Show Job Controls
Bid Cobra

NAVARRO FM 2930 (1724-03-009)

Items: 102

County: NAVARRO
Length: N/A
Highway: FM 2930
District: DALLAS
Control Number: 1724-03-009
DBE Goal: N/A
Project: C 1724-3-9
Guaranty: N/A
Time: 315 WORKING DAYS
Engineer's Estimate: $10,886,278.93
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: RECONSTRUCT EXISTING ROADWAY
Mail/Deliver Bids To: N/A
JUAN PAREDES
AMANDA MCKITTRICK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$10,886,278.93
$11,334,814.78
Over/Under Est: 4.12% $448,535.85
Over/Under Est: 6.14% $668,872.07
Amt Left: 1.94% $220,336.22
Over/Under Est: 10.12% $1,102,162.10
Amt Left: 5.77% $653,626.25
Delta: -3.75% -$433,290.03
Subcontractor Percentage Amount
BEAR CREEK CONSTRUCTION, LLC 22.49% $2,872,355.52
FORTSON CONTRACTING, INC. 2.31% $295,026.29
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 2.09% $266,928.55
STRIPE-A-ZONE, LLC 1.37% $174,972.30
H4 CONSTRUCTION SERVICES, LLC 0.96% $122,608.33
COLD CREEK CONSTRUCTION, LTD 0.62% $79,184.55
MURRAY CONSTRUCTION 0.48% $61,304.16
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.46% $58,749.82
SITE BARRICADES 0.14% $17,880.38
TEXAS TRAFFIC AND BARRICADE, LLC 0.14% $17,880.38
Total: 31.06% $3,966,890.28

