MONTGOMERY FM 1314 (1986-01-065)

Items: 71

County: MONTGOMERY
Length: N/A
Highway: FM 1314
District: HOUSTON
Control Number: 1986-01-065
DBE Goal: N/A
Project: CC 1986-1-65
Guaranty: N/A
Time: 196 WORKING DAYS
Engineer's Estimate: $3,429,850.60
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: CONSTRUCT DRAINAGE CULVERTS&REPLACE CONCRETE PVMNT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (13)
E
Engineer's Estimate
$3,429,850.60
$3,360,866.55
Over/Under Est: -2.01% -$68,984.05
Over/Under Est: 1.93% $66,120.30
Amt Left: 4.02% $135,104.35
Over/Under Est: 7.13% $244,643.93
Amt Left: 9.33% $313,627.98
Delta: -5.11% -$178,523.63
Over/Under Est: 8.05% $276,227.38
Amt Left: 10.27% $345,211.43
Delta: -0.86% -$31,583.45
Over/Under Est: 9.29% $318,737.90
Amt Left: 11.54% $387,721.95
Delta: -1.15% -$42,510.52
Over/Under Est: 12.56% $430,893.65
Amt Left: 14.87% $499,877.70
Delta: -2.99% -$112,155.75
$3,961,743.54
Over/Under Est: 15.51% $531,892.94
Amt Left: 17.88% $600,876.99
Delta: -2.62% -$100,999.29
Over/Under Est: 22.2% $761,434.35
Amt Left: 24.71% $830,418.40
Delta: -5.79% -$229,541.41
Over/Under Est: 22.75% $780,221.87
Amt Left: 25.27% $849,205.92
Delta: -0.45% -$18,787.52
$4,310,307.10
Over/Under Est: 25.67% $880,456.50
Amt Left: 28.25% $949,440.55
Delta: -2.38% -$100,234.63
Over/Under Est: 27.79% $953,109.10
Amt Left: 30.41% $1,022,093.15
Delta: -1.69% -$72,652.60
$5,424,887.31
Over/Under Est: 58.17% $1,995,036.71
Amt Left: 61.41% $2,064,020.76
Delta: -23.77% -$1,041,927.61
$5,853,345.50
Over/Under Est: 70.66% $2,423,494.90
Amt Left: 74.16% $2,492,478.95
Delta: -7.90% -$428,458.19

Bid Items & Bid Tabulations

71 Total 0 of 71
MONTGOMERY  |  FM 1314  |  HOUSTON  |  1986-01-065  |  09/03/2020  |  $3,429,850.60  |  CC 1986-1-65  |  CONSTRUCT DRAINAGE CULVERTS&REPLACE...  |  196 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RAC INDUSTRIES, LLC
SER CONSTRUCTION PARTNERS, LLC
HARPER BROTHERS CONSTRUCTION LLC
JAMES CONSTRUCTION GROUP, L.L.C.
R CONSTRUCTION CIVIL, LLC
LINDSEY CONSTRUCTION, INC.
ISI CONTRACTING, INC.
STERLING DELAWARE HOLDING COMPANY, INC.
RAGLE CONSTRUCTION, INC.
NBG CONSTRUCTORS, INC.
MAIN LANE INDUSTRIES LTD.
