Bid Cobra

NACOGDOCHES SH 21 (0118-08-076)

Items: 83

County: NACOGDOCHES
Length: N/A
Highway: SH 21
District: LUFKIN
Control Number: 0118-08-076
DBE Goal: N/A
Project: BR 2021(343)
Guaranty: N/A
Time: 321 WORKING DAYS
Engineer's Estimate: $5,795,198.60
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (6)
E
Engineer's Estimate
$5,795,198.60
$5,478,921.25
Over/Under Est: -5.46% -$316,277.35
Over/Under Est: -1.79% -$104,022.08
Amt Left: 3.87% $212,255.27
Over/Under Est: 7.22% $418,197.06
Amt Left: 13.41% $734,474.41
Delta: -9.18% -$522,219.14
Over/Under Est: 12.8% $741,815.20
Amt Left: 19.31% $1,058,092.55
Delta: -5.21% -$323,618.14
Over/Under Est: 16.18% $937,425.11
Amt Left: 22.88% $1,253,702.46
Delta: -2.99% -$195,609.91
$7,118,015.59
Over/Under Est: 22.83% $1,322,816.99
Amt Left: 29.92% $1,639,094.34
Delta: -5.72% -$385,391.88
Subcontractor Percentage Amount
SKYLINE BRIDGE LLC 52.52% $2,960,644.44
RAYFORD'S TRUCK & TRACTOR 9.18% $517,492.69
PREMIER PAVING, LTD. 4.26% $240,143.67
DREWERY CONSTRUCTION COMPANY, INCORPORATED 3.92% $220,977.27
GVK GROUP LLC 2.64% $148,821.43
PEACHTREE CONSTRUCTION, LTD. 2.26% $127,400.16
MORRIS COUNTY CONTRACTORS, L.L.C. 1.18% $66,518.67
STRIPING TECHNOLOGY, L.P. 0.52% $29,313.31
TEXOP CONSTRUCTION 0.48% $27,058.44
PANOLA SIGN & BARRICADE, INC. 0.31% $17,475.24
CAP RIVER LLC 0.31% $17,475.24
PRIMATE CONSTRUCTION, LP 0.18% $10,146.92
PANOLA SIGN & BARRICADE, INC. 0.15% $8,455.76
TEXOP CONSTRUCTION 0.14% $7,892.05
NEXT CONSTRUCTION SOLUTIONS LLC 0.05% $2,818.59
Total: 78.10% $4,402,633.88