Bid Items & Bid Tabulations

102 Total 0 of 102
NAVARRO  |  FM 2930  |  DALLAS  |  1724-03-009  |  08/02/2023  |  $10,886,278.93  |  C 1724-3-9  |  RECON EXIST ROADWAY  |  315 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
PREPARING ROW
STA 330.100 $800.000 $275.000 $2,500.000 $503.000
REMOVING CONC (DRIVEWAYS)
SY 269.000 $24.100 $80.000 $25.000 $33.100
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 4,497.000 $7.270 $14.000 $10.000 $13.800
EXCAVATION (ROADWAY)
CY 6,035.000 $26.000 $9.000 $20.000 $40.000
SUBGRADE WIDENING (ORD COMP)
STA 328.850 $400.000 $225.000 $750.000 $250.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 17,485.000 $17.350 $41.000 $20.000 $30.000
BACKFILL (TY A OR B)
STA 328.850 $244.350 $125.000 $250.000 $195.000
ROAD GRADER WORK (ORD COMP)
STA 328.850 $165.000 $135.000 $250.000 $500.000
COMPOST MANUF TOPSOIL (4")
SY 98,225.000 $1.370 $1.500 $1.000 $1.150
BLOCK SODDING
SY 1,764.000 $8.500 $11.750 $7.000 $7.850
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 96,461.000 $0.300 $0.260 $0.200 $0.210
DRILL SEED (TEMP)(WARM OR COOL)
SY 96,461.000 $0.300 $0.200 $0.200 $0.200
VEGETATIVE WATERING
MG 28,766.000 $5.000 $1.000 $1.000 $0.010
FL BS (RDWY DEL) (TY D GR 1-2)
TON 4,105.000 $30.000 $45.000 $35.000 $39.000
FL BS (CMP IN PLC)(TY D GR1-2)(12")
SY 102,309.000 $26.000 $29.500 $22.000 $24.940
REWORK BS MTL (TY C)(12")(ORD COMP)
SY 80,386.000 $2.800 $1.750 $2.500 $2.150
CEMENT
TON 733.000 $250.000 $308.000 $275.000 $282.000
CEMENT TREAT (MX EXST MTL & NW BS) (6")
SY 109,617.000 $2.000 $2.150 $3.000 $1.250
PRIME COAT(MC-30 OR AE-P)
GAL 20,462.000 $6.500 $6.500 $4.500 $7.300
ASPH (CRS-2P)
GAL 32,058.000 $4.820 $4.500 $4.000 $4.800
ASPH (RC-250)
GAL 9,549.000 $5.840 $5.000 $5.000 $6.800
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 273.000 $150.250 $150.000 $125.000 $270.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 51,156.000 $5.400 $4.750 $4.000 $4.350
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 853.000 $143.000 $195.000 $160.000 $178.000
AGGR (TY-B GR-4 OR TY-L GR-4 SAC-B)
CY 285.000 $190.000 $260.000 $125.000 $245.000
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 650.000 $250.000 $250.000 $125.000 $207.000
CEM STABIL BKFL
CY 3.000 $560.000 $737.000 $500.000 $779.080
TEMPORARY SPL SHORING
SF 7,604.000 $33.000 $31.000 $50.000 $32.550
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 2,200.000 $571.000 $647.000 $600.000 $683.750
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 212.000 $205.000 $309.000 $250.000 $326.750
RIPRAP (MOW STRIP)(4 IN)
CY 730.000 $700.000 $585.000 $600.000 $617.450
CONC BOX CULV (7 FT X 7 FT)
LF 56.000 $1,100.000 $944.000 $1,500.000 $998.000
RC PIPE (CL III)(18 IN)
LF 248.000 $56.570 $69.000 $85.000 $73.250
RC PIPE (CL III)(24 IN)
LF 196.000 $77.850 $123.000 $100.000 $130.250
RC PIPE (CL III)(30 IN)
LF 60.000 $99.670 $246.000 $200.000 $260.500
RC PIPE (CL III)(36 IN)
LF 152.000 $142.880 $296.000 $250.000 $312.800
RC PIPE (CL III)(42 IN)
LF 40.000 $189.600 $395.000 $275.000 $418.000
RC PIPE (CL III)(48 IN)
LF 48.000 $208.860 $416.000 $350.000 $440.000
RC PIPE (CL III)(60 IN)
LF 40.000 $400.000 $616.000 $600.000 $650.000
RC PIPE (CL III)(72 IN)
LF 32.000 $345.530 $809.000 $800.000 $855.000
HEADWALL (CH - FW - 0) (DIA= 72 IN)
EA 2.000 $22,000.000 $14,812.000 $20,000.000 $15,657.000
HEADWALL (CH - FW - 30) (DIA= 60 IN)
EA 2.000 $15,000.000 $13,500.000 $8,000.000 $14,267.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 2.000 $6,400.000 $9,900.000 $4,000.000 $10,460.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $8,457.680 $10,425.000 $7,500.000 $11,016.000
HEADWALL (CH - PW - 0) (DIA= 60 IN)
EA 1.000 $19,450.000 $13,685.000 $17,000.000 $14,466.000
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 1.000 $9,000.000 $11,250.000 $7,500.000 $11,885.000
HEADWALL (CH - PW - S) (DIA= 48 IN)
EA 1.000 $11,000.000 $15,960.000 $20,000.000 $16,872.000
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $38,000.000 $22,980.000 $50,000.000 $24,290.000
SET (TY I) (30 IN) (3: 1) (C)
EA 1.000 $7,000.000 $13,155.000 $10,000.000 $13,905.000
SET (TY I) (36 IN) (3: 1) (C)
EA 1.000 $6,200.000 $16,770.000 $12,500.000 $17,730.000
SET (TY I) (36 IN) (4: 1) (C)
