MOORE US 87 (0066-05-066)

Items: 71

County: MOORE
Length: N/A
Highway: US 87
District: AMARILLO
Control Number: 0066-05-066
DBE Goal: N/A
Project: C 66-5-66
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $12,476,002.93
Date: 04/04/2018 (8 years ago)
Contract Number: N/A
Type: THICK OVERLAY,PAV REPAIR,SIGNS,BMGF,HSIP IMPROVE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$12,476,002.93
$11,242,986.20
Over/Under Est: -9.88% -$1,233,016.73
$11,284,176.06
Over/Under Est: -9.55% -$1,191,826.87
Amt Left: 0.37% $41,189.86
$11,347,786.75
Over/Under Est: -9.04% -$1,128,216.18
Amt Left: 0.93% $104,800.55
Delta: -0.56% -$63,610.69
$11,366,231.73
Over/Under Est: -8.9% -$1,109,771.20
Amt Left: 1.1% $123,245.53
Delta: -0.16% -$18,444.98
Over/Under Est: -8.59% -$1,071,649.36
Amt Left: 1.44% $161,367.37
Delta: -0.34% -$38,121.84
$11,408,328.47
Over/Under Est: -8.56% -$1,067,674.46
Amt Left: 1.47% $165,342.27
Delta: -0.03% -$3,974.90