Bid Items & Bid Tabulations

83 Total 0 of 83
NACOGDOCHES  |  SH 21  |  LUFKIN  |  0118-08-076  |  05/06/2021  |  $5,795,198.60  |  BR 2021(343)  |  BRIDGE REPL  |  321 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
HIGHWAY 19 CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
A. L. HELMCAMP, INC.
PREPARING ROW
STA 35.400 $1,500.000 $675.000 $5,000.000 $2,500.000 $3,500.000 $2,800.000 $3,000.000
EXCAVATION (ROADWAY)
CY 11,240.000 $10.000 $10.000 $4.750 $10.000 $15.000 $10.000 $7.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 5,555.000 $6.000 $14.000 $12.250 $13.000 $15.000 $7.400 $8.000
BLADING
STA 26.700 $110.000 $325.000 $230.000 $250.000 $1.000 $325.000 $150.000
BLOCK SODDING
SY 117.000 $5.000 $10.250 $8.250 $10.000 $10.000 $8.500 $7.880
BROADCAST SEED (TEMP) (WARM)
SY 5,357.000 $0.150 $0.250 $0.170 $0.280 $0.500 $0.200 $0.170
BROADCAST SEED (TEMP) (COOL)
SY 5,357.000 $0.150 $0.250 $0.170 $0.280 $0.500 $0.200 $0.170
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 26,202.000 $0.400 $0.370 $0.350 $0.400 $0.500 $0.350 $0.330
VEGETATIVE WATERING
MG 740.600 $15.000 $11.000 $5.000 $10.000 $1.000 $20.000 $20.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 2,989.000 $1.250 $1.500 $1.200 $1.000 $2.000 $1.250 $1.140
FL BS (RDWY DEL) (TY D GR 1-2)
TON 1,480.600 $35.000 $59.000 $35.000 $35.000 $55.000 $51.000 $65.000
CEMENT
TON 76.300 $150.000 $200.000 $218.000 $180.000 $200.000 $195.000 $170.000
CEMENT TREAT (NEW BASE 14")
SY 996.000 $2.000 $5.700 $2.000 $10.000 $8.000 $5.500 $14.000
CEM TRT(MX EXST MTL & NEW BS)(14")
SY 2,590.000 $5.000 $9.000 $2.150 $3.500 $8.000 $6.750 $4.000
ASPH (RC-250)
GAL 928.000 $4.000 $12.000 $4.900 $10.000 $6.000 $10.000 $4.500
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 4,903.000 $4.500 $9.000 $3.750 $6.000 $6.000 $4.000 $3.500
AGGR (TY E OR L, PE OR PL GR 4)
CY 112.000 $120.000 $342.000 $160.000 $180.000 $300.000 $270.000 $295.000
AGGR (TY E OR L GR 5)
CY 30.000 $110.000 $342.000 $210.000 $500.000 $300.000 $300.000 $445.000
CEM STABIL BKFL
CY 274.000 $100.000 $225.000 $190.000 $180.000 $250.000 $180.000 $180.000
DRILL SHAFT (18 IN)
LF 182.000 $70.000 $149.500 $53.000 $120.000 $75.000 $60.000 $125.000
DRILL SHAFT (36 IN)
LF 2,579.000 $190.000 $160.000 $165.000 $173.000 $140.000 $180.000 $160.000
CL C CONC (ABUT)
CY 67.600 $1,000.000 $800.000 $925.000 $755.000 $1,000.000 $950.000 $1,100.000
CL C CONC (CAP)
CY 286.000 $1,000.000 $850.000 $950.000 $1,200.000 $1,000.000 $975.000 $1,100.000
CL C CONC (COLUMN)
CY 63.800 $1,150.000 $1,050.000 $950.000 $1,000.000 $1,000.000 $1,000.000 $1,500.000
REINF CONC SLAB
SF 55,680.000 $15.000 $14.000 $17.000 $18.000 $20.000 $18.600 $22.000
APPROACH SLAB
CY 89.900 $525.000 $400.000 $475.000 $500.000 $650.000 $545.000 $800.000
PRESTR CONC GIRDER (TX34)
LF 6,678.420 $140.000 $145.000 $140.000 $157.000 $150.000 $158.000 $130.000
RIPRAP (CONC)(5 IN)
CY 71.000 $500.000 $350.000 $400.000 $500.000 $500.000 $505.000 $550.000
RAIL (TY T223)
LF 1,972.000 $115.000 $82.000 $75.000 $100.000 $100.000 $96.000 $90.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 290.000 $120.000 $95.000 $100.000 $180.000 $100.000 $125.000 $100.000
RC PIPE (CL III)(24 IN)
LF 40.000 $70.000 $85.000 $80.000 $120.000 $100.000 $90.000 $90.000
RC PIPE (CL III)(48 IN)
LF 8.000 $150.000 $210.000 $200.000 $310.000 $300.000 $225.000 $350.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 2.000 $2,000.000 $835.000 $935.000 $1,200.000 $2,500.000 $850.000 $650.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 1.000 $5,000.000 $5,000.000 $5,000.000 $75,000.000 $9,000.000 $4,500.000 $4,200.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $20,000.000 $70,000.000 $25,000.000 $60,000.000 $45,000.000 $34,000.000 $25,000.000
REMOV STR (PIPE)
EA 1.000 $600.000 $1,500.000 $3,500.000 $1,000.000 $500.000 $225.000 $1,200.000
REMOV STR (SMALL FENCE)
LF 1,870.000 $2.500 $2.250 $3.000 $10.000 $5.000 $2.250 $2.500
MOBILIZATION
LS 1.000 $527,000.000 $275,000.000 $400,000.000 $600,000.000 $550,000.000 $600,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 27.000 $4,100.000 $2,000.000 $1,800.000 $5,000.000 $2,500.000 $2,000.000 $9,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $35.000 $50.000 $38.000 $45.000 $35.000 $39.000 $36.230
ROCK FILTER DAMS (REMOVE)
LF 80.000 $8.000 $15.000 $8.000 $12.000 $15.000 $9.000 $8.400
