NACOGDOCHES FM 1878 (1810-01-032)

Items: 67

County: NACOGDOCHES
Length: N/A
Highway: FM 1878
District: LUFKIN
Control Number: 1810-01-032
DBE Goal: N/A
Project: BR 2017(829)
Guaranty: N/A
Time: 115 WORKING DAYS
Engineer's Estimate: $2,043,699.25
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$2,043,699.25
Over/Under Est: -13.16% -$268,869.80
Over/Under Est: -7.55% -$154,299.55
Amt Left: 6.46% $114,570.25
Over/Under Est: -5.93% -$121,261.73
Amt Left: 8.32% $147,608.07
Delta: -1.75% -$33,037.82
Over/Under Est: -3.19% -$65,251.25
Amt Left: 11.47% $203,618.55
Delta: -2.91% -$56,010.48
Over/Under Est: -2.88% -$58,807.30
Amt Left: 11.84% $210,062.50
Delta: -0.33% -$6,443.95
Over/Under Est: -2.35% -$47,959.25
Amt Left: 12.45% $220,910.55
Delta: -0.55% -$10,848.05
$1,998,888.88
Over/Under Est: -2.19% -$44,810.37
Amt Left: 12.62% $224,059.43
Delta: -0.16% -$3,148.88
Over/Under Est: 3.8% $77,601.99
Amt Left: 19.52% $346,471.79
Delta: -6.12% -$122,412.36

Bid Items & Bid Tabulations

67 Total 0 of 67
NACOGDOCHES  |  FM 1878  |  LUFKIN  |  1810-01-032  |  03/07/2017  |  $2,043,699.25  |  BR 2017(829)  |  BRIDGE REPL  |  115 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DREWERY CONSTRUCTION COMPANY, INCORPORATED
EAST TEXAS BRIDGE, INC.
COPPELL CONSTRUCTION CO., INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
STATELINE CONSTRUCTION, LLC
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 1.000 $1,500.000 $2,200.000 $3,000.000 $2,000.000 $2,000.000 $5,500.000 $2,000.000 $2,000.000 $1,000.000
REMOVING CONC (RIPRAP)
SY 69.000 $20.000 $18.000 $20.000 $23.000 $40.000 $40.000 $25.000 $50.000 $25.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 393.000 $50.000 $8.000 $10.000 $8.000 $20.000 $20.000 $4.000 $9.000 $10.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 9.000 $500.000 $30.000 $30.000 $94.000 $20.000 $80.000 $50.000 $45.000 $50.000
REMOVING STAB BASE & ASPH PAV (0"-10")
SY 1,519.000 $15.000 $7.000 $9.000 $11.000 $12.000 $7.000 $6.250 $8.000 $15.000
EXCAVATION (ROADWAY)
CY 810.000 $20.000 $12.000 $15.000 $29.000 $16.000 $15.000 $19.000 $17.000 $10.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 324.000 $30.000 $37.000 $25.000 $32.000 $16.000 $28.000 $23.000 $39.000 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 302.000 $20.000 $23.000 $25.000 $20.000 $16.000 $24.000 $23.000 $37.000 $50.000
COMPOST MANUF TOPSOIL (4")
SY 1,948.000 $2.000 $5.450 $5.000 $3.000 $2.500 $7.000 $2.000 $3.750 $1.590
BLOCK SODDING
SY 1,948.000 $10.000 $4.200 $4.500 $4.250 $5.000 $5.000 $4.000 $4.000 $4.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 1,948.000 $1.000 $0.550 $0.850 $2.640 $1.000 $0.550 $0.750 $0.860 $0.770
CELL FBR MLCH SEED(TEMP)(COOL)
SY 1,948.000 $1.000 $0.550 $0.850 $2.640 $1.000 $0.550 $0.750 $0.870 $0.770
VEGETATIVE WATERING
MG 58.500 $50.000 $35.000 $20.000 $90.000 $1.000 $50.000 $25.000 $60.000 $10.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 380.000 $5.000 $1.600 $3.000 $2.240 $3.000 $2.000 $2.900 $2.950 $3.000
PRIME COAT (MC-30)
GAL 529.000 $10.000 $4.300 $10.000 $8.000 $12.000 $2.900 $8.750 $8.750 $10.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,010.000 $10.000 $3.300 $10.000 $9.000 $10.000 $4.000 $10.000 $11.700 $10.000
