NAVARRO CR (0918-18-133)

Items: 63

County: NAVARRO
Length: N/A
Highway: CR
District: DALLAS
Control Number: 0918-18-133
DBE Goal: 700.0%
Project: BR 2022(309)
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $3,820,306.85
Date: 03/06/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JUAN PAREDES
AMANDA MCKITTRICK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,820,306.85
Over/Under Est: -11.54% -$440,784.55
$3,602,958.02
Over/Under Est: -5.69% -$217,348.83
Amt Left: 6.61% $223,435.72
Over/Under Est: -4.52% -$172,630.55
Amt Left: 7.93% $268,154.00
Delta: -1.24% -$44,718.28
Over/Under Est: -2.26% -$86,514.35
Amt Left: 10.48% $354,270.20
Delta: -2.36% -$86,116.20
Over/Under Est: 9.56% $365,198.75
Amt Left: 23.85% $805,983.30
Delta: -12.10% -$451,713.10
Subcontractor Percentage Amount
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.00% $0.00
MORRIS COUNTY CONTRACTORS, L.L.C. 0.00% $0.00
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
TRP CONSTRUCTION GROUP, LLC 0.00% $0.00
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

63 Total 0 of 63
NAVARRO  |  CR  |  DALLAS  |  0918-18-133  |  03/06/2024  |  $3,820,306.85  |  BR 2022(309)  |  BRIDGE REPL  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
TALBERT COMPANIES LLC
R CONSTRUCTION CIVIL, LLC
KNIFE RIVER CORPORATION - SOUTH
TRUE ROADS CONSTRUCTION, LLC
PREPARING ROW
STA 18.600 $9,700.000 $4,300.000 $20,875.000 $6,000.000 $5,500.000 $5,000.000
REMOVING STAB BASE & ASPH PAV (4"-11")
SY 2,751.300 $7.500 $16.000 $12.650 $23.000 $1.000 $10.000
EXCAVATION (ROADWAY)
CY 414.600 $35.000 $25.000 $27.600 $45.000 $75.000 $48.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 1,219.800 $50.000 $40.000 $32.200 $40.000 $40.000 $50.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 257.900 $60.000 $40.000 $32.200 $25.000 $100.000 $78.000
COMPOST MANUF TOPSOIL (4")
SY 4,211.000 $6.500 $4.500 $4.600 $6.000 $6.000 $10.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 4,211.000 $0.500 $1.500 $1.150 $0.450 $2.500 $1.200
DRILL SEED (TEMP)(WARM OR COOL)
SY 4,211.000 $0.500 $0.500 $1.150 $0.450 $2.500 $1.200
VEGETATIVE WATERING
MG 1,252.800 $20.000 $1.000 $75.900 $20.000 $1.000 $10.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 3,521.700 $30.000 $40.000 $23.000 $24.000 $35.000 $38.000
PRIME COAT(MC-30 OR AE-P)
GAL 704.200 $11.000 $12.000 $9.720 $8.000 $15.000 $48.000
ASPH (CRS-2P)
GAL 1,103.400 $7.000 $12.000 $9.560 $7.000 $12.000 $29.000
ASPH (RC-250)
GAL 328.700 $15.000 $15.000 $12.220 $10.000 $21.000 $54.000
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 9.400 $1,000.000 $650.000 $664.030 $500.000 $1,185.000 $2,800.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 1,760.900 $11.000 $15.000 $9.800 $15.000 $11.000 $38.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 ( SAC-B)
CY 29.300 $200.000 $800.000 $187.280 $300.000 $865.000 $2,800.000
AGGR (TY-B GR-4 OR TY-L GR-4 SAC-B)
CY 32.200 $950.000 $800.000 $643.680 $1,000.000 $775.000 $2,800.000
CEM STABIL BKFL
CY 94.400 $253.000 $350.000 $258.750 $85.000 $369.000 $500.000
SHEET PILING (PZ - 40)
SF 3,332.000 $150.000 $90.000 $72.450 $100.000 $160.000 $135.000
DRILL SHAFT (24 IN)
LF 921.000 $250.000 $170.000 $184.000 $435.000 $265.000 $270.000
DRILL SHAFT (36 IN)
LF 423.000 $311.000 $230.000 $264.500 $515.000 $355.000 $600.000
CL C CONC (ABUT)(HPC)
CY 72.300 $1,550.000 $2,000.000 $1,063.750 $3,200.000 $1,975.000 $1,550.000
CL C CONC (CAP)(HPC)
CY 26.500 $1,550.000 $2,500.000 $1,132.750 $2,700.000 $2,200.000 $1,950.000
CL C CONC (COLUMN)(HPC)
CY 17.000 $1,550.000 $2,500.000 $1,124.700 $3,100.000 $2,200.000 $2,200.000
CL C CONC (RAIL FOUNDATION)
CY 4.900 $1,000.000 $1,000.000 $459.200 $1,900.000 $1,200.000 $2,000.000
REINF CONC SLAB (SLAB BEAM)(HPC)