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 444.000 $28.000 $5.000 $22.000 $37.000 $30.000 $22.500 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $8.500 $2.000 $8.000 $8.000 $15.000 $9.000 $2.000
CONSTRUCTION PERIMETER FENCE
LF 2,271.000 $2.250 $11.000 $5.000 $35.000 $7.000 $5.000 $3.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,296.000 $2.550 $3.000 $3.150 $3.000 $4.000 $3.200 $2.990
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,296.000 $1.000 $1.000 $1.000 $0.500 $2.000 $1.100 $1.000
CONSTRUCTING DETOURS
SY 5,811.000 $160.000 $132.000 $150.000 $80.000 $135.000 $205.000 $240.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,648.000 $35.000 $75.000 $70.000 $75.000 $85.000 $87.000 $75.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 1,680.000 $7.000 $22.500 $14.000 $25.000 $30.000 $34.000 $25.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 4,328.000 $15.000 $6.450 $6.000 $25.000 $35.000 $9.000 $22.000
DRIVEWAYS (ACP)
SY 211.000 $35.000 $50.000 $85.000 $55.000 $90.000 $41.000 $65.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,000.000 $25.000 $27.000 $24.750 $23.000 $25.000 $25.000 $23.630
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $1,710.000 $1,570.000 $1,500.000 $1,600.000 $2,500.000 $1,497.300
REMOVE METAL BEAM GUARD FENCE
LF 900.000 $5.000 $2.400 $2.500 $2.000 $2.000 $5.000 $2.630
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $3,120.000 $2,640.000 $2,500.000 $2,600.000 $2,700.000 $2,520.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $400.000 $240.000 $275.000 $250.000 $500.000 $255.000 $262.500
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,150.000 $600.000 $990.000 $1,000.000 $1,500.000 $1,000.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $10,500.000 $9,800.000 $9,790.000 $7,500.000 $12,000.000 $10,000.000 $10,000.000
WIRE FENCE (TY A)
LF 3,570.000 $15.000 $10.250 $12.000 $15.000 $15.000 $12.500 $4.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $350.000 $1,025.000 $357.500 $850.000 $800.000 $365.000 $341.250
RELOCATE SM RD SN SUP&AM TY TWT
EA 2.000 $450.000 $850.000 $434.500 $350.000 $800.000 $445.000 $414.750
REMOVE SM RD SN SUP&AM
EA 1.000 $80.000 $300.000 $104.500 $100.000 $50.000 $80.000 $99.750
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 22.000 $35.000 $18.000 $16.500 $35.000 $50.000 $17.000 $15.750
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 17.000 $40.000 $30.000 $30.250 $65.000 $50.000 $31.000 $28.880
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,541.000 $0.150 $0.400 $1.100 $1.000 $1.500 $1.150 $0.270
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 3,439.000 $0.150 $0.400 $1.100 $1.000 $1.500 $1.150 $0.270
PAVEMENT SEALER 4"
LF 4,080.000 $0.150 $0.400 $0.550 $0.500 $1.000 $0.600 $0.270
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 7,064.000 $0.500 $1.000 $1.380 $1.250 $1.500 $1.400 $0.680
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 7,064.000 $0.500 $1.000 $1.380 $1.250 $1.500 $1.400 $0.680
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 883.000 $0.500 $0.620 $4.400 $4.000 $4.500 $4.500 $0.420
REFL PAV MRKR TY I-C
EA 45.000 $3.000 $7.500 $5.500 $5.000 $10.000 $6.000 $5.250
REFL PAV MRKR TY II-A-A
EA 89.000 $3.000 $7.500 $5.500 $5.000 $10.000 $6.000 $5.250
ELIM EXT PAV MRK & MRKS (4")
LF 7,320.000 $0.480 $1.030 $1.100 $1.000 $1.500 $1.150 $0.710
PAV SURF PREP FOR MRK (4")
LF 4,080.000 $0.300 $0.750 $0.550 $0.500 $1.000 $0.600 $0.090
D-GR HMA TY-B PG64-22
TON 666.200 $90.000 $140.000 $125.000 $130.000 $120.000 $145.000 $115.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 202.800 $200.000 $200.000 $130.000 $130.000 $120.000 $220.000 $160.000
TACK COAT
GAL 32.000 $3.000 $25.000 $4.000 $5.000 $8.000 $4.000 $20.000
SP MIXES SP-C PG64-22 (LEVEL-UP)
TON 162.400 $150.000 $150.000 $140.000 $120.000 $120.000 $185.000 $175.000
SP MIXES SP-C SAC-A PG70-22
TON 1,646.900 $120.000 $150.000 $110.000 $110.000 $120.000 $135.000 $110.000
TACK COAT
GAL 737.000 $3.000 $7.000 $4.000 $5.000 $5.000 $4.000 $11.140
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $4,000.000 $17,000.000 $10,000.000 $32,000.000 $11,500.000 $10,000.000
TMA (STATIONARY)
DAY 4.000 $210.000 $500.000 $350.000 $1,000.000 $200.000 $500.000 $500.000
TMA (MOBILE OPERATION)
DAY 4.000 $210.000 $350.000 $350.000 $500.000 $200.000 $300.000 $520.000
Totals: $5,795,198.600 $5,478,921.250 $5,691,176.520 $6,213,395.660 $6,537,013.800 $6,732,623.710 $7,118,015.590