AGGR (TY E OR L, PE OR PL GR 4)
CY 22.000 $120.000 $270.000 $275.000 $250.000 $400.000 $400.000 $700.000 $780.000 $1,000.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 1,452.000 $100.000 $107.000 $115.000 $130.000 $140.000 $114.000 $155.000 $150.000 $130.000
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
TON 264.000 $125.000 $120.000 $130.000 $140.000 $140.000 $128.000 $165.000 $160.000 $130.000
PLANE ASPH CONC PAV (1")
SY 2,642.000 $10.000 $3.500 $5.000 $4.000 $4.000 $5.000 $3.000 $4.250 $6.000
CEM STABIL BKFL
CY 216.000 $175.000 $140.000 $225.000 $147.000 $180.000 $200.000 $175.000 $214.000 $200.000
DRILL SHAFT (24 IN)
LF 732.000 $150.000 $104.000 $115.000 $113.000 $110.000 $130.000 $107.000 $117.000 $140.000
CL A CONC (MISC)
CY 2.300 $600.000 $660.000 $700.000 $1,100.000 $1,000.000 $1,100.000 $1,000.000 $700.000 $500.000
CL C CONC (ABUT)
CY 40.800 $1,000.000 $980.000 $930.000 $1,100.000 $1,000.000 $900.000 $1,125.000 $1,000.000 $1,000.000
CL C CONC (BENT)
CY 73.000 $1,500.000 $1,200.000 $950.000 $1,100.000 $1,000.000 $950.000 $1,450.000 $1,100.000 $1,200.000
CL C CONC (RAIL FOUNDATION)
CY 38.000 $350.000 $580.000 $550.000 $440.000 $600.000 $900.000 $450.000 $600.000 $1,000.000
REINF CONC SLAB (SLAB BEAM)
SF 10,880.000 $20.000 $12.000 $15.000 $16.000 $16.000 $19.000 $18.500 $15.600 $15.000
APPROACH SLAB
CY 108.200 $500.000 $510.000 $535.000 $400.000 $600.000 $550.000 $650.000 $500.000 $500.000
PRESTR CONC SLAB BEAM (4SB15)
LF 632.000 $160.000 $146.000 $135.000 $161.740 $160.000 $155.000 $175.000 $138.000 $167.000
PRESTR CONC SLAB BEAM (5SB15)
LF 1,580.000 $190.000 $146.000 $135.000 $161.740 $160.000 $155.000 $150.000 $138.000 $167.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 287.800 $500.000 $550.000 $450.000 $475.000 $400.000 $550.000 $400.000 $415.000 $500.000
RIRRAP (STONE COMMON)(DRY)(15 IN)
CY 79.000 $185.000 $182.000 $165.000 $250.000 $150.000 $230.000 $225.000 $200.000 $200.000
RAIL (TY C411)
LF 400.000 $175.000 $159.000 $185.000 $160.000 $90.000 $200.000 $225.000 $200.000 $210.000
RAIL (TY PR1)
LF 637.000 $95.000 $68.000 $70.000 $75.000 $160.000 $100.000 $75.000 $80.000 $75.000
ARMOR JOINT (SEALED)
LF 136.000 $110.000 $88.000 $90.000 $59.000 $80.000 $100.000 $72.000 $95.000 $120.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $65,000.000 $100,000.000 $80,000.000 $111,000.000 $100,000.000 $47,000.000 $90,000.000 $105,000.000 $100,000.000
MOBILIZATION
LS 1.000 $182,000.000 $178,500.000 $180,000.000 $190,000.000 $225,000.000 $200,000.000 $185,000.000 $199,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $2,000.000 $1,900.000 $5,000.000 $1,800.000 $5,000.000 $2,000.000 $4,000.000 $3,000.000 $2,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 28.000 $30.000 $52.500 $40.000 $83.000 $60.000 $50.000 $45.000 $82.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 28.000 $10.000 $21.000 $5.000 $18.000 $20.000 $20.000 $15.000 $20.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $20.000 $31.500 $30.000 $60.000 $30.000 $30.000 $12.000 $58.000 $75.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $9.500 $9.450 $7.000 $16.000 $10.000 $9.000 $12.000 $16.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,077.000 $3.000 $3.300 $3.000 $2.500 $3.000 $3.500 $3.000 $2.580 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,077.000 $1.000 $1.050 $0.500 $1.500 $1.000 $1.000 $1.000 $1.700 $1.000