TRIPLE B SERVICES LLP
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 22.000 $1,500.000 $3,500.000 $1,700.000 $500.000 $5,374.230 $1,100.000 $5,400.000 $1,000.000 $10,000.000 $18,000.000 $10,000.000 $15,000.000 $7,500.000 $15,000.000
REMOVING CONC (PAV)
SY 1,920.000 $10.000 $3.100 $6.000 $3.000 $6.540 $10.000 $9.100 $5.300 $3.600 $4.860 $10.000 $7.000 $5.000 $20.000
REMOVING STAB BASE AND ASPH PAV (7")
SY 2,014.000 $10.000 $2.900 $3.000 $3.000 $4.030 $3.000 $9.000 $4.600 $3.150 $1.000 $4.500 $6.000 $5.000 $20.000
EXCAVATION (ROADWAY)
CY 400.000 $15.000 $20.000 $14.000 $15.000 $16.670 $12.000 $34.000 $38.000 $16.000 $30.000 $12.000 $15.000 $14.000 $20.000
EXCAVATION (CHANNEL)
CY 3,000.000 $18.000 $20.000 $9.000 $15.000 $10.010 $15.000 $22.000 $16.000 $20.000 $15.000 $12.000 $15.000 $8.000 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 2,000.000 $15.000 $21.000 $9.000 $4.000 $4.390 $5.000 $26.000 $25.000 $17.000 $20.000 $5.000 $4.000 $19.000 $35.000
COMPOST MANUF TOPSOIL (4")
SY 12,000.000 $2.000 $1.100 $1.000 $0.880 $1.990 $1.000 $2.000 $1.000 $2.000 $0.800 $1.000 $1.000 $0.930 $8.000
BLOCK SODDING
SY 6,800.000 $5.000 $5.400 $4.600 $3.680 $4.000 $4.000 $5.000 $3.600 $3.350 $5.000 $4.200 $4.000 $3.840 $8.000
STRAW OR HAY MULCH
SY 16,020.000 $1.000 $0.610 $0.300 $0.440 $0.250 $0.200 $0.350 $0.180 $0.400 $0.400 $0.400 $0.200 $0.190 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 200.000 $0.250 $0.910 $2.100 $3.300 $1.000 $3.000 $0.160 $3.300 $3.000 $3.000 $3.000 $3.000 $3.490 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 3,700.000 $0.250 $0.490 $0.700 $1.100 $0.150 $0.200 $0.160 $0.250 $1.000 $1.000 $1.000 $0.250 $1.280 $1.000
BROADCAST SEED (PERM)(SPECIAL MIX)
SY 120.000 $0.250 $2.700 $2.100 $4.400 $1.000 $5.000 $0.200 $2.750 $4.000 $4.000 $4.000 $5.000 $5.820 $1.000
DRILL SEEDING (PERM)(WARM OR COOL)
SY 12,000.000 $0.200 $0.690 $0.700 $0.640 $0.220 $0.200 $0.160 $0.200 $0.580 $0.580 $0.600 $0.200 $0.190 $1.000
FERTILIZER
AC 5.000 $1,100.000 $1,400.000 $901.000 $965.870 $850.000 $900.000 $1,000.000 $940.000 $879.000 $879.000 $900.000 $900.000 $989.920 $2,500.000
VEGETATIVE WATERING
MG 600.000 $25.000 $34.000 $10.000 $25.000 $14.050 $15.000 $35.000 $14.000 $22.000 $5.000 $40.000 $15.000 $23.290 $50.000
LIME (HYDRATED LIME (DRY))
TON 38.000 $400.000 $180.000 $198.000 $177.000 $198.610 $200.000 $200.000 $178.000 $190.000 $187.000 $200.000 $175.000 $196.820 $200.000
LIME TRT (SUBGRADE)(6")
SY 2,012.000 $4.250 $7.300 $5.000 $10.000 $7.850 $6.000 $7.000 $5.000 $10.000 $9.000 $6.000 $8.000 $6.250 $12.000
CEM TRT(PLNT MX) (CL N)(TY E)(GR 4)(6")
SY 2,012.000 $8.000 $23.000 $20.000 $20.000 $11.080 $20.000 $16.000 $16.000 $18.000 $18.000 $20.000 $20.000 $19.000 $42.000
ASPHALT STAB BASE (GR 4)(PG 64)
TON 111.000 $90.000 $120.000 $85.000 $120.000 $349.440 $150.000 $195.000 $130.000 $120.000 $120.000 $125.000 $120.000 $150.000 $150.000
SALV, HAUL & STKPL RCL APH PV (0 TO 2")
