NAVARRO FM1393 (6482-13-001)
Items: 13
County: NAVARRO
Length: 0.0100 MILES
Highway: FM1393
District: DALLAS
Control Number: 6482-13-001
DBE Goal: N/A
Project: BPM - A00214674
Guaranty: N/A
Time: 35 WORKING DAYS
Engineer's Estimate: $568,766.10
Date: 08/13/2025 (10 months ago)
Contract Number: 8251809
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00214674
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
4777 E HWY 80, MESQUITE, TX 75150
JUAN PAREDES
JOSEPH LANOUE
NAVARRO FM1393 (6482-13-001)
Project Name: N/A
Project: BPM - A00214674
Length: N/A
Project Type: MAINTENANCE
Limits From: NAVARRO COUNTY
Limits To: MAINTENANCE SECTION
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Informational
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$568,766.10 | |||
| $335,539.00 |
-41.01%
-$233,227.10
|
|||
| $344,444.00 |
-39.44%
-$224,322.10
|
2.65%
$8,905.00
|
||
| $350,284.00 |
-38.41%
-$218,482.10
|
4.39%
$14,745.00
|
-1.70%
-$5,840.00
|
|
| $442,124.00 |
-22.27%
-$126,642.10
|
31.77%
$106,585.00
|
-26.22%
-$91,840.00
|
|
| $471,400.00 |
-17.12%
-$97,366.10
|
40.49%
$135,861.00
|
-6.62%
-$29,276.00
|
|
| $474,850.00 |
-16.51%
-$93,916.10
|
41.52%
$139,311.00
|
-0.73%
-$3,450.00
|
|
| $491,475.00 |
-13.59%
-$77,291.10
|
46.47%
$155,936.00
|
-3.50%
-$16,625.00
|
|
| $517,364.00 |
-9.04%
-$51,402.10
|
54.19%
$181,825.00
|
-5.27%
-$25,889.00
|
|
| $624,250.00 |
9.76%
$55,483.90
|
86.04%
$288,711.00
|
-20.66%
-$106,886.00
|
E
Engineer's Estimate
$568,766.10
1
Awarded
$335,539.00
Over/Under Est:
-41.01%
-$233,227.10
$344,444.00
Over/Under Est:
-39.44%
-$224,322.10
Amt Left:
2.65%
$8,905.00
$350,284.00
Over/Under Est:
-38.41%
-$218,482.10
Amt Left:
4.39%
$14,745.00
Delta:
-1.70%
-$5,840.00
$442,124.00
Over/Under Est:
-22.27%
-$126,642.10
Amt Left:
31.77%
$106,585.00
Delta:
-26.22%
-$91,840.00
$471,400.00
Over/Under Est:
-17.12%
-$97,366.10
Amt Left:
40.49%
$135,861.00
Delta:
-6.62%
-$29,276.00
$474,850.00
Over/Under Est:
-16.51%
-$93,916.10
Amt Left:
41.52%
$139,311.00
Delta:
-0.73%
-$3,450.00
$491,475.00
Over/Under Est:
-13.59%
-$77,291.10
Amt Left:
46.47%
$155,936.00
Delta:
-3.50%
-$16,625.00
$517,364.00
Over/Under Est:
-9.04%
-$51,402.10
Amt Left:
54.19%
$181,825.00
Delta:
-5.27%
-$25,889.00
$624,250.00
Over/Under Est:
9.76%
$55,483.90
Amt Left:
86.04%
$288,711.00
Delta:
-20.66%
-$106,886.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| ALBECO CONTRACTORS LLC | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
13
Total
0 of 13