CONC CURB & GUTTER (TY II)
LF 831.000 $40.000 $25.000 $25.000 $24.000 $24.000 $60.000 $35.000 $54.000 $35.000
CONC SIDEWALKS (4")
SY 613.000 $75.000 $63.000 $65.000 $90.000 $46.000 $80.000 $61.000 $65.000 $65.000
CURB RAMPS (TY 10)
EA 1.000 $4,000.000 $1,800.000 $3,000.000 $1,700.000 $600.000 $3,400.000 $3,500.000 $2,000.000 $1,800.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $20.000 $25.200 $25.000 $22.000 $30.000 $25.000 $26.000 $33.000 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,500.000 $2,900.000 $2,100.000 $2,000.000 $1,800.000 $1,500.000 $1,700.000 $2,112.000 $1,800.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $2.500 $4.400 $3.300 $3.000 $5.000 $5.000 $3.000 $3.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $150.000 $165.000 $220.000 $200.000 $400.000 $500.000 $200.000 $340.000 $500.000
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 2.000 $2,000.000 $2,150.000 $2,500.000 $2,300.000 $2,400.000 $2,100.000 $2,500.000 $2,740.000 $2,510.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 3.000 $300.000 $340.000 $550.000 $550.000 $600.000 $400.000 $475.000 $780.000 $800.000
REMOVE SM RD SN SUP&AM
EA 5.000 $120.000 $75.000 $100.000 $200.000 $100.000 $100.000 $75.000 $110.000 $200.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 6.000 $50.000 $15.750 $22.000 $20.000 $60.000 $20.000 $21.000 $36.030 $25.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 4.000 $60.000 $47.250 $45.000 $40.000 $60.000 $50.000 $50.000 $84.000 $65.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 6.000 $50.000 $29.000 $30.000 $25.000 $60.000 $30.000 $21.000 $54.390 $42.000
PAVEMENT SEALER 4"
LF 3,124.000 $1.000 $1.050 $1.100 $1.000 $0.500 $1.250 $1.250 $1.100 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 320.000 $1.000 $1.050 $1.100 $1.000 $1.000 $1.250 $1.250 $1.250 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,236.000 $1.000 $1.600 $1.650 $1.500 $1.000 $1.700 $1.750 $1.660 $1.500
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,568.000 $1.000 $1.600 $1.650 $1.500 $1.000 $1.700 $1.750 $1.650 $1.500
REFL PAV MRKR TY I-C
EA 16.000 $3.500 $8.000 $8.250 $7.500 $6.000 $9.000 $8.500 $11.500 $7.500
REFL PAV MRKR TY II-A-A
EA 20.000 $3.000 $8.000 $8.250 $7.500 $10.000 $9.000 $8.500 $10.850 $7.500
ELIM EXT PAV MRK & MRKS (4")
LF 47.000 $5.000 $3.150 $3.300 $3.000 $2.000 $3.500 $3.500 $4.450 $3.000
PAV SURF PREP FOR MRK (4")
LF 1,225.000 $0.250 $1.050 $1.100 $1.000 $1.500 $1.250 $1.500 $1.120 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $8,000.000 $30,000.000 $5,000.000 $12,000.000 $10,000.000 $6,000.000 $13,500.000 $5,000.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $5.000 $75.000 $10.000 $15.000 $10.000 $20.000 $15.000 $34.600 $10.000
Totals: $2,043,699.250 $1,774,829.450 $1,889,399.700 $1,922,437.520 $1,978,448.000 $1,984,891.950 $1,995,740.000 $1,998,888.880 $2,121,301.240