SY 2,014.000 $5.000 $1.800 $6.000 $3.000 $0.100 $2.000 $5.000 $4.000 $1.750 $1.000 $2.000 $3.000 $2.200 $20.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 1,920.000 $75.000 $110.000 $50.000 $80.000 $73.900 $90.000 $80.000 $74.000 $95.000 $95.000 $70.000 $80.000 $85.000 $125.000
STRUCT EXCAV
CY 17,000.000 $7.000 $5.300 $0.100 $5.000 $7.790 $10.000 $10.200 $13.000 $16.000 $12.000 $10.000 $4.000 $9.500 $30.000
CEM STABIL BKFL
CY 900.000 $175.000 $34.000 $52.000 $35.000 $36.130 $30.000 $64.000 $40.000 $43.000 $40.000 $45.000 $35.000 $50.000 $350.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 35.000 $100.000 $34.000 $52.000 $35.000 $36.130 $30.000 $65.000 $40.000 $43.000 $40.000 $45.000 $35.000 $50.000 $350.000
TEMPORARY SPL SHORING
SF 6,506.000 $25.000 $45.000 $20.000 $25.000 $50.460 $20.000 $44.000 $5.000 $23.000 $23.000 $1.000 $25.000 $35.000 $45.000
RETAINING WALL (CAST - IN - PLACE)
SF 4,868.000 $150.000 $110.000 $200.000 $240.000 $215.330 $275.000 $160.250 $270.000 $285.000 $200.000 $320.000 $300.000 $560.000 $85.000
RIPRAP (CONC)(4 IN)
CY 35.000 $500.000 $450.000 $518.000 $600.000 $444.240 $550.000 $595.000 $400.000 $470.000 $500.000 $450.000 $550.000 $425.000 $650.000
RIPRAP (MOW STRIP)(4 IN)
CY 32.000 $550.000 $380.000 $450.000 $750.000 $578.230 $450.000 $510.000 $650.000 $580.000 $500.000 $550.000 $700.000 $570.000 $650.000
CONC BOX CULV (5 FT X 3 FT)
LF 192.000 $325.000 $500.000 $269.000 $330.000 $287.390 $270.000 $400.000 $320.000 $330.000 $350.000 $340.000 $450.000 $320.000 $650.000
CONC BOX CULV (12 FT X 10 FT)
LF 544.000 $1,500.000 $1,600.000 $2,150.200 $1,690.000 $1,430.030 $1,430.000 $1,706.000 $1,350.000 $1,350.000 $1,700.000 $1,600.000 $1,400.000 $1,450.000 $2,500.000
RC PIPE (CL III)(24 IN)
LF 96.000 $100.000 $78.000 $74.000 $95.000 $83.020 $50.000 $77.000 $83.000 $90.000 $90.000 $95.000 $120.000 $76.000 $105.000
RC PIPE (CL III)(42 IN)
LF 96.000 $200.000 $360.000 $140.000 $185.000 $144.190 $110.000 $180.000 $185.000 $165.000 $170.000 $160.000 $200.000 $170.000 $450.000
MANH (COMPL)(TY A)
EA 2.000 $4,500.000 $6,500.000 $6,752.000 $10,000.000 $5,710.220 $4,300.000 $6,000.000 $6,000.000 $8,500.000 $8,000.000 $4,000.000 $5,000.000 $9,200.000 $8,500.000
MANH (COMPL) (JUNCT BOX)(SPL W/RISER)
EA 2.000 $5,000.000 $10,600.000 $8,153.000 $18,000.000 $10,064.770 $12,000.000 $11,000.000 $10,500.000 $12,500.000 $14,000.000 $7,500.000 $10,000.000 $14,500.000 $16,500.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (P)
EA 2.000 $7,500.000 $4,500.000 $6,120.000 $12,000.000 $8,801.590 $7,000.000 $11,000.000 $11,600.000 $10,500.000 $13,000.000 $7,500.000 $10,000.000 $13,000.000 $15,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 1.000 $2,000.000 $1,200.000 $1,449.000 $3,000.000 $1,749.900 $1,200.000 $1,500.000 $1,600.000 $1,900.000 $2,500.000 $2,500.000 $1,500.000 $2,200.000 $2,500.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 1.000 $7,500.000 $6,600.000 $6,500.000 $11,000.000 $9,917.500 $9,000.000 $10,000.000 $9,700.000 $6,700.000 $12,000.000 $13,000.000 $4,500.000 $11,500.000 $16,500.000
