.000 $1.000 $20.000 $1.000 $41.000
CONSTRUCTION EXITS (REMOVE)
SY 234.000 $15.000 $1.000 $5.000 $10.000 $8.000 $1.000 $5.000 $1.000 $12.000
CONSTRUCTION PERIMETER FENCE
LF 510.000 $8.000 $1.000 $6.000 $5.000 $8.000 $7.000 $5.000 $10.000 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,403.000 $8.000 $1.000 $5.000 $4.000 $4.000 $3.880 $5.000 $6.000 $6.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,403.000 $6.000 $1.000 $1.000 $2.000 $1.500 $1.350 $1.000 $1.000 $1.200
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 80.000 $30.000 $40.000 $30.000 $70.000 $80.000 $119.200 $80.000 $200.000 $10.200
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 160.000 $30.000 $40.000 $30.000 $20.000 $80.000 $99.360 $80.000 $200.000 $13.800
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 60.000 $6.000 $30.000 $11.000 $20.000 $50.000 $13.950 $40.000 $1.000 $2.300
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 120.000 $6.000 $30.000 $11.000 $20.000 $50.000 $13.950 $40.000 $1.000 $2.300
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 80.000 $15.000 $30.000 $5.000 $20.000 $80.000 $36.540 $40.000 $1.000 $18.500
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 160.000 $15.000 $30.000 $5.000 $20.000 $80.000 $36.540 $40.000 $1.000 $6.200
DRIVEWAYS (BASE)
SY 43.000 $40.000 $45.000 $134.000 $70.000 $140.000 $76.170 $40.000 $100.000 $102.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $25.000 $30.000 $27.000 $27.000 $35.000 $30.120 $40.000 $36.070 $63.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $1,500.000 $1,600.000 $1,700.000 $1,850.000 $2,200.000 $1,897.560 $1,500.000 $2,372.000 $2,150.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,600.000 $1,500.000 $1,400.000 $1,565.000 $1,500.000 $1,566.240 $2,000.000 $2,015.000 $2,248.000
REMOVE METAL BEAM GUARD FENCE
LF 40.000 $5.000 $2.000 $4.000 $5.000 $10.000 $31.100 $5.000 $1.000 $15.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,000.000 $3,200.000 $3,400.000 $2,975.000 $3,500.000 $3,795.120 $3,500.000 $3,330.000 $3,858.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $25,000.000 $29,000.000 $51,700.000 $30,000.000 $35,000.000 $34,186.200 $20,000.000 $47,200.000 $25,675.000
REMOVE SM RD SN SUP&AM
EA 4.000 $80.000 $50.000 $225.000 $300.000 $150.000 $198.790 $500.000 $1.000 $115.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $40.000 $25.000 $30.000 $30.000 $50.000 $30.120 $25.000 $58.500 $15.700
Totals: $1,795,624.500 $1,485,795.740 $1,744,494.600 $1,775,911.200 $1,870,205.900 $1,872,637.673 $2,092,459.000 $2,220,060.120 $2,733,805.770
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $15,000.00