MONTGOMERY SH 99 (3510-07-015)

Items: 42

County: MONTGOMERY
Length: N/A
Highway: SH 99
District: HOUSTON
Control Number: 3510-07-015
DBE Goal: 0.0%
Project: C 3510-7-15
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $11,693,364.62
Date: 05/02/2024 (2 years ago)
Contract Number: N/A
Type: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$11,693,364.62
Over/Under Est: 6.13% $716,506.01
Subcontractor Percentage Amount
XTREME PRO CLEANING LLC 17.16% $2,139,417.96
R & A DIRECTIONAL BORING 0.07% $8,727.23
Total: 17.23% $2,148,145.19

Bid Items & Bid Tabulations

42 Total 0 of 42
MONTGOMERY  |  SH 99  |  HOUSTON  |  3510-07-015  |  05/02/2024  |  $11,693,364.62  |  C 3510-7-15  |  LANDSCAPE DEVELOPMENT  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
EXCAVATION (SPECIAL)
CY 18,236.000 $65.000 $21.299
FURNISHING AND PLACING TOPSOIL
CY 11,748.000 $27.000 $42.560
EROSION CONTROL COMPOST
CY 40,212.000 $21.000 $21.760
GENERAL USE COMPOST
CY 8,575.000 $25.000 $24.295
BLOCK SODDING
SY 360,117.000 $4.000 $4.512
STRAW OR HAY MULCH
SY 648,794.000 $0.180 $0.447
BROADCAST SEED (PERM)(SPECIAL MIX)
SY 648,794.000 $0.350 $0.234
FERTILIZER
AC 208.160 $1,250.000 $1,961.632
VEGETATIVE WATERING
MG 25,014.000 $36.000 $36.513
IRRIGATION SYSTEM (TY I)
LS 1.000 $90,000.000 $316,666.667
PLANT MATERIAL (3-GAL)
EA 24,926.000 $20.000 $21.932
PLANT MATERIAL (15 GAL) (TREE)
EA 1,023.000 $135.000 $130.336
PLANT MATERIAL (30 GAL) (TREE)
EA 415.000 $275.000 $220.884
PLANT MATERIAL (45 GAL) (TREE)
EA 65.000 $400.000 $474.359
PLANT MATERIAL (3 GAL) (SHRUB)
EA 766.000 $21.000 $19.147
PLANT BED PREP (TYPE II)
SY 153,770.000 $0.350 $0.130
PLANT MAINTENANCE
MO 18.000 $27,000.000 $17,592.593
PLANT MAINTENANCE
CYC 7.000 $31,000.000 $65,476.190
MOBILIZATION
LS 1.000 $1,058,397.000 $619,700.039
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $4,250.000 $2,222.222
BULLDOZER WORK (EROSION & SEDMT CONT)
HR 2,450.000 $175.000 $66.667
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,000.000 $4.500 $3.167
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,000.000 $1.500 $0.333
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 20,000.000 $4.000 $3.042
BIODEG EROSN CONT LOGS (REMOVE)
LF 20,000.000 $1.000 $0.267
CONDT (PVC) (SCH 40) (4") (BORE)
LF 347.000 $50.000 $38.305
STORM SEWER CLEANING (ALL SIZES)
LF 245,768.000 $3.500 $7.353
STORM SEWER CLEAN (BOX CULV)(ALL SIZES)
LF 158,998.000 $5.500 $7.862
LANDSCAPE SOIL AMENDMENT (TYPE I)
SY 153,770.000 $0.150 $0.163
LANDSCAPE SOIL AMENDMENT (TYPE II)
SY 153,770.000 $0.200 $0.141
LANDSCAPE SOIL AMENDMENT (TYPE III)
SY 26,429.000 $1.500 $1.009
LANDSCAPE SOIL AMENDMENT (TYPE IV)
SY 142,121.000 $0.300 $0.305
LANDSCAPE SOIL AMENDMENT (TYPE V)
SY 27,195.000 $2.000 $2.329
LANDSCAPE TREATMENT(TY 1)
EA 144.000 $1,350.000 $1,967.593
LANDSCAPE TREATMENT(TY 2)
EA 161.000 $850.000 $1,086.957
LANDSCAPE TREATMENT(TY 3)
EA 1.000 $35,000.000 $73,333.333
LANDSCAPE TREATMENT(TY 4)
EA 104.000 $1,350.000 $336.538
LANDSCAPE TREATMENT (TY 5)
EA 1.000 $15,000.000 $20,000.000
LANDSCAPE TREATMENT (TY 6)
EA 1.000 $15,000.000 $62,500.000
LANDSCAPE TREATMENT (TY 8)
EA 1.000 $250,000.000 $93,333.333
TMA (STATIONARY)
DAY 120.000 $250.000 $895.833
TMA (MOBILE OPERATION)
DAY 120.000 $750.000 $912.500
Totals: $11,693,364.620 $12,409,870.750