MOBILIZATION
LS 1.000 $292,804.600 $317,800.000 $340,000.000 $220,000.000 $350,000.000 $300,000.000 $313,000.000 $370,000.000 $400,000.000 $410,000.000 $440,000.000 $400,000.000 $220,000.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $10,000.000 $3,800.000 $1,000.000 $1,700.000 $2,467.230 $4,500.000 $4,200.000 $1,000.000 $4,000.000 $15,000.000 $2,800.000 $23,000.000 $2,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 80.000 $35.000 $34.000 $36.000 $37.360 $25.000 $30.000 $32.000 $28.000 $34.000 $35.000 $40.000 $40.000 $44.000 $30.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 80.000 $75.000 $110.000 $74.000 $75.820 $55.000 $80.000 $60.000 $55.000 $69.000 $69.000 $75.000 $60.000 $140.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 160.000 $10.000 $20.000 $11.000 $10.920 $10.000 $6.000 $8.750 $9.000 $9.940 $9.940 $10.000 $10.000 $20.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,500.000 $3.000 $4.900 $1.600 $3.730 $4.000 $2.000 $3.750 $3.000 $4.000 $3.390 $4.000 $3.000 $6.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,500.000 $1.000 $1.100 $0.500 $1.100 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.500 $2.000
CONSTRUCTING DETOURS
SY 2,480.000 $75.000 $43.000 $49.000 $80.000 $76.000 $58.000 $76.000 $133.000 $50.000 $55.000 $80.000 $50.000 $68.000 $45.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,260.000 $10.000 $77.000 $30.000 $65.000 $15.180 $63.000 $59.000 $95.000 $16.000 $10.000 $27.000 $30.000 $85.000 $90.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 630.000 $5.000 $26.000 $3.700 $6.650 $12.330 $5.000 $8.500 $20.000 $4.000 $7.000 $10.000 $10.000 $8.000 $20.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,260.000 $10.000 $17.000 $7.900 $17.710 $8.020 $15.000 $15.000 $9.000 $9.000 $11.000 $15.000 $12.000 $15.000 $20.000
MTL W-BEAM GD FEN (TIM POST)
LF 400.000 $22.000 $22.000 $26.500 $15.000 $15.000 $16.000 $25.000 $20.000 $15.000 $20.500 $22.000 $15.000 $19.000 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,200.000 $1,400.000 $1,272.000 $1,170.000 $1,170.000 $1,200.000 $1,400.000 $1,250.000 $1,170.000 $1,053.000 $1,400.000 $1,500.000 $1,360.000 $1,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,000.000 $2,500.000 $2,650.000 $2,435.000 $2,435.000 $2,500.000 $3,200.000 $2,900.000 $2,435.000 $2,700.000 $2,500.000 $2,600.000 $2,800.000 $2,850.000
CRASH CUSH ATTEN (DES SOURCE)
EA 2.000 $15,000.000 $4,400.000 $1,734.000 $3,050.000 $3,050.000 $4,000.000 $5,300.000 $6,500.000 $3,050.000 $1,200.000 $4,000.000 $6,000.000 $3,500.000 $8,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $3,000.000 $1,500.000 $1,637.000 $3,050.000 $3,050.000 $3,000.000 $1,750.000 $1,800.000 $3,050.000 $1,600.000 $3,000.000 $3,000.000 $3,500.000 $5,000.000
CRASH CUSH ATTEN (STKPL)