EA 3.000 $7,016.600 $17,560.000 $15,000.000 $18,655.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $816.500 $1,500.000 $1,250.000 $1,587.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,900.000 $1,530.000 $1,400.000 $1,620.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 8.000 $1,246.560 $1,810.000 $1,500.000 $1,915.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $2,290.000 $2,075.000 $2,000.000 $2,195.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $3,000.000 $2,635.000 $3,000.000 $2,787.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 4.000 $3,060.000 $4,750.000 $6,000.000 $5,015.000
CLEAN EXIST CULVERTS
EA 21.000 $3,570.000 $1,640.000 $5,000.000 $1,733.000
REMOV STR (HEADWALL)
EA 27.000 $1,080.130 $1,515.000 $3,500.000 $1,599.000
REMOV STR (PIPE)
LF 524.000 $19.370 $12.000 $35.000 $12.800
REMOV STR (BOX CULVERT)
LF 8.000 $47.190 $225.000 $250.000 $239.550
MOBILIZATION
LS 1.000 $989,661.000 $760,000.000 $1,100,000.000 $1,197,190.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $11,000.000 $13,500.000 $15,000.000 $22,600.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 2,928.000 $33.000 $32.000 $35.000 $33.700
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 386.000 $70.000 $67.000 $65.000 $70.900
ROCK FILTER DAMS (REMOVE)
LF 3,314.000 $10.310 $12.000 $10.000 $12.800
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 493.000 $30.000 $15.000 $20.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 493.000 $10.500 $5.000 $10.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 19,423.000 $3.000 $3.200 $4.500 $3.350
TEMP SEDMT CONT FENCE (REMOVE)
LF 19,423.000 $0.750 $0.950 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 4,807.000 $4.200 $5.900 $7.000 $6.200
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,807.000 $1.000 $1.100 $1.000 $1.150
INTERSECTIONS (ACP)
SY 1,735.000 $54.850 $70.000 $50.000 $93.850
DRIVEWAYS (CONC)
SY 311.000 $70.000 $165.000 $125.000 $216.800
DRIVEWAYS (ACP)
SY 2,801.000 $77.000 $68.000 $50.000 $128.150
MTL W-BEAM GD FEN (TIM POST)
LF 6,385.000 $25.100 $23.000 $30.000 $29.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,390.000 $865.000 $1,000.000 $1,453.500
REMOVE METAL BEAM GUARD FENCE
LF 7,418.000 $3.040 $2.500 $3.000 $3.500
GUARDRAIL END TREATMENT (INSTALL)
EA 48.000 $3,067.080 $3,055.000 $3,000.000 $3,401.000
GUARDRAIL END TREATMENT (REMOVE)
EA 44.000 $325.000 $275.000 $300.000 $348.850
RELOCATE EXISTING MAILBOX
EA 20.000 $519.000 $305.000 $200.000 $320.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 65.000 $680.000 $616.000 $550.000 $651.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 6.000 $797.500 $745.000 $650.000 $785.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 1.000 $1,250.000 $825.000 $1,000.000 $872.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,200.000 $1,045.000 $650.000 $1,105.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 5.000 $1,361.000 $935.000 $650.000 $988.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 4.000 $1,523.190 $1,100.000 $650.000 $1,162.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 86.000 $24.000 $28.000 $35.000 $48.850
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 84.000 $63.870 $66.000 $150.000 $68.800
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 65,902.000 $0.400 $0.760 $0.750 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 153.000 $8.080 $20.500 $20.000 $23.250
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 65,032.000 $0.800 $1.140 $1.000 $1.090
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 2,880.000 $1.020 $1.170 $1.000 $1.080
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 47,859.000 $1.090 $1.140 $1.000 $1.080
REFL PAV MRKR TY II-A-A
EA 602.000 $5.040 $6.470 $6.000 $7.270
PAV SURF PREP FOR MRK (6")
LF 115,771.000 $0.010 $0.120 $0.100 $0.100
PAV SURF PREP FOR MRK (24")
LF 153.000 $0.990 $2.330 $2.000 $1.160
PAV SURF PREP FOR MRK (RPM)
EA 602.000 $0.060 $0.580 $1.000 $0.070
FULL - WIDTH MOWING
CYC 3.000 $3,704.180 $3,500.000 $5,000.000 $2,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,000.000 $16,000.000 $16,500.000 $2,900.000
TMA (STATIONARY)
DAY 315.000 $250.000 $285.000 $350.000 $485.000
TMA (MOBILE OPERATION)
HR 90.000 $80.000 $75.000 $60.000 $191.900
Totals: $10,886,278.928 $11,334,814.780 $11,555,151.000 $11,988,441.030