MONTGOMERY IH0069 (6308-71-001)

Items: 41

County: MONTGOMERY
Length: N/A
Highway: IH0069
District: HOUSTON
Control Number: 6308-71-001
DBE Goal: N/A
Project: RMC - 630871001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $326,015.00
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: GUARDRAIL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$326,015.00
$319,525.00
Over/Under Est: -1.99% -$6,490.00

Bid Items & Bid Tabulations

41 Total 0 of 41
MONTGOMERY  |  IH0069  |  HOUSTON  |  6308-71-001  |  03/07/2017  |  $326,015.00  |  RMC - 630871001  |  GUARDRAIL REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
STRUCT EXCAV
CY 50.000 $25.000 $25.000
CONC STR REPR(REMOV AND REPL WINGWALL)
CY 20.000 $80.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 20.000 $160.000 $500.000
MOBILIZATION (CALLOUT)
EA 26.000 $250.000 $250.000
MOBILIZATION (EMERGENCY)
EA 1.000 $1,500.000 $1,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $25.000 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $25.000 $27.000
TERMINAL ANCHOR SECTION
EA 16.000 $30.000 $1.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $1,900.000 $2,500.000
SHORT RADIUS
LF 300.000 $30.000 $40.000
REMOVE METAL BEAM GUARD FENCE
LF 150.000 $35.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $75.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,600.000 $2,900.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 3.000 $600.000 $850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $250.000 $200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,000.000 $2,000.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $600.000 $500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 503.000 $20.000 $10.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 165.000 $15.000 $10.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,000.000 $20.000 $16.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 150.000 $10.000 $5.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 5.000 $10.000 $25.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 200.000 $42.000 $40.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 200.000 $42.000 $45.000
REALIGN POSTS
EA 50.000 $10.000 $8.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 3,000.000 $18.000 $19.250
REPLACE SINGLE GDRAIL TERMINAL POST
EA 300.000 $46.000 $45.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 50.000 $10.000 $1.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 2.000 $2,900.000 $2,900.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 40.000 $915.000 $950.000
REM & RESET SGT IMPACT HEAD
EA 100.000 $120.000 $100.000
REPLACE SGT CABLE ASSEMBLY
EA 40.000 $80.000 $95.000
REPLACE SGT CABLE ANCHOR
EA 40.000 $80.000 $90.000
REPLACE SGT STRUT
EA 40.000 $75.000 $75.000
REPLACE SGT OBJECT MARKER
EA 40.000 $25.000 $20.000
REM & REPLACE BLOCKOUTS (FURNISHED)
EA 100.000 $5.000 $5.000
REPAIR REACT (N) (MISC HARDWARE)
EA 2.000 $1,050.000 $1,200.000
REPAIR REACT (N) (FRONT SECTION)
EA 2.000 $450.000 $200.000
REPAIR REACT (N) (CYLINDERS)
EA 4.000 $2,500.000 $2,700.000
REPAIR (QUAD) (N) (BAY)
EA 4.000 $1,100.000 $1,500.000
REPAIR (QUAD) (W) (BAY)
EA 2.000 $1,900.000 $2,000.000
Totals: $326,015.000 $319,525.000