EA 2.000 $1,000.000 $1,400.000 $1,231.000 $800.000 $800.000 $2,000.000 $1,900.000 $1,100.000 $800.000 $1,200.000 $2,000.000 $1,000.000 $1,100.000 $2,500.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 3,959.000 $1.000 $0.750 $1.300 $0.650 $0.650 $0.700 $0.750 $0.800 $0.750 $0.650 $0.700 $1.000 $0.850 $2.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 15,834.000 $1.000 $0.750 $1.300 $0.650 $0.650 $0.700 $0.750 $0.800 $0.750 $0.650 $0.700 $1.000 $0.800 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 15,834.000 $1.000 $0.750 $1.300 $0.650 $0.650 $0.700 $0.750 $0.800 $0.750 $0.650 $0.700 $1.000 $0.800 $1.000
REFL PAV MRKR TY II-A-A
EA 232.000 $5.000 $4.000 $6.400 $5.000 $5.000 $5.000 $5.500 $4.250 $4.000 $5.000 $5.200 $6.000 $5.400 $6.000
REFL PAV MRKR TY II-C-R
EA 118.000 $5.000 $4.000 $6.400 $5.000 $5.000 $5.000 $5.500 $4.250 $4.000 $5.000 $5.200 $6.000 $5.400 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 35,627.000 $1.000 $0.300 $0.300 $0.350 $0.350 $0.400 $0.400 $0.320 $0.300 $0.350 $0.400 $0.100 $0.400 $0.500
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 9,467.000 $1.250 $0.650 $0.800 $0.720 $0.720 $0.700 $0.800 $0.700 $0.650 $0.720 $0.800 $1.000 $0.900 $2.000
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 2,360.000 $1.250 $0.650 $0.800 $0.720 $0.720 $0.700 $0.800 $0.700 $0.650 $0.720 $0.800 $1.000 $0.900 $2.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 9,377.000 $1.250 $0.650 $0.900 $0.720 $0.720 $0.700 $0.800 $0.700 $0.650 $0.720 $0.800 $1.000 $0.900 $2.000
MULTIPOLYMER PAV MRK (Y)(6")(BRK)
LF 2,340.000 $1.250 $0.650 $0.900 $0.720 $0.720 $0.700 $0.800 $0.700 $0.650 $0.720 $0.800 $1.000 $0.900 $2.000
MULTIYPOLYMER PAV MRK (W) (ARROW)
EA 4.000 $200.000 $200.000 $97.500 $165.000 $165.000 $170.000 $175.000 $210.000 $200.000 $165.000 $165.000 $200.000 $220.000 $250.000
TMA (STATIONARY)
DAY 20.000 $300.000 $160.000 $260.600 $70.000 $400.940 $250.000 $220.000 $190.000 $100.000 $400.000 $150.000 $200.000 $320.000 $550.000
TMA (MOBILE OPERATION)
DAY 10.000 $300.000 $350.000 $260.600 $380.000 $694.750 $250.000 $260.000 $350.000 $200.000 $400.000 $300.000 $400.000 $88.000 $850.000
SANITARY SEWER (4IN) (PVC) (C900)
LF 478.000 $10.000 $26.000 $22.100 $35.000 $25.770 $35.000 $54.000 $38.000 $55.000 $90.000 $70.000 $100.000 $43.000 $85.000
MANHOLE (SAN SEWER) (4" DIA)
EA 2.000 $10,000.000 $2,700.000 $2,884.000 $7,000.000 $3,760.410 $4,200.000 $5,000.000 $5,650.000 $4,300.000 $6,500.000 $7,000.000 $5,000.000 $6,000.000 $8,500.000
ABANDON SANITARY SEWER (4 IN)
EA 452.000 $5.000 $8.000 $4.300 $10.000 $8.790 $6.000 $30.000 $25.000 $10.000 $7.000 $0.100 $5.000 $8.800 $500.000
REMOVE EXISTING MANHOLE(SANITARY SEWER)
EA 1.000 $2,000.000 $1,000.000 $283.600 $400.000 $459.780 $1,000.000 $1,650.000 $950.000 $600.000 $778.190 $1,500.000 $1,200.000 $100.000 $2,500.000
Totals: $3,429,850.600 $3,360,866.550 $3,495,970.900 $3,674,494.530 $3,706,077.980 $3,748,588.500 $3,860,744.250 $3,961,743.540 $4,191,284.950 $4,210,072.470 $4,310,307.100 $4,382,959.700 $5,424,887.310 $5,853,345.500