SF 8,580.000 $22.000 $30.000 $53.540 $23.000 $29.000 $34.500
APPROACH SLAB (HPC)
CY 157.500 $800.000 $1,200.000 $702.080 $1,400.000 $775.000 $850.000
RETAINING WALL (SPREAD FOOTING)
SF 255.300 $130.000 $35.000 $115.000 $90.000 $140.000 $120.000
PRESTR CONC SLAB BEAM (5SB15)
LF 1,630.000 $281.000 $255.000 $227.130 $240.000 $320.000 $325.000
RIPRAP (CONC)(CL B)(5 IN)
CY 21.500 $650.000 $800.000 $590.990 $500.000 $770.000 $850.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 778.300 $200.000 $200.000 $110.620 $190.000 $160.000 $220.000
RIPRAP (MOW STRIP)(4 IN)
CY 61.700 $700.000 $650.000 $590.990 $575.000 $750.000 $760.000
RAIL (TY T221)(HPC)
LF 114.000 $170.000 $160.000 $139.150 $185.000 $230.000 $175.000
RAIL (TY T631)
LF 682.800 $120.000 $100.000 $86.250 $100.000 $100.000 $110.000
RC PIPE (CL III)(24 IN)
LF 42.000 $230.000 $120.000 $67.850 $110.000 $140.000 $135.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $2,600.000 $2,600.000 $1,130.450 $1,800.000 $1,900.000 $2,000.000
REMOV STR (PIPE)
LF 38.000 $80.000 $5.000 $46.000 $14.000 $27.000 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $40,000.000 $18,000.000 $25,300.000 $35,000.000 $20,000.000 $22,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 2.000 $100,000.000 $26,000.000 $45,195.000 $50,000.000 $29,000.000 $30,000.000
MOBILIZATION
LS 1.000 $350,000.000 $295,000.000 $382,030.680 $200,000.000 $365,000.000 $375,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $10,000.000 $16,000.000 $10,000.000 $5,000.000 $2,500.000 $2,600.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 561.000 $38.000 $1.000 $46.000 $31.000 $47.000 $48.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 128.000 $60.000 $1.000 $86.250 $64.000 $80.000 $90.000
ROCK FILTER DAMS (REMOVE)
LF 689.000 $16.000 $1.000 $12.650 $15.000 $16.000 $13.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 621.000 $30.000 $1.000 $40.250 $33.000 $20.000 $42.000
CONSTRUCTION EXITS (REMOVE)
SY 621.000 $10.000 $1.000 $11.500 $10.000 $8.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,823.000 $5.000 $1.000 $4.890 $3.000 $8.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,823.000 $1.500 $1.000 $1.150 $1.000 $1.500 $1.200
MTL W-BEAM GD FEN (TIM POST)
LF 750.000 $30.000 $25.000 $37.370 $60.000 $30.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,400.000 $1,600.000 $27.020 $2,200.000 $2,875.000 $1,800.000
MTL BEAM GD FEN TRANS (T6)
EA 12.000 $525.000 $800.000 $743.480 $900.000 $900.000 $900.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $3,500.000 $2,800.000 $4,025.000 $3,300.000 $3,500.000 $3,300.000
WIRE FENCE (TY A)
LF 877.600 $30.000 $20.000 $31.210 $15.000 $27.000 $20.000
GATE (TY 1)
EA 3.000 $2,100.000 $2,000.000 $2,143.000 $1,700.000 $2,700.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 6.000 $25.000 $20.000 $28.320 $20.000 $25.000 $24.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 18.000 $55.000 $20.000 $30.120 $20.000 $25.000 $24.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 16.000 $100.000 $200.000 $100.000 $45.000 $100.000 $90.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 48.000 $55.000 $25.000 $42.610 $25.000 $30.000 $30.000
PAVEMENT SEALER 6"
LF 7,340.000 $0.500 $1.000 $0.580 $0.750 $0.850 $2.400
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 3,617.000 $1.500 $2.500 $1.780 $3.000 $2.700 $4.800
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 3,724.000 $1.500 $2.500 $1.780 $3.000 $2.700 $4.800
PAV SURF PREP FOR MRK (6")
LF 7,340.000 $0.500 $1.000 $0.400 $0.020 $0.850 $1.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $18,000.000 $35,000.000 $17,250.000 $11,000.000 $12,000.000 $18,600.000
Totals: $3,820,306.850 $3,379,522.300 $3,602,958.079 $3,647,676.300 $3,733,792.500 $4,185,505.600