NEWTON SH 63 (0214-03-034)

Items: 71

County: NEWTON
Length: N/A
Highway: SH 63
District: BEAUMONT
Control Number: 0214-03-034
DBE Goal: N/A
Project: F 2022(029)
Guaranty: N/A
Time: 199 WORKING DAYS
Engineer's Estimate: $1,617,643.54
Date: 03/03/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (2)
E
Engineer's Estimate
$1,617,643.54
$2,254,911.00
Over/Under Est: 39.39% $637,267.46
$2,839,452.46
Over/Under Est: 75.53% $1,221,808.92
Amt Left: 25.92% $584,541.46
Subcontractor Percentage Amount
AMERICAN REMEDIATION OPTIONS, INC. 3.84% $87,495.60
BARRICADES UNLIMITED 2.21% $50,355.54
TRP CONSTRUCTION GROUP, LLC 0.83% $18,911.81
CEN TEX HYDROSEED, INC. 0.77% $17,544.69
PRIMATE CONSTRUCTION, LP 0.48% $10,936.95
CPAVE, INC. 0.29% $6,607.74
Total: 8.42% $191,852.33

Bid Items & Bid Tabulations

71 Total 0 of 71
NEWTON  |  SH 63  |  BEAUMONT  |  0214-03-034  |  03/03/2022  |  $1,617,643.54  |  F 2022(029)  |  BRIDGE REPL  |  199 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
TREVWAY, INC.
PREPARING ROW
STA 11.000 $3,500.000 $4,545.000 $10,000.000
REMOVING STAB BASE AND ASPH PAV (10")
SY 94.000 $10.000 $25.000 $25.000
REMOVE STAB BASE AND ASPH PAV (1"-3")
SY 2,878.000 $10.000 $4.950 $7.000
EXCAVATION (ROADWAY)
CY 430.000 $12.000 $33.500 $65.000
EXCAVATION (CHANNEL)
CY 1,802.000 $10.000 $15.000 $13.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 4,729.000 $24.000 $30.000 $29.000
BROADCAST SEED (TEMP) (WARM)
SY 1,739.000 $0.150 $0.520 $2.000
BROADCAST SEED (TEMP) (COOL)
SY 1,739.000 $0.150 $0.520 $2.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 3,478.000 $0.380 $0.780 $3.000
VEGETATIVE WATERING
MG 30.000 $17.000 $130.000 $100.000
PROOF ROLLING
HR 40.000 $40.000 $95.000 $100.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 4,522.000 $18.000 $26.000 $50.000
REWRK BS MATL (TY B)(10")(DENS CONT)
SY 2,878.000 $2.500 $8.000 $2.570
CEMENT
TON 51.000 $180.000 $266.000 $200.000
CEMENT TREAT (NEW BASE) (8")
SY 4,522.000 $2.500 $7.600 $5.680
ASPH (RC-250)
GAL 887.000 $4.000 $7.000 $7.000
AGGR(TY-L GR-5 SAC-B)
CY 36.000 $145.000 $780.000 $400.000
CEM STABIL BKFL
CY 100.000 $90.000 $196.000 $150.000
TEMPORARY SPL SHORING
SF 1,775.000 $26.000 $60.000 $33.000
PRESTR CONC PIL (18 IN SQ)
LF 1,120.000 $143.000 $135.000 $243.000
PRESTR CONC PIL (20 IN SQ)
LF 432.000 $165.000 $202.000 $353.000
CL C CONC (ABUT)
CY 50.800 $1,296.000 $1,792.000 $1,147.000
CL C CONC (CAP)
CY 21.300 $1,346.000 $3,230.000 $1,500.000
REINF CONC SLAB
SF 5,062.000 $21.000 $42.000 $25.000
APPROACH SLAB
CY 70.700 $350.000 $612.000 $622.000
PRESTR CONC GIRDER (TX28)
LF 654.000 $150.000 $207.000 $331.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 374.000 $184.000 $181.000 $332.000
RIPRAP (MOW STRIP)(4 IN)
CY 40.000 $450.000 $598.000 $641.000
RAIL (TY SSTR)
LF 260.000 $42.000 $145.000 $150.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 91.000 $110.000 $200.000 $156.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $36,000.000 $40,000.000 $50,000.000
MOBILIZATION
LS 1.000 $150,000.000 $215,480.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $5,000.000 $1,600.000 $1,900.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 60.000 $60.000 $53.000 $168.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $10.000 $16.000 $22.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,060.000 $3.000 $3.250 $9.540
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,060.000 $1.000 $1.050 $2.490
CONSTRUCTING DETOURS
SY 316.000 $69.000 $130.000 $300.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 10.000 $2,500.000 $5,727.000 $7,063.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,020.000 $40.000 $66.000 $91.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 840.000 $6.000 $11.750 $16.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,020.000 $10.000 $16.750 $24.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $30.000 $30.000 $32.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $2,113.000 $1,283.000
REMOVE METAL BEAM GUARD FENCE
LF 720.000 $3.000 $2.550 $10.690
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $2,980.000 $4,236.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $300.000 $253.000 $1,283.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,800.000 $1,905.000 $2,567.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $950.000 $925.000 $320.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $8,000.000 $9,900.000 $26,967.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $700.000 $678.000 $1,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $750.000 $778.000 $158.000
REMOVE SM RD SN SUP&AM
EA 4.000 $120.000 $102.000 $0.710
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $24.000 $15.500 $3.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $32.000 $37.500 $0.710
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,204.000 $0.800 $1.510 $0.320
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 88.000 $8.000 $26.150 $0.870
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 564.000 $0.800 $1.880 $0.900
PAVEMENT SEALER 4"
LF 600.000 $0.150 $0.660 $0.900
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 2,845.000 $0.500 $1.670 $0.870
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 360.000 $0.500 $1.670 $0.900
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 697.000 $0.500 $1.670 $3.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 32.000 $12.000 $22.500 $17.900
REFL PAV MRKR TY II-A-A
EA 28.000 $3.500 $8.050 $6.420
ELIM EXT PAV MRK & MRKS (4")
LF 2,783.000 $0.400 $2.000 $0.450
PAV SURF PREP FOR MRK (4")
LF 600.000 $0.050 $2.530 $1.000
D-GR HMA TY-D SAC-A PG76-22
TON 366.000 $220.000 $187.000 $250.000
TACK COAT
GAL 266.000 $4.000 $12.000 $12.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $14,500.000 $15,000.000
TMA (STATIONARY)
DAY 16.000 $350.000 $355.000 $600.000
TMA (MOBILE OPERATION)
DAY 8.000 $450.000 $600.000 $600.000
Totals: $1,617,643.540 $2,254,911.000 $2,839,452.460