Show Job Controls
Bid Cobra

MONTGOMERY FM 2854 (2744-01-037)

Items: 12

County: MONTGOMERY
Length: 1.5700 MILES
Highway: FM 2854
District: HOUSTON
Control Number: 2744-01-037
DBE Goal: 0.0%
Project: STP 2B25(022)HES
Guaranty: $13,000.00
Time: 52 WORKING DAYS
Engineer's Estimate: $667,613.00
Date: 09/04/2025 (9 months ago)
Contract Number: 9253030
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193463
Contract Type: Federal
Project Description: FIBER INSTALLATION TO CONNECT TRAFFIC SIGNALS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$667,613.00
$636,099.25
Over/Under Est: -4.72% -$31,513.75
$642,269.97
Over/Under Est: -3.8% -$25,343.03
Amt Left: 0.97% $6,170.72
Over/Under Est: 7.79% $52,032.47
Amt Left: 13.13% $83,546.22
Delta: -12.05% -$77,375.50
$775,901.19
Over/Under Est: 16.22% $108,288.19
Amt Left: 21.98% $139,801.94
Delta: -7.82% -$56,255.72
Over/Under Est: 21.23% $141,715.75
Amt Left: 27.23% $173,229.50
Delta: -4.31% -$33,427.56
Over/Under Est: 31.2% $208,262.00
Amt Left: 37.69% $239,775.75
Delta: -8.22% -$66,546.25
$968,950.75
Over/Under Est: 45.14% $301,337.75
Amt Left: 52.33% $332,851.50
Delta: -10.63% -$93,075.75
Over/Under Est: 70.73% $472,232.00
Amt Left: 79.19% $503,745.75
Delta: -17.64% -$170,894.25

Bid Items & Bid Tabulations

12 Total 0 of 12
MONTGOMERY  |  FM 2854  |  HOUSTON  |  2744-01-037  |  09/04/2025  |  $667,613.00  |  STP 2B25(022)HES  |  HAZARD ELIM & SAFETY  |  52 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THIRD COAST SERVICES LLC
CREACOM, INC.
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SICE, INC.
LIGHT IT UP ELECTRIC
FLORIDA TRAFFIC CONTROL DEVICES, INC.
TRAF-TEX, INC.
VACA UNDERGROUND UTILITIES INC
MOBILIZATION
LS 1.000 $45,000.000 $63,609.920 $55,000.000 $20,000.000 $72,350.000 $80,000.000 $50,000.500 $62,652.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,400.000 $1,935.000 $5,221.040 $1,762.000 $5,763.000 $5,000.000 $5,100.000 $2,703.000 $2,500.000
TMA (STATIONARY)
DAY 41.000 $300.000 $397.730 $595.310 $250.000 $310.000 $350.000 $171.000 $476.000 $500.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 2,945.000 $16.900 $14.510 $8.090 $17.820 $20.980 $32.000 $19.000 $28.320 $30.000
CONDT (PVC) (SCH 80) (2") (CONC ENCSE)
LF 16,885.000 $18.500 $15.910 $15.400 $21.110 $23.164 $19.000 $29.200 $34.000 $35.000
ELEC CONDR (NO.14) INSULATED
LF 19,875.000 $1.000 $1.250 $0.420 $1.440 $0.787 $1.250 $1.500 $1.350 $2.000
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 31.000 $4,050.000 $3,978.750 $5,280.810 $4,075.000 $4,544.000 $4,500.000 $4,377.000 $4,076.000 $6,500.000
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 990.000 $1.900 $3.090 $9.660 $7.510 $1.612 $2.000 $4.300 $4.700 $3.000
FIBER OPTIC CBL (SINGLE-MODE)(36 FIBER)
LF 20,320.000 $2.300 $1.870 $2.090 $3.000 $1.792 $4.000 $2.450 $1.820 $5.000
FO SPLICE ENCLOSURE (TYPE 2)
EA 10.000 $1,760.000 $2,615.360 $1,383.220 $2,006.270 $728.000 $1,200.000 $965.000 $1,291.000 $1,500.000
FIBER OPTIC FUSION SPLICE
EA 96.000 $93.000 $68.950 $16.440 $103.970 $49.000 $45.000 $56.000 $50.450 $75.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 10.000 $1,800.000 $1,505.480 $1,862.880 $2,004.150 $838.000 $1,600.000 $1,490.000 $590.250 $1,200.000
Totals: $667,613.000 $636,099.250 $642,269.970 $719,645.470 $775,901.185 $809,328.750 $875,875.000 $968,950.750 $1,139,845.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $4,500.00
CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $14,500.00