MOORE US 287 (0066-04-081)
Items: 70
County: MOORE
Length: 0.2750 MILES
Highway: US 287
District: AMARILLO
Control Number: 0066-04-081
DBE Goal: 6.5%
Project: BR 2025(617)
Guaranty: $84,000.00
Time: 161 WORKING DAYS
Engineer's Estimate: $4,198,524.50
Date: 04/04/2025 (1 year ago)
Contract Number: 4253216
Type: BRIDGE MAINTENANCE
Project ID: A00197805
Contract Type: Federal
Project Description: REMOVE ACP, HYDRODEMO 1", CONCRETE OVERLAY,INSTALL HEADER JOINT, REMOVE AND REPLACE BRIDGE RAIL, SUBSTRUCTURE SPALL REPAIR, RELOCATE BACKWALLS, REMOVE AND REPLACE APPROACH SLABS, EROSION MITIGATION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
MOORE US 287 (0066-04-081)
Project Name: N/A
Project: BR 2025(617)
Length: 0.0890 MILES
Project Type: CONSTRUCTION
Limits From: AT BNSF RR
Limits To: .
Project Description: REMOVE ACP, HYDRODEMO 1", CONCRETE OVERLAY,INSTALL HEADER JOINT, REMOVE AND REPLACE BRIDGE RAIL, SUBSTRUCTURE SPALL REPAIR, RELOCATE BACKWALLS, REMOVE AND REPLACE APPROACH SLABS, EROSION MITIGATION
MOORE US 287 (0066-04-082)
Project Name: US 287 SB/FM 281 & RR BRG FY 25 BMIP
Project: BR 2025(617)
Length: 0.0890 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: AT FM 281 & RR
Limits To: .
Project Description: REMOVE ACP, HYDRODEMO 1", CONCRETE OVERLAY, INSTALL HEADER JOINT, REMOVE AND REPLACE BRIDGE RAIL, SUBSTRUCTURE SPALL REPAIR, RELOCATE BACKWALLS, REMOVE AND REPLACE APPROACH SLABS, EROSION MITIGATION
GRAY SL 171 (2403-01-013)
Project Name: SL 171/BNSF RR BRG FY 25 BMIP
Project: BR 2025(777)
Length: 0.0970 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: AT BNSF RR
Limits To: .
Project Description: REMOVE ACP, HYDRODEMO 1", CONCRETE OVERLAY, HEADER JOINT REPLACEMENT, REMOVE AND REPLACE RAIL, FULL-DEPTH OVERHANG REPAIR, RELOCATE BACKWALLS, REMOVE AND REPLACE APPROACH SLABS, EROSION MITIGATION
Informational
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,198,524.50 | |||
| $3,547,551.90 |
-15.5%
-$650,972.60
|
|||
| $3,648,092.40 |
-13.11%
-$550,432.10
|
2.83%
$100,540.50
|
||
| $4,037,046.00 |
-3.85%
-$161,478.50
|
13.8%
$489,494.10
|
-10.66%
-$388,953.60
|
|
| $4,481,822.30 |
6.75%
$283,297.80
|
26.34%
$934,270.40
|
-11.02%
-$444,776.30
|
|
| $5,552,691.02 |
32.25%
$1,354,166.52
|
56.52%
$2,005,139.12
|
-23.89%
-$1,070,868.72
|
E
Engineer's Estimate
$4,198,524.50
1
Awarded
$3,547,551.90
Over/Under Est:
-15.5%
-$650,972.60
$3,648,092.40
Over/Under Est:
-13.11%
-$550,432.10
Amt Left:
2.83%
$100,540.50
$4,037,046.00
Over/Under Est:
-3.85%
-$161,478.50
Amt Left:
13.8%
$489,494.10
Delta:
-10.66%
-$388,953.60
$4,481,822.30
Over/Under Est:
6.75%
$283,297.80
Amt Left:
26.34%
$934,270.40
Delta:
-11.02%
-$444,776.30
$5,552,691.02
Over/Under Est:
32.25%
$1,354,166.52
Amt Left:
56.52%
$2,005,139.12
Delta:
-23.89%
-$1,070,868.72
| Subcontractor | Percentage | Amount |
|---|---|---|
| ONE WAY CONCRETE CONSTRUCTION, LLC | 34.88% | $1,328,271.28 |
| HYDRO TECHNOLOGIES, INC. | 5.25% | $199,926.15 |
| 1 PRIORITY ENVIRONMENTAL SERVICES, LLC | 5.16% | $196,498.85 |
| TRP CONSTRUCTION GROUP, LLC | 3.14% | $119,574.88 |
| TRUMBLE CRANE & RIGGING | 1.48% | $56,360.13 |
| DUSTROL, INC. | 1.28% | $48,743.90 |
| TEXOP CONSTRUCTION | 1.14% | $43,412.54 |
| BARRICADES UNLIMITED | 0.48% | $18,278.96 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 0.29% | $11,043.54 |
| Total: | 53.10% | $2,022,110.23 |
Bid Items & Bid Tabulations
70
Total
0 of 70
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) | $115,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,000.00 |
| Total: | $129,000.00 |