Items: 57

County: MONTGOMERY
Length: N/A
Highway: IH0045
District: HOUSTON
Control Number: 6388-49-001
DBE Goal: N/A
Project: RMC - 638849001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $439,291.00
Date: 02/03/2022 (4 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$439,291.00
$437,375.50
Over/Under Est: -0.44% -$1,915.50
Over/Under Est: 8.91% $39,129.00
Amt Left: 9.38% $41,044.50
Over/Under Est: 14.66% $64,391.00
Amt Left: 15.16% $66,306.50
Delta: -5.28% -$25,262.00
Over/Under Est: 30.72% $134,960.00
Amt Left: 31.29% $136,875.50
Delta: -14.01% -$70,569.00

Bid Items & Bid Tabulations

57 Total 0 of 57
MONTGOMERY  |  IH0045  |  HOUSTON  |  6388-49-001  |  02/03/2022  |  $439,291.00  |  RMC - 638849001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RHINO EQUITY, LLC
S6 INTERSTATE SERVICES
ROY JORGENSEN ASSOCIATES, INC.
ISI CONTRACTING, INC.
REMOVING CONCRETE(MOW STRIP)
LF 50.000 $9.800 $9.800 $12.000 $10.000 $7.000
BACKFILL TY A
CY 25.000 $50.000 $40.000 $200.000 $85.000 $75.000
RIPRAP (MOW STRIP)(4 IN)
CY 5.000 $440.000 $440.000 $450.000 $450.000 $800.000
MOBILIZATION (CALLOUT)
EA 26.000 $1.000 $1.000 $150.000 $100.000 $500.000
MOBILIZATION (EMERGENCY)
EA 6.000 $1.000 $200.000 $200.000 $300.000 $1,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 25.000 $20.500 $20.500 $20.000 $24.000 $45.000
MTL W-BEAM GD FEN (STEEL POST)
LF 25.000 $23.000 $23.000 $30.000 $32.000 $60.000
TERMINAL ANCHOR SECTION
EA 1.000 $500.000 $1.000 $100.000 $1.000 $1.000
SHORT RADIUS
LF 125.000 $32.000 $32.000 $25.000 $50.000 $70.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,200.000 $1,200.000 $900.000 $2,000.000 $2,500.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 150.000 $19.800 $20.000 $21.000 $30.000 $30.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $250.000 $500.000 $180.000 $500.000 $500.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $250.000 $500.000 $200.000 $1.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,450.000 $2,400.000 $3,000.000 $4,200.000 $3,200.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 1.000 $350.000 $250.000 $200.000 $250.000 $250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $350.000 $1.000 $300.000 $250.000 $200.000
CRASH CUSH ATTEN (DES SOURCE)
EA 1.000 $480.000 $2,900.000 $1,500.000 $2,500.000 $2,100.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $480.000 $480.000 $1,000.000 $2,500.000 $1,000.000
CRASH CUSH ATTEN (STKPL)
EA 1.000 $480.000 $480.000 $1,000.000 $2,500.000 $1,500.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $2,500.000 $1,000.000 $2,500.000 $1,000.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $14,850.000 $15,000.000 $16,000.000 $15,000.000 $25,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 500.000 $10.000 $3.000 $11.000 $6.000 $15.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 150.000 $15.000 $5.000 $6.000 $20.000 $15.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 3,000.000 $15.500 $24.500 $21.000 $16.500 $23.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 50.000 $19.500 $20.000 $100.000 $20.000 $20.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 15.000 $19.500 $20.000 $22.000 $35.000 $50.000
RAISE RAIL ELEMENT
LF 300.000 $8.500 $7.000 $6.000 $10.000 $10.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 50.000 $45.000 $35.000 $40.000 $55.000 $45.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 200.000 $40.000 $40.000 $46.000 $50.000 $60.000
REALIGN POSTS
EA 60.000 $2.000 $5.000 $18.000 $10.000 $5.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 3,000.000 $23.100 $30.000 $28.000 $25.000 $24.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 300.000 $70.000 $70.000 $66.000 $50.000 $50.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 20.000 $3,780.000 $2,700.000 $2,600.000 $3,250.000 $3,100.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 40.000 $1,100.000 $900.000 $900.000 $1,000.000 $1,100.000
REM & RESET SGT IMPACT HEAD
EA 40.000 $200.000 $300.000 $120.000 $150.000 $25.000
REPLACE SGT CABLE ASSEMBLY
EA 40.000 $75.000 $75.000 $46.000 $80.000 $95.000
REPLACE SGT CABLE ANCHOR
EA 40.000 $75.000 $75.000 $60.000 $75.000 $60.000
REPLACE SGT STRUT
EA 40.000 $75.000 $75.000 $90.000 $55.000 $60.000
REPLACE SGT OBJECT MARKER
EA 40.000 $20.000 $20.000 $20.000 $22.000 $25.000
REM & REPLACE BLOCKOUTS (FURNISHED)
EA 100.000 $5.000 $5.000 $8.000 $10.000 $6.000
REPLACE POSTS (TL-4)
EA 60.000 $129.000 $120.000 $110.000 $150.000 $150.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 15.000 $125.000 $125.000 $95.000 $150.000 $250.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 10.000 $93.000 $1.000 $50.000 $100.000 $50.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 10.000 $1,100.000 $800.000 $1,100.000 $1,250.000 $1,000.000
REPLACE CABLE (TL-4)
LF 2,500.000 $1.000 $2.000 $2.000 $2.000 $3.000
CHECK / RE-TENSION CABLE
EA 10.000 $190.000 $150.000 $225.000 $250.000 $250.000
REPLACE POST HARDWARE (TL-4)
EA 40.000 $7.350 $7.000 $5.000 $25.000 $35.000
REMOVE AND REPLACE (SMTC) (N)
EA 1.000 $15,250.000 $13,000.000 $9,800.000 $24,500.000 $25,000.000
REPAIR (SMTC) (N)
EA 5.000 $1,700.000 $2,000.000 $1,850.000 $2,000.000 $750.000
REMOVE AND REPLACE (SMTC) (W)
EA 1.000 $21,000.000 $15,000.000 $15,000.000 $40,000.000 $33,000.000
REPAIR (SMTC) (W)
EA 1.000 $1,900.000 $1,200.000 $3,200.000 $3,500.000 $1,000.000
REMOVE AND REPLACE TAU II (W)
EA 1.000 $19,000.000 $14,000.000 $20,000.000 $30,000.000 $30,000.000
REPAIR (TAU)(II)(W)(BAY)
EA 1.000 $495.000 $495.000 $2,200.000 $1,500.000 $500.000
REMOVE AND REPLACE (TAU)(MASH)(N)
EA 1.000 $13,000.000 $8,000.000 $25,000.000 $19,500.000 $25,000.000
REPAIR (TAU)(MASH)(N)
EA 1.000 $950.000 $950.000 $2,200.000 $3,000.000 $2,000.000
REPAIR (TAU)(MASH)(N)(BAY)
EA 1.000 $500.000 $500.000 $90.000 $1,500.000 $500.000
TMA (STATIONARY)
DAY 150.000 $1.000 $1.000 $150.000 $1.000 $250.000
Totals: $439,291.000 $437,375.500 $478,420.000 $503,682.000 $574,251.000