SAN AUGUSTINE SH0021 (6480-13-001)

Items: 25

County: SAN AUGUSTINE
Length: 0.0100 MILES
Highway: SH0021
District: LUFKIN
Control Number: 6480-13-001
DBE Goal: N/A
Project: BPM - A00214050
Guaranty: $11,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $518,760.00
Date: 07/09/2025 (11 months ago) Changed
Contract Number: 7251101
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00214050
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
LAUREN PERRY
TAMARA GIBSON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$518,760.00
$425,610.00
Over/Under Est: -17.96% -$93,150.00
Over/Under Est: 11.43% $59,317.00
Amt Left: 35.82% $152,467.00

Bid Items & Bid Tabulations

25 Total 0 of 25
SAN AUGUSTINE  |  SH0021  |  LUFKIN  |  6480-13-001  |  07/09/2025  |  $518,760.00  |  BPM - A00214050  |  BRIDGE PREVENT MAINT  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACE CONTRACTORS, INC.
CROSS PLUS CONSTRUCTION, LLC
REMOV CONC (RIPRAP)
SY 85.000 $45.000 $25.000 $55.000
EMBANK (VEH)(OC)(TY B)
CY 247.000 $60.000 $75.000 $55.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 30.000 $100.000 $100.000 $125.000
BLOCK SODDING
SY 220.000 $10.000 $10.000 $14.000
BROADCAST SEED (TEMP_WARM)
SY 220.000 $1.000 $1.000 $1.000
BROADCAST SEED (TEMP_COOL)
SY 220.000 $1.000 $1.000 $1.000
VEGETATIVE WATERING
TGL 14.000 $50.000 $5.000 $123.000
CEM STABIL BKFL
CY 7.000 $500.000 $300.000 $900.000
FLOWABLE BACKFILL
CY 97.000 $350.000 $350.000 $600.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 3.000 $300.000 $1,000.000 $1,200.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 31.000 $400.000 $250.000 $200.000
RIPRAP (CONC)(4 IN)
CY 10.000 $850.000 $375.000 $900.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 717.000 $225.000 $275.000 $275.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 1.000 $5,000.000 $500.000 $1,500.000
CLEAN EXIST CULVERTS
EA 4.000 $5,000.000 $4,000.000 $1,500.000
REMOV STR (SET)
EA 1.000 $1,000.000 $1,500.000 $1,500.000
MOBILIZATION
LS 1.000 $47,000.000 $25,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $200.000 $5,200.000
TMA (STATIONARY)
DAY 45.000 $200.000 $300.000 $410.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $10.000 $10.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $5.000 $2.000 $1.000
DRIFTWOOD REMOVAL
LS 29.000 $4,000.000 $2,500.000 $3,000.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 15.000 $800.000 $75.000 $900.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 24.000 $50.000 $500.000 $250.000
CONCRETE BEAM REPAIR (CFRP)
EA 2.000 $17,000.000 $3,000.000 $30,000.000
Totals: $518,760.000 $425,610.000 $578,077.000