Bid Items & Bid Tabulations

71 Total 0 of 71
MOORE  |  US 87  |  AMARILLO  |  0066-05-066  |  04/04/2018  |  $12,476,002.93  |  C 66-5-66  |  THICK OVERLAY,PAV REPAIR,SIGNS,BMGF,...  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY CONTRACTORS, INC.
DUININCK, INC.
J. LEE MILLIGAN, INC.
GILVIN-TERRILL, LTD.
KIEWIT INFRASTRUCTURE SOUTH CO.
RK HALL, LLC
PREPARING ROW
AC 37.230 $630.000 $300.000 $202.010 $245.000 $250.000 $136.080 $197.670
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 160.000 $50.000 $50.000 $39.830 $43.000 $35.000 $74.700 $31.180
BACKFILL (TY A)
STA 1,622.270 $200.000 $150.000 $248.960 $151.000 $100.000 $84.450 $212.620
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 37.230 $540.000 $315.000 $324.830 $350.000 $350.000 $357.210 $330.750
EMULS ASPH (EROSN CONT)(MS-2)
GAL 11,266.000 $3.100 $2.500 $4.150 $2.600 $3.000 $3.240 $2.940
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
TON 101,437.000 $85.000 $90.630 $79.360 $81.100 $77.800 $76.000 $85.630
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 43,664.000 $26.000 $0.850 $24.050 $17.500 $25.000 $19.780 $20.120
PLANE ASPH CONC PAV(0" TO 2")
SY 2,250.000 $5.000 $2.500 $4.970 $3.100 $3.600 $2.700 $5.510
PLANE ASPH CONC PAV(0" TO 3")
SY 407.000 $5.000 $2.500 $5.840 $5.600 $3.700 $2.860 $12.600
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 351.000 $5.000 $2.500 $5.970 $6.350 $3.600 $2.620 $12.600
PLANE ASPH CONC PAV (2 1/2")
SY 380.000 $5.000 $2.500 $6.220 $6.200 $3.750 $3.160 $12.600
PLANE ASPH CONC PAV (0"- 2 1/2")
SY 27,953.000 $2.000 $2.500 $2.650 $1.600 $3.750 $3.020 $2.260
DRILL SHAFT (NON - REINFORCED) (12 IN)
LF 14.000 $200.000 $115.000 $118.590 $127.350 $150.000 $130.410 $120.750
DRILL SHAFT (SIGN MTS) (24 IN)
LF 48.000 $200.000 $134.000 $139.210 $149.500 $200.000 $153.090 $141.750
CLEANING AND SEALING EXISTING JOINTS
LF 720.000 $100.000 $34.300 $36.830 $55.350 $30.000 $38.900 $37.200
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 480.000 $20.000 $29.200 $43.270 $31.000 $30.000 $33.450 $32.750
RC PIPE (CL III)(24 IN)
LF 18.000 $200.000 $90.000 $154.680 $265.000 $300.000 $168.140 $231.950
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 2.000 $7,500.000 $10,000.000 $6,702.740 $6,000.000 $7,000.000 $9,412.510 $10,140.960
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $15,000.000 $10,000.000 $10,311.910 $6,500.000 $8,000.000 $7,655.740 $7,890.710
SET (TY I)(S= 4 FT)(HW= 7 FT)(4:1) (C)
EA 1.000 $15,000.000 $10,000.000 $12,889.880 $10,000.000 $16,500.000 $10,691.230 $12,073.710
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 3.000 $2,500.000 $2,000.000 $1,546.790 $4,900.000 $6,000.000 $2,689.590 $2,543.680
REMOV STR (SET)
EA 7.000 $300.000 $210.000 $515.600 $950.000 $800.000 $981.590 $1,946.730
MOBILIZATION
LS 1.000 $1,045,739.070 $350,000.000 $510,692.750 $890,000.000 $1,000,000.000 $1,174,261.580 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $6,000.000 $9,038.880 $20,282.580 $9,300.000 $22,000.000 $35,000.000 $9,490.820
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 500.000 $7.500 $4.000 $8.250 $8.550 $10.000 $7.450 $5.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $2.400 $0.500 $2.060 $2.100 $4.000 $2.020 $1.050
RUMBLE STRIPS (SHOULDER)
LF 290,000.000 $0.140 $0.200 $0.100 $0.100 $0.250 $0.110 $0.110
MTL W-BEAM GD FEN (STEEL POST)
LF 9,500.000 $25.000 $21.500 $22.170 $24.250 $21.500 $26.080 $24.150
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 25.000 $1,850.000 $1,450.000 $1,753.020 $2,000.000 $1,450.000 $2,154.600 $1,995.000
SHORT RADIUS
LF 400.000 $30.000 $22.000 $22.690 $28.000 $22.000 $30.050 $27.830
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 24.000 $1,200.000 $910.000 $938.380 $195.000 $910.000 $209.790 $194.250
REMOVE METAL BEAM GUARD FENCE
LF 11,050.000 $4.000 $1.750 $1.800 $2.650 $1.750 $2.840 $2.630
REMOVE TERMINAL ANCHOR SECTION
EA 24.000 $250.000 $150.000 $154.680 $265.000 $150.000 $283.500 $262.500
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 25.000 $250.000 $150.000 $154.680 $265.000 $150.000 $283.500 $262.500
GUARDRAIL END TREATMENT (INSTALL)
EA 39.000 $2,400.000 $2,140.000 $2,206.750 $2,740.000 $2,140.000 $2,948.400 $2,730.000
GUARDRAIL END TREATMENT (REMOVE)
EA 35.000 $275.000 $190.000 $195.930 $265.000 $190.000 $283.500 $262.500
ALUMINUM SIGNS (TY G)
SF 326.000 $27.000 $30.000 $24.750 $25.300 $25.000 $27.220 $25.200
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 84.000 $700.000 $4,400.000 $732.150 $748.000 $245.000 $805.140 $745.500
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 19.000 $860.000 $520.000 $809.480 $825.000 $250.000 $890.190 $824.250
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 11.000 $900.000 $655.000 $943.540 $965.000 $390.000 $1,037.610 $960.750
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 10.000 $1,100.000 $805.000 $1,072.440 $1,095.000 $425.000 $1,179.360 $1,092.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $1,200.000 $795.000 $1,082.750 $1,100.000 $425.000 $1,190.700 $1,102.500
REMOVE SM RD SN SUP&AM
EA 128.000 $110.000 $70.000 $103.120 $105.000 $35.000 $113.400 $105.000
INSTALL LRSS (STRUCT STEEL)
LB 1,910.000 $6.000 $5.000 $5.160 $5.250 $10.000 $5.670 $5.250
REMOVE LRSA
EA 6.000 $550.000 $600.000 $876.510 $896.000 $1,150.000 $963.900 $892.500
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 252.000 $150.000 $55.000 $56.720 $142.250 $55.000 $153.090 $141.750
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 23.000 $20.000 $18.000 $18.560 $19.000 $18.000 $20.410 $18.900
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 113.000 $25.000 $17.000 $17.530 $19.000 $17.000 $20.410 $18.900
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 8.000 $25.000 $19.000 $19.590 $19.000 $19.000 $20.410 $18.900
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 220.000 $125.000 $57.000 $58.780 $142.250 $57.000 $153.090 $141.750
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 23.000 $20.000 $17.000 $17.530 $19.000 $17.000 $20.410 $18.900
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
EA 49.000 $25.000 $18.000 $18.560 $19.000 $18.000 $20.410 $18.900
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 196.000 $120.000 $58.000 $59.810 $142.250 $58.000 $153.090 $141.750
REMOVE DELIN & OBJECT MARKER ASSMS
EA 984.000 $12.000 $1.000 $1.030 $10.550 $1.000 $11.340 $10.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 113.000 $30.000 $19.500 $20.110 $38.000 $19.500 $40.820 $37.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $30.000 $20.000 $20.620 $38.000 $20.000 $40.820 $37.800
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 49.000 $25.000 $19.000 $19.590 $38.000 $19.000 $40.820 $37.800
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 2,050.000 $0.250 $1.000 $1.030 $1.050 $1.000 $1.130 $1.050
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,160.000 $0.250 $1.000 $1.030 $1.050 $1.000 $1.130 $1.050
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,050.000 $0.250 $1.000 $1.030 $1.050 $1.000 $1.130 $1.050
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 12,282.000 $0.900 $0.500 $1.030 $1.050 $1.000 $1.700 $0.810
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 10,705.000 $0.650 $0.520 $0.540 $0.550 $0.520 $0.590 $0.550
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 255.000 $2.000 $2.500 $2.580 $2.630 $2.500 $2.840 $2.630
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 867.000 $7.000 $5.000 $5.160 $5.270 $5.000 $5.670 $5.250
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 2.000 $115.000 $95.000 $97.960 $100.000 $95.000 $107.730 $99.750
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 700.000 $30.000 $12.000 $12.370 $12.640 $12.000 $13.610 $12.600
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 40,862.000 $0.370 $0.260 $0.270 $0.270 $0.260 $0.290 $0.270
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 167,684.000 $0.370 $0.260 $0.270 $0.270 $0.260 $0.290 $0.270
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 165,657.000 $0.370 $0.260 $0.270 $0.270 $0.260 $0.290 $0.270
REFL PAV MRKR TY II-C-R
EA 2,048.000 $2.500 $3.000 $3.090 $3.160 $3.000 $3.400 $3.150
TMA (STATIONARY)
EA 2.000 $12,000.000 $30,000.000 $41,247.620 $12,000.000 $20,000.000 $16,895.960 $37,606.470
Totals: $12,476,002.930 $11,242,986.200 $11,284,176.072 $11,347,786.750 $11,366,231.730 $11,404,353.588 $11,408,328.484