MOTLEY SH 70 (0105-04-047)
Items: 63
County: MOTLEY
Length: 0.0000 MILES
Highway: SH 70
District: CHILDRESS
Control Number: 0105-04-047
DBE Goal: 0.0%
Project: BR 2026(651)
Guaranty: $74,000.00
Time: 243 WORKING DAYS
Engineer's Estimate: $3,331,356.57
Date: 06/02/2026 (8 days ago)
Contract Number: 6263011
Type: BRIDGE REPLACEMENT
Project ID: A00200068
Contract Type: Federal
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MOTLEY SH 70 (0105-04-047)
Project Name: N/A
Project: BR 2026(651)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: SH 70 @ QUITAQUE RIVER
Limits To: .
Project Description: BRIDGE REPLACEMENT
HALL SH 70 (0311-03-015)
Project Name: SH 70 @ LITTLE RED RIVER
Project: BR 2026(651)
Length: 0.0000 MILES
Project Type: BRIDGE WIDENING OR REHABILITATION
Limits From: SH 70 @ LITTLE RED RIVER
Limits To: .
Project Description: BRIDGE REHABILITATION
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,331,356.57 | |||
| $3,403,214.02 |
2.16%
$71,857.45
|
|||
| $3,678,459.71 |
10.42%
$347,103.14
|
8.09%
$275,245.69
|
||
| $3,932,667.50 |
18.05%
$601,310.93
|
15.56%
$529,453.48
|
-6.91%
-$254,207.79
|
|
| $3,960,161.83 |
18.88%
$628,805.26
|
16.37%
$556,947.81
|
-0.70%
-$27,494.33
|
|
| $4,044,922.50 |
21.42%
$713,565.93
|
18.86%
$641,708.48
|
-2.14%
-$84,760.67
|
|
| $4,553,977.12 |
36.7%
$1,222,620.55
|
33.81%
$1,150,763.10
|
-12.59%
-$509,054.62
|
|
| $4,869,670.80 |
46.18%
$1,538,314.23
|
43.09%
$1,466,456.78
|
-6.93%
-$315,693.68
|
|
| $5,374,970.65 |
61.34%
$2,043,614.08
|
57.94%
$1,971,756.63
|
-10.38%
-$505,299.85
|
|
| $6,005,898.21 |
80.28%
$2,674,541.64
|
76.48%
$2,602,684.19
|
-11.74%
-$630,927.56
|
E
Engineer's Estimate
$3,331,356.57
$3,403,214.02
Over/Under Est:
2.16%
$71,857.45
$3,678,459.71
Over/Under Est:
10.42%
$347,103.14
Amt Left:
8.09%
$275,245.69
$3,932,667.50
Over/Under Est:
18.05%
$601,310.93
Amt Left:
15.56%
$529,453.48
Delta:
-6.91%
-$254,207.79
$3,960,161.83
Over/Under Est:
18.88%
$628,805.26
Amt Left:
16.37%
$556,947.81
Delta:
-0.70%
-$27,494.33
$4,044,922.50
Over/Under Est:
21.42%
$713,565.93
Amt Left:
18.86%
$641,708.48
Delta:
-2.14%
-$84,760.67
$4,553,977.12
Over/Under Est:
36.7%
$1,222,620.55
Amt Left:
33.81%
$1,150,763.10
Delta:
-12.59%
-$509,054.62
$4,869,670.80
Over/Under Est:
46.18%
$1,538,314.23
Amt Left:
43.09%
$1,466,456.78
Delta:
-6.93%
-$315,693.68
$5,374,970.65
Over/Under Est:
61.34%
$2,043,614.08
Amt Left:
57.94%
$1,971,756.63
Delta:
-10.38%
-$505,299.85
$6,005,898.21
Over/Under Est:
80.28%
$2,674,541.64
Amt Left:
76.48%
$2,602,684.19
Delta:
-11.74%
-$630,927.56
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $70,543.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $66,009.75 |
| Total: | $136,552.75 |