NAVARRO IH0045 (6351-13-001)

Items: 15

County: NAVARRO
Length: N/A
Highway: IH0045
District: DALLAS
Control Number: 6351-13-001
DBE Goal: N/A
Project: BPM - 635113001
Guaranty: N/A
Time: 20 W
Engineer's Estimate: $169,595.00
Date: 12/08/2020 (5 years ago)
Contract Number: N/A
Type: BPM - BRIDGE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$169,595.00
$143,114.00
Over/Under Est: -15.61% -$26,481.00
Over/Under Est: -7.1% -$12,047.00
Amt Left: 10.09% $14,434.00
Over/Under Est: -1.86% -$3,160.00
Amt Left: 16.3% $23,321.00
Delta: -5.64% -$8,887.00
Over/Under Est: 20.26% $34,354.00
Amt Left: 42.51% $60,835.00
Delta: -22.54% -$37,514.00

Bid Items & Bid Tabulations

15 Total 0 of 15
NAVARRO  |  IH0045  |  DALLAS  |  6351-13-001  |  12/08/2020  |  $169,595.00  |  BPM - 635113001  |  BPM - BRIDGE REPAIR  |  20 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
BECK-REIT & SONS, LTD.
TALBRAN ENTERPRISES LLC
SJ&J CONSTRUCTION, LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
EXCAVATION (SPECIAL)
CY 3.000 $100.000 $250.000 $220.000 $25.000 $579.000
EMBANKMENT (FINAL)(ORD COMP)(TY C2)
CY 79.000 $50.000 $50.000 $88.000 $30.000 $176.000
EMBANKMENT (FINAL)(ORD COMP)(TY C2)(DS)
CY 166.000 $55.000 $50.000 $77.000 $30.000 $92.000
FLOWABLE BACKFILL
CY 34.000 $350.000 $150.000 $275.000 $220.000 $608.000
TEMPORARY SPL SHORING
SF 42.000 $75.000 $20.000 $100.000 $35.000 $306.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 120.000 $170.000 $300.000 $110.000 $150.000 $226.000
PNEUMATICALLY PLACED CONCRETE (2")
SF 80.000 $18.000 $50.000 $110.000 $50.000 $102.000
RIPRAP (CONC)(5 IN)
CY 9.000 $575.000 $800.000 $495.000 $900.000 $1,324.000
GABION MATTRESSES (GALV)(12 IN)
SY 528.000 $125.000 $75.000 $132.000 $120.000 $69.000
GABIONS (3' X 3')(GALV)
CY 93.000 $250.000 $178.000 $250.000 $300.000 $266.000
MOBILIZATION
LS 1.000 $16,000.000 $15,000.000 $3,000.000 $20,000.000 $20,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $5,000.000 $4,000.000 $1.000 $6,000.000 $6,772.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 600.000 $4.000 $2.000 $1.000 $3.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 600.000 $1.500 $1.000 $1.000 $1.000 $2.000
TMA (STATIONARY)
DAY 2.000 $300.000 $10.000 $1.000 $150.000 $437.000
Totals: $169,595.000 $143,114.000 $157,548.000 $166,435.000